PPPL PRINCETON PLASMA
PHYSICS LABORATORY PROCEDURE No. ENG-060 Rev 1
Task Order Statement of Work Attachment 3
MCR-ENG-060,R1-005
JOB ORDER STATEMENT OF WORK
FOR
INDEFINITE DELIVERY INDEFINITE QUANTITY AGREEMENT
Title: Design, Procurement, Installation and Commissioning of Gas Delivery and Detection System for L130-L131 Quantum CVD Lab
CAT: A3
Revision: 0
Requisition No.: 427803
REQUIRED REVIEWS/APPROVAL:
PREPARED BY:_____________________________________________
Name: Phillip Egan
APPROVED BY:____________________________________________
Craig Shaw, Responsible Engineer
APPROVED BY:____________________________________________
Kenyon Petura, Facilities SME
PRINCETON PLASMA PHYSICS LABORATORY
P.O. BOX 451
PRINCETON, N.J. 08543
609-243-2000
Task Order Statement of Work Attachment 3
MCR-ENG-060,R1-005
RECORD OF CHANGES
Rev # Date Description of Changes
0 Initial Release
Task Order Statement of Work Attachment 3
MCR-ENG-060,R1-005
SCOPE OF WORK
The Subcontractor shall provide all materials, labor, supervision, equipment, and expertise required to complete the following Work:
▪ Develop and submit for approval a project schedule, which at a minimum contains design, procurement, construction, and commissioning activities. Lead times of all major equipment shall also be provided with this schedule.
▪ Coordinate with Princeton Technical Representative (PTR) to further define required performance parameters for the system. Develop Performance Parameter Summary and submit for review and approval by PPPL prior to specifying the system. Performance Parameter Summary shall define gases/mixtures used, operating pressures, flow rates, estimated usage, purification requirements, storage location and any other system performance requirements defined by the PTR or lab end user.
▪ Specify, furnish, install and commission a fully functional gas delivery and detection system as described in the attached Performance Specification and Concept Drawings as well as the Approved Performance Parameter Summary. Approved Performance Parameter Summary will be the governing document in the development of the project specifications. Provide Gas Delivery System Drawings and Specifications Signed and Sealed by a Licensed Engineer in the State of New Jersey and a commissioning plan for review and approval by PPPL.
▪ Facilitate weekly progress meetings with the PRT to provide progress updates during design, construction, and commissioning.
▪ Provide closeout document package including, but not limited to the following:
as-built construction drawings, operations and maintenance manuals, manufacturer, and installer warranties.
ATTACHMENT(S)
Attachment 1, Deliverables List Attachment 2, Performance Specification Attachment 3, Concept Drawings
REFERENCE(S)
“Parent” Statement of Work for IQID Subcontract
GENERAL REQUIREMENTS:
Task Order Statement of Work Attachment 3
MCR-ENG-060,R1-005
Upon receipt of an appropriate BOA Job Order, Subcontractor agrees to perform the Work required by this Job Order Statement of Work, maintaining full compliance with the referenced BOA Subcontract and any other documents included or referenced therein or elsewhere in this Job Order Statement of Work.
SPECIAL REQUIREMENTS:
Contractor shall comply with all PPPL site access and ES&H requirements (training, COVID testing, etc.)
Task Order Statement of Work Attachment 3
MCR-ENG-060,R1-005
Attachment 1 - Deliverables List
# Physical Deliverables Required When
Deliverable Is Required
Deliverable Received
1 Fully Functional Gas Delivery and Detection System Completion of Project
Exceptions:
# Document Deliverables Required
When Deliverable Is
Required
Deliverable format (paper, electronic etc.)
Storage Location for Deliverable
Deliverable Received (✔)
1 Performance Parameter Summary Prior to Design Electronic Project File (p drive)
2 System Drawings, Specifications and Commissioning Plan Prior to Construction
Electronic Project File (p drive)
3 As-Built Drawings, Commissioning Reports, Operation and Maintenance Manuals, Mfr. and Installation Warranty
Prior To Completion
Electronic Project File (p drive)
Exceptions:
Princeton Technical Representative:
(Sign-off and provide to the Operations Center when job is completed and deliverables are dispositioned and placed/filed in Operations Center (or other Project, Department or Division designated file center)
| 2022-08-05T14:14:04-0400 | |
| Kenyon Petura |
| 2022-08-05T14:31:10-0400 | |
| CS | |
| I have reviewed this document |
| 2022-08-08T12:53:59-0400 | |
| Phil Egan |