L079-0004_Special_Provisions.pdf

PDF 9 MB Posted

Attached to
B027-23 Oregon Road Bridge Replacement
Solicitation number
State Project No. L079-0004-Oregon Road Bridge No. 04184
Issued by
New Haven County, Connecticut

About this file

This Special Provisions document pertains to Connecticut Department of Transportation (CTDOT) Local Transportation Capital Improvement Program (LOTCIP) Project #L079-0004 for the replacement of the Oregon Road Bridge (Bridge No. 04184) over the Quinnipiac River in Meriden, Connecticut. The project scope includes bridge replacement, utility relocation (water, sanitary sewer, electric, and telecommunications), environmental compliance measures, traffic management, and associated site work. The special provisions detail numerous work items including excavation and reuse of channel bottom material, cofferdam and dewatering, temporary water handling systems, sediment control, joint and crack sealing, expansion joint systems, preformed joint seals, steel-laminated elastomeric bearings, and ultra-high-performance concrete installation. The contractor must perform at least 50 percent of the contract work with its own organization and maintain minimum traffic lane requirements: one 11-foot-wide lane in each direction during weekday peak hours (6:00-9:00 a.m. and 2:00-6:00 p.m.) and weekend hours (10:00 a.m.-6:00 p.m.). Construction sign requirements specify MDO-EXT-APA plywood or 0.125-gauge aluminum with blue letters and white background, mounted 7 feet above the road edge with 6-12 feet lateral offset.

The project incorporates significant environmental compliance requirements, particularly for protection of the State-listed wood turtle species (Glyptemys insculpta) present within project limits, mandating coordination with the District Environmental Coordinator and Office of Environmental Planning at least 10 days prior to construction commencement. During the turtle's active period (April 1-October 31), exclusionary fencing at least 20 inches tall must be installed and maintained, morning work-area surveys conducted, and staging/storage areas approved by the Office of Environmental Planning. The contractor must coordinate with the City of Meriden, Eversource Energy (electric), and Frontier Communications (telecommunications) at least 30 days prior to any work affecting their utilities. Specialized work items include asphaltic plug expansion joint systems, preformed joint seals from approved manufacturers (Silicoflex, V-Seal, B.E.J.S., or Wabo FS), and ultra-high-performance concrete meeting specific compressive strength (20 ksi at 28 days), direct tension cracking stress, shrinkage, and freeze-thaw resistance requirements. The contract establishes detailed material specifications, construction methods, quality control procedures, and testing requirements for all work, with payment typically made on unit price or lump-sum bases upon completion and engineer acceptance.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOTCIP #L079-0004

Replacement of Oregon Road Bridge (Bridge No. 04184)

Over Quinnipiac River – Meriden, CT

TABLE OF CONTENTS OF SPECIAL PROVISIONS

Note: This Table of Contents has been prepared for the convenience of those using this contract with the sole express purpose of locating quickly the information contained herein;

and no claims shall arise due to omissions, additions, deletions, etc., as this Table of

Contents shall not be considered part of the contract.

Notice To Contractor - Procurement of Materials

Notice To Contractor - LOTCIP Project Sign Requirements

Section 1.07 – Legal Relations and Responsibilities

Section 1.08 – Prosecution and Progress

Section 1.10 – Environmental Compliance

0100600A Construction Access

0202216A Excavation and Reuse of Existing Channel Bottom Material

0204001A Co7erdam and Dewatering

0204151A Handling Water

0219011A Sedimentation Control at Catch Basin

0406194A Joint and Crack Sealing of Bituminous Concrete Pavement

0406312A Gutter Line Sealing for Bridges

0520036A Asphaltic Plug Expansion Joint System

0520041A Preformed Joint Seal

0521021A Steel-Laminated Elastomeric Bearings

0601054A Ultra High-Performance Concrete

0601088A Concrete Form Liners

0602865A #5 Mechanical Couplers

0602867A #6 Mechanical Couplers

0602869A #8 Mechanical Couplers

0602872A #11 Mechanical Couplers

0603474A Metallizing Structural Steel (Site No. 1)

0686002.24A 24in. R.C. Pipe (Class V) 0' To 10' Deep

0707009A Membrane Waterproofing (Cold Liquid Elastomeric)

0714999A Monitoring Structures

LOTCIP #L079-0004

Replacement of Oregon Road Bridge (Bridge No. 04184)

Over Quinnipiac River – Meriden, CT

0728032A No. 6 Crushed Stone

0819002A Penetrating Sealer Protective Compound

0904051A 3 Tube Curb Mounted Bridge Rail

0950019A Turf Establishment – Lawn

0950043A Wetland Grass Establishment

0952051A Control and Removal of Invasive Vegetation

0969064A Construction Field O7ice Large

0971001A Maintenance & Protection of Tra7ic

0979005A Pedestrian Barricade

1020037A Temporary Lighting

1117111A Rectangular Rapid Flashing Beacon RRFB

1117115A Temporary Rectangular Rapid Flashing Beacon (RRFB) – Type B

1117116A Removal of Existing Flashing Beacon

1208931A Sign Face - Sheet Aluminum (Type IX Retroreflective Sheeting)

1208937A Sign Face - Sheet Aluminum (Type XI Retroreflective Sheeting)

1301771A Furnish and Install Pre-insulated 12” Ductile Iron Water Main on Bridge

1301861A Furnishing and Installing 12in Ductile Iron Pipe, Valves and Miscellaneous

Fittings

1301952A Steel Pipe Sleeve

1401246A 10” Ductile Iron Pipe (Sanitary Sewer)

1401662A Sanitary Manhole (4’ Dia.) 0’ to 10’ Deep

1401947A Remove Existing Pipe (Sanitary Sewer)

1403030A Doghouse Manhole (Sanitary Sewer)

1403501A Reset Manhole (Sanitary Sewer)

1403517A Remove Sanitary Manhole (Sanitary Sewer)

1507000A Protection and Support of Existing Utilities

Rev. Date 02/04/26

L079-0004 GENERAL

NOTICE TO CONTRACTOR - PROCUREMENT OF MATERIALS

Upon Award, the Contractor shall proceed with shop drawings, working drawings, procurement of materials, and all other submittals required to complete the work in accordance with the contract documents.

Rev. Date 05/12/26

NOTICE TO CONTRACTOR – LOTCIP PROJECT SIGN

REQUIREMENTS

Project Sign Requirements:

SIGN PANEL: Signs should be made from suitable materials to perform effectively for a minimum of 3 years. Example of allowable materials include ¾” MDO-EXT-APA Plywood or 0.125-gauge sheet aluminum. The following types of materials shall not be used:

mesh, non-rigid, roll-up, corrugated or waffle board type substrates, foam core and composite aluminum sign substrates.

Suitable attachments shall be provided so that the signs can be firmly attached to the sign supports without causing damage to the signs.

Signs may be painted or use non-reflective plastic sheeting. Paint shall be extremely durable, high quality, semi-gloss enamel resistant to air, sun and water. Non-reflective plastic sheeting shall be permanently adhered to the backing. The material shall withstand 3 years’ vertical, south-facing exterior exposure.

COLORS: All letters and symbols shall be blue code #0000FF, rgb (0, 0, 255), pantone 294, or approved equal. Background shall be white code #FFFFFF, rgb (255, 255, 255), or approved equal. If plywood is used for the sign panel, the back of the panel shall be painted matte black.

TYPEFACE: Helvetica Medium

SIGN SUPPORT: Sign panels shall be attached to vertical sign support posts. All sign supports shall have breakaway features that meet AASHTO requirements contained in the current “Standard Specifications for Structural Supports for Highway Signs, Luminaries and Traffic Signals”. The breakaway features shall be structurally adequate to carry the sign panel at 60-mph wind loading. Installation shall be in accordance with the manufacturer’s recommendations. A minimum 2-ft embedment depth below the ground line is required.

LOCATION: The signs SHALL be installed parallel to the travelway, so they are NOT easily viewable by drivers, as the signs are not MUTCD compliant and not intended to be roadway signs.

The lateral offset from the edge of road to the face of sign should be 6-12 feet. 12 feet is preferred where space is available for installation. When installed on a trail, the lateral offset should be 2 feet.

The bottom of the sign should be mounted 7 feet above the edge of road.

One sign shall be placed along Route 70 and one sign shall be placed along Oregon

Road and shall be field located as directed by the Engineer.

DURATION: The signs shall be erected for the life of the construction project. This means that they should be erected only after Notice to Proceed has been given to the contractor and should be removed with all other construction related signs at the end of the project considered to be the point that acceptance of the construction work is given.

NAME OF PROJECT: Oregon Road Bridge Replacement

FUNDING PROGRAM: Local Transportation Capital Improvement Program

SIGN DETAILS: The signs shall meet the requirements of the following details:

Method of Measurement:

The work to furnish, install and remove LOTCIP signs will be measured for payment by the number of square feet of sign face delivered and used on the Project.

Sign supports will not be measured for payment.

Basis of Payment:

This item will be paid for at the Contract unit price per square foot for

"Construction Signs," delivered and used on the Project, which price shall include the signs, portable sign supports, metal sign posts, and all hardware required to attach the sign to the support or posts. Each sign and support or posts furnished will be paid for once, regardless of the number of times used on the Project.

Pay Item Pay Unit

Construction Signs s.f.

SECTION 1.07 - LEGAL RELATIONS AND RESPONSIBILITIES

Article 1.07.13 - Contractor's Responsibility for Adjacent Property, Facilities and Services is supplemented as follows:

The following company and representative shall be contacted by the Contractor to coordinate the protection of their utilities on this project 30 days prior to the start of any work on this project involving their utilities:

City of Meriden – Water and Sanitary Sewer

Mr. Brian Ennis, City Engineer

Department of Public Works

142 East Main Street, Meriden, CT 06450

Phone: 203-630-4020 bennis@meridenct.gov

The Connecticut Light and Power Company dba Eversource Energy - Electric Distribution Mrs. Robin Lyons, Lead Engineer - Distribution Projects and Programs 107 Selden Street, Berlin, CT 06037 Phone: 860-665-4733 Robin.Lyons@eversource.com

The Southern New England Telephone Company dba Frontier Communications of

Connecticut

Ms. Lynne DeLucia, Manager - Engineering & Construction

1441 North Colony Road, Meriden, CT, 06450-4101

Phone: 203-238-5000 Lynne.m.delucia@ftr.com

Rev. Date 9-05-2025

SECTION 1.08 - PROSECUTION AND PROGRESS

Article 1.08.01 – Transfer of Work or Contract:

The Contractor shall perform with its own organization Contract work with a value under the Contract of at least 50% of the original total Contract value. If the Contractor sublets, sells, transfers, or otherwise disposes of any part of the Contract work without the Commissioner's prior written consent, the Contractor will not be relieved of any Contractual or other legal responsibility in connection therewith. Such an unauthorized act by the Contractor shall constitute a material breach of the Contract, and the Commissioner may, in such a case, terminate the Contract without further compensation to the Contractor.

Article 1.08.04 - Limitation of Operations - Add the following:

In order to provide for traffic operations as outlined in the Special Provision "Maintenance and Protection of Traffic," the Contractor will not be permitted to perform any work which will interfere with the described traffic operations on all project roadways as follows:

All Roadways

The Contractor shall maintain and protect a minimum of 1 lane of traffic in each direction with each lane on a paved travel path not less than 11 feet in width during the following times:

Monday through Friday between 6:00 a.m. and 9:00 a.m. & between 2:00 p.m. and 6:00 p.m.

Saturday and Sunday between 10:00 a.m. and 6:00 p.m.

Additional Lane Closure Restrictions

It is anticipated that work on adjacent projects will be ongoing simultaneously with this project. The Contractor shall be aware of those projects and anticipate that coordination will be required to maintain proper traffic flow at all times on all project roadways, in a manner consistent with these specifications and acceptable to the Engineer.

The Contractor will not be allowed to perform any work that will interfere with traffic operations on a roadway when traffic operations are being restricted on that same roadway, unless there is at least a one mile clear area length where the entire roadway is open to traffic or the closures have been coordinated and are acceptable to the Engineer. The one mile clear area length shall be measured from the end of the first work area to the beginning of the signing pattern for the next work area.

Rev. 07-25-2024

SECTION 1.10 ENVIRONMENTAL COMPLIANCE

In Article 1.10.03-Water Pollution Control:

REQUIRED BEST MANAGEMENT PRACTICES

Add the following after Required Best Management Practice Number 13:

14. The Contractor is hereby notified that the State listed species of Special Concern wood turtle

(Glyptemys insculpta), is present within the Project limits. Wood turtles require riparian habitats bordered by floodplain, woodland, or meadows. Their summer habitat includes pastures, fields, woodlands, power line cuts, and railroad beds bordering or adjacent to streams and rivers. Wood turtles spend most of their summer on land and can use areas up to 1500 feet from the streams/rivers where they overwinter. They hibernate submerged in tangled tree roots along riverbanks or in deep pools.

All construction activities taking place within the Project limits will need to be coordinated with the District Environmental Coordinator (DEC) and Office of Environmental Planning

(OEP) through the Engineer. At least 10 days prior to the commencement of any construction activities, the Contractor shall, through the Engineer, arrange a meeting with DEC and

CTDOT Environmental Inspector from the OEP (or their authorized delegate) to discuss proper protocol for maintaining environmental commitments made for the protection of this species and habitat. OEP will provide oversight through DEC and Engineer to ensure that the following protocols are followed and maintained during the Project.

During the wood turtle’s dormant period (November 1 to March 31):

• Construction activities will be allowed in upland areas.

• Work is not allowed in wetland/watercourse areas unless these areas were in active construction prior to November 1, and additionally, do not contain any areas of turtle habitat (no stream edge vegetation, stumps, or roots).

For any work done during the wood turtle’s active period (April 1 to October 31) the

Department will require the following precautionary measures to protect the wood turtle and wood turtle habitat:

a. All areas within the Project limits must be surveyed to verify the presence of any active wood turtle activity prior to commencement of the initial clearing and grubbing activities.

b. All construction personnel working within wood turtle habitat must be apprised of the species description and the possible presence of this listed species.

c. Exclusionary practices will be required in order to prevent any wood turtle to access construction areas. These measures will need to be installed at the limits of disturbance as shown on the plans.

Rev. 07-25-2024

d. Exclusionary fencing shall be at least 20” tall and must be secured to and remain in contact with the ground. The Contractor shall regularly inspect and maintain the fencing to prevent any gaps or openings at ground level. Silt fence with netting shall not be used.

e. The Contractor must search the work area each morning for the presence of this listed species prior to any work being done.

f. Any wood turtles encountered within the Project shall be carefully moved outside of the excluded work area and the Engineer shall be immediately informed in order to contact the DEC and OEP with the location.

When a species is found, the OEP will be responsible for completing and submitting the

Natural Diversity Data Base (NDDB) Vertebrate Sheet

(https://portal.ct.gov/DEEP/Endangered-Species/Contributing-Data). This completed document allows CTDEEP to update their database.

g. All staging and storage areas within the vicinity of the Project limits of the wood turtle habitat must be submitted to the DEC and Engineer and receive written approval from the OEP.

h. The Contractor shall not park heavy machinery or vehicles within the wood turtle habitat without submitting to the DEC and Engineer and receiving written approval from the

OEP.

i. Exclusionary fencing shall be removed at the completion of the Project and when final stabilization has occurred to allow for reptile and amphibian passage to resume.

j. When felling trees adjacent to watercourses, they shall be cut to fall away from the waterway and not dragged across the waterway. Stumps shall be left in waterway banks where possible.

These practices will be applied to the entire Project unless a sketch is attached, which identifies specific areas of concern.

If any wood turtles are observed in or around the Project area, the Engineer will notify the

DEC to facilitate further coordination with OEP’s Environmental Resource Compliance

Unit. If the DEC is unable to be reached, notify OEP at Andrew.Piraneo@ct.gov or at

Marilyn.Gould@ct.gov.

This species is protected by State laws, which prohibit killing, harming, taking, or keeping them in your possession. A CTDEEP’s fact sheet of the wood turtle shall be posted in the

Contractor’s and Inspection field offices and can be downloaded at the link below.

CTDEEP’s Fact Sheet for the Wood Turtle:

https://portal.ct.gov//media/DEEP/wildlife/pdf_files/outreach/fact_sheets/woodturtlepdf.pdf

L079-0004

ITEM #0100600A

ITEM #0100600A – CONSTRUCTION ACCESS

Description: The item “Construction Access” shall consist of the design, construction, maintenance and removal of temporary works that the Contractor elects to use to access the work under the bridge structure for the removal of existing sewer main and installation of proposed sewer main attached to the bridge girder, removal of existing bridge, and construction of the proposed bridge.

Construction Methods: The Contractor’s means and methods for construction shall meet all requirements established for the Project. At least 30 days prior to construction of temporary works, access, platforms and scaffolding, the Contractor shall submit detailed construction access working drawings and computations in accordance with Article 1.05.02. The working drawings and calculations must be prepared, stamped and signed by a Professional Engineer licensed in the State of Connecticut.

The furnishing of such plans, methods and calculations shall not serve to relieve the Contractor of his responsibility for the safety of the work and the successful completion of the Project. The

Contractor's proposal must meet the requirements of Section 1.10.

Method of Measurement: This item will be paid for on a lump sum basis and will not be measured for payment.

Basis of Payment: Construction Access will be paid for at the contract lump sum price for

“Construction Access” which price shall include the design, construction, maintenance and removal of all temporary works, all construction access, and all materials, tools, equipment, labor and work incidental thereto.

Construction Access L.S.

Rev. 05/08/2025

L079-0004 ITEM #0202216A

ITEM #0202216A – EXCAVATION AND REUSE OF EXISTING CHANNEL

BOTTOM MATERIAL

Description: This work shall consist of excavating existing channel bottom material, herein referred to as natural streambed material, in areas where the channel bottom is to be disturbed and regraded to create a work area for a bridge, culvert, articulated concrete block placement, cofferdam installation, as shown on the plans or as directed by the Engineer. This item shall also include the stockpiling and protecting of the excavated material on-Site, subsequent placement, top dressing, or backfilling of the excavated stockpiled material within the watercourse, as shown on the plans or as directed by the Engineer.

Materials: The material for this item shall consist of the existing naturally-formed rocks, cobbles, gravel, soils and clean natural sediments from within the channel.

Any material excavated from shale, ledge (bedrock) formations broken from larger boulders, or material with sharp acute edges will not be accepted. Broken concrete will not be accepted.

Geotextile: Geotextile shall be as specified in M.08.01-19 Geotextiles.

Construction Methods:

1. Stockpiling of Material. The Contractor shall submit for the Engineer’s approval a proposed location for stockpiling material. The proposed location shall be upland where disruption to the stream channel or impact to wetland areas caused by moving the natural streambed material to and from the stockpile are minimized. The Contractor shall prepare the area approved by the Engineer, suitable in size and location for stockpiling the natural streambed material.

The stockpile shall be located where it can remain undisturbed for the duration of the stream channel reconstruction or as shown on the plans and shall be protected using sedimentation control measures. The stockpile area shall be free of debris and cleaned adequately to prevent mixing with underlying soil or other materials, including the use of a separation barrier such as: Geotextile –

(Separation Class 1), polyethylene sheeting, or similar. The stockpile area shall be adequately covered to protect the excavated natural streambed material from erosion by rain, wind, or other forces.

2. Excavation of Natural Streambed Material. The Contractor shall notify the Engineer 10 days in advance of excavation and placement of natural streambed material activities. The

Engineer will identify the limits of the exposed natural streambed material during excavation under this item. The Engineer will identify the bottom limit of excavation, an amount up to but not exceeding 24 inches in depth, unless approved by the Engineer or their authorized delegate, based upon visual inspection of the natural streambed material. After the limits of excavation have been determined, the Contractor shall excavate the natural streambed material, separate from any other roadway, structure, channel or unsuitable material excavation on Site. After the natural streambed material has been excavated, it shall be placed in the pre-approved stockpile area.

3. Backfilling and Placement with Natural Streambed Material. The stockpiled natural streambed material shall be placed as fill material as specified at the designated location(s) to the required thickness and elevation as shown on the plans or as directed by the Engineer or their authorized delegate. Placement methods likely to cause segregation of the various sizes of stone will not be permitted. Placement techniques shall prevent integration with non-natural streambed material and shall keep the natural streambed material relatively homogenous. The natural streambed material shall be placed in a manner that replicates the original condition of the channel prior to excavation and to the elevation as shown on the plans.

4. Top Dressing with Natural Streambed Material. The stockpiled natural streambed material shall be used as top dressing over riprap or other material as specified at the designated location(s) to the required thickness and elevation as shown on the plans or as directed by the Engineer or their authorized delegate. Placement techniques shall prevent integration with the non-natural streambed material and shall keep the natural streambed material relatively homogenous. The natural streambed material shall be placed in a manner that replicates the original condition of the channel prior to excavation and to the elevation as shown on the plans.

5. Site Maintenance. When backfilling, placing, or top dressing, the Contractor shall perform all containment, diversion, or other separation of the channel flow to minimize sediment transport downstream.

The disposal of any surplus and/or unsuitable material shall be in accordance with Article 1.09.04.

If the Engineer determines that there is an insufficient quantity of natural streambed material within the Project limits, the Contractor shall procure Supplemental Streambed Channel Material as specified under Item #0202217A.

If it is required for the Project to have washing-in of supplemental streambed material, the

Contractor shall procure Washing-in Supplemental Streambed Material as specified under Item

#0202218A.

The pre-approved stockpile areas shall be restored to the satisfaction of the Engineer. Work to restore/regrade stockpile areas will be paid for under the respective pay item(s).

Method of Measurement: This work will be measured for payment by the number of cubic yards of natural streambed material excavated, stockpiled, maintained, installed, and accepted.

The Engineer will delineate the horizontal pay limit prior to the start of excavation. The vertical pay limit will be measured from the top of the existing channel bottom to the bottom of excavation required specifically for the stockpiling of channel bottom material.

Any material excavated beyond the approved horizontal pay limits or deeper than the depth of natural streambed material identified and approved by the Engineer will not be measured for payment under this item. Should such additional excavation be required to complete the Contract work, it will be measured for payment separately under the applicable pay item(s).

Basis of Payment: Payment for this work will be made at the Contract unit price per cubic yard for "Excavation and Reuse of Existing Channel Bottom Material.” The price shall include all materials, equipment, geotextile, tools, and labor incidental to the preparation of the stockpile area, excavation of natural streambed material, hauling of the material to the stockpile, and separation of any rock ledge or concrete debris, storing, and protecting (including sedimentation controls and covering) excavated material.

Payment for clearing and grubbing of the approved stockpile area will be included in the item

“Clearing and Grubbing.”

Payment for the removal and proper disposal of all surplus and/or unsuitable material will be in accordance with Article 1.09.04 – Extra and Cost-Plus Work.

Riprap or other specified material as shown on the plan will be paid for under the respective items.

Payment for supplemental streambed channel material will be included in the Item #0202217A

“Supplemental Streambed Channel Material.” If no item appears in the proposal, payment for the work will be in accordance with Article 1.09.04 – Extra and Cost-Plus Work.

Payment for washing in supplemental streambed channel material will be included in the Item

#0202218A “Washing-in Supplemental Streambed Material.” If no item appears in the proposal, payment for the work will be in accordance with Article 1.09.04 – Extra and Cost-Plus Work.

Payment for all containment, diversion or other separation of stream flow will be included in the item “Cofferdam and Dewatering” or special provision for "Handling Water."

Excavation and Reuse of Existing Channel Bottom Material c.y.

L079-0004 ITEM #0204001A

ITEM #0204001A – COFFERDAM AND DEWATERING

Cofferdam and Dewatering shall be constructed in accordance with Section 2.04 and supplemented as follows:

Article 2.04.01 - Description: Add the following:

The installed cofferdam may act as a temporary earth retaining system where needed so that existing or planned facilities are properly retained during the excavation or placement of fill.

Article 2.04.03 – Construction Methods: Add the following at the end of section 1:

If Cofferdam is being used as a temporary earth retaining system, the work shall also be performed per article 7.16.03.

During the removal of the cofferdams, care shall be taken not to damage the recently constructed structures. Vibratory removal of cofferdams shall be limited to avoid disruption to the surrounding ground.

Cofferdam and Dewatering l.f.

Rev. 7-6-2023

L079-0004 ITEM #0204151A

ITEM #0204151A - HANDLING WATER

Description: Work under this item shall consist of designing, furnishing, installing, maintaining, and removing of a temporary water handling system. This may include water-handling-cofferdams, bypass pipes, bypass pumps/hoses, temporary energy dissipation, sump pumps, drainage channels, water handling for ancillary drainage, and dewatering.

A temporary water handling system redirects water beyond, through, or around the limits of construction to allow work to be done in the dry.

Materials: The materials required for this work shall be as shown on the plans, on the accepted

Contractor’s Working Drawing submittal, or as ordered by the Engineer.

Construction Methods: The Contractor shall prepare and submit written procedures for handling water. Working Drawings, in accordance with Article 1.05.02, shall also be prepared and submitted.

The Contractor shall consider stream conditions, water elevations, expected weather, and risks associated with the Site to determine the type of temporary water handling system required to redirect water away from work being performed. The system shall be designed to comply with the Temporary Hydraulic Table in the Contract plans and be compatible with the stage of construction and Maintenance and Protection of Traffic scheme, as indicated in the Contract, and shall conform to Section 1.10.

The Contractor shall be responsible to maintain and repair the water handling system throughout the duration of the Contract. If the system becomes damaged, displaced, or not functioning properly due to construction activities, stream conditions or storm events, the Contractor shall be responsible to remediate the system back to working order per plan or as required at the direction of the Engineer.

Unless otherwise directed by the Engineer, all temporary water handling system components shall be removed in an acceptable manner when no longer required.

Bypass Pumping:

The bypass pump system shall be designed by the Contractor to comply with the Temporary

Hydraulic Table in the Contract plans.

When incorporating a bypass pump/hose system, the Contractor shall provide a means to maintain continuous flow to the downstream channel to protect resources, unless otherwise noted in the

Contract plans or as accepted by the Engineer. The Contractor shall provide for both maintaining continuous flow and accommodating temporary design flows using appropriate pump size for each case, valving, metering, or adjusting the flow during construction.

A pump screen shall be provided on the intake with maximum 0.5 inch diameter openings.

Method of Measurement: The work under this item, being paid on a lump sum basis, will not be measured for payment.

Basis of Payment: This work will be paid for at the Contract lump sum price for “Handling Water” completed and accepted, which price shall include designing (including submittals and

Rev. 7-6-2023

L079-0004 ITEM #0204151A

Working Drawings), furnishing, installing, maintaining, and removing of all temporary water handling system components as are necessary for completion of the work. This price shall include all materials, equipment, tools, labor and work incidental thereto.

A schedule of values for payment shall be submitted to the Engineer for review and comment.

Handling Water l.s.

Rev. Date 06/30/24

L079-0004 ITEM #0219011A

ITEM #0219011A – SEDIMENT CONTROL SYSTEM AT CATCH BASIN

Description: Work under this item shall consist of furnishing, installing, maintaining, replacing, and removing sediment control system at catch basins, herein referred to as Silt Sack, at the locations as shown on plans or as directed by the Engineer. The work shall also include removal of accumulated sediment, and disposal of accumulated sediment, Materials: The Silt Sack must be commercially produced and marketed for the specific application(s) on the Project. All Silt Sack must be manufactured from a specially designed woven polypropylene geotextile sewn material. The Silt Sack must be able to handle flows of at least 180 gallons per minute per square foot, fit any sized catch basin or drop inlet, and be UV resistant.

The Silt Sack product shall be one of the following or an approved equal:

1. Siltsack®

2. Dandy Sack®

3. FleXstorm Catch-It™

4. PIG®Sediment-Drain Filter

5. ACF Environmental Silt Sack

The Sediment Control System at Catch Basin must have the following features: two dump straps attached at the bottom to facilitate the emptying of the Silt Sack and lifting straps to be used to lift the

Silt Sack from the catch basin or drop inlet. The Silt Sack shall have a restraint cord approximately halfway up to keep the sides away from the catch basin or drop inlet walls. When required, a curb deflector shall be installed as directed by the Engineer.

Product Data for the Silt Sack to be used by the Contractor must be submitted for review and acceptance by the Engineer or their authorized delegate prior to the installation on-Site.

Construction Methods: The Contractor shall install the Silk Sack per the manufacturer’s instructions and recommendations at each catch basin or drop inlet as shown on the plans or as directed by the Engineer to provide inlet protection to prevent silt, sediment, or debris from entering the stormwater drainage system.

When the Silt Sack becomes 1/2 full of accumulated sediment, the Contractor shall empty, clean, and replace the Silt Sack back into the catch basin or drop inlet. Sediment emptied shall be considered unsuitable material and be disposed of at an off-Site approved upland facility per federal, State, and local environmental laws and regulations.

At the completion of the Project, the Contractor shall remove all Silt Sacks within the Project limits.

Any spilled sediment material during removal operations shall be removed by the Contractor at no cost to the State.

Rev. Date 06/30/24

L079-0004 ITEM #0219011A

Method of Measurement: Sediment Control System at Catch Basin will be measured as each installed, maintained, accepted, and removed. There will be no separate measurement for maintenance or replacement associated with this item.

Basis of Payment: The item “Sediment Control System at Catch Basin” will be paid at the Contract unit price for each completed system in place and accepted, which price shall include installing, maintaining, replacing, removal of material, off-Site disposal of accumulated material, materials, equipment, tools, and labor incidental thereto.

The cost of installing hay bales, geotextile, check dam, or fiber roll for inlet protection shall be paid for under their respective Contract item or special provision.

Sediment Control System at Catch Basin ea.

Rev. 07/14/2025

L079-0004 ITEM #0406194A

ITEM #0406194A – JOINT AND CRACK SEALING OF BITUMINOUS CONCRETE

PAVEMENT (LF)

Description: This work consists of furnishing and applying hot-applied asphalt crack sealer to bituminous concrete pavement joints and cracks. It shall be constructed in close conformity with the lines, grades, thicknesses, and typical cross sections shown on the plans or established by the

Engineer. Joint and Crack Sealing of Bituminous Concrete Pavement may be used in conjunction with other repair treatments including joint and crack filling or patching, in which case the sequence of treatments will be provided in the Plans or directed by the Engineer.

For the purposes of this document, the word “crack” includes all longitudinal (along the direction of travel) and transverse (perpendicular to the direction of travel) cracks and joints. All work specified for “crack(s)” herein shall apply to all types of cracks and joints unless otherwise specified.

Materials:

1. Crack Seal: The crack seal material shall be composed of a hot-applied asphalt meeting

ASTM D6690 Type II requirements. The Contractor must submit to the Engineer all Material

Safety Data Sheet documents from the material manufacturer prior to the commencement of work. During work progress, the Contractor must submit to the Engineer a Materials

Certificate (MC) and a Certified Test Report (CTR) showing conformance to ASTM D6690

Type II requirements for each batch or lot of material utilized on the Contract in accordance with Section 1.06.07.

2. Optional Barrier Material – Backer Rod: The backer rod shall be a heat resistant material compatible with the crack sealant and acceptable to the manufacturer of the sealant. No bond or reaction shall occur between the sealant and the rod. It shall be of a non-water absorbent material and shall not melt or shrink when hot sealant is poured on it.

The backer rod shall have a maximum of 5% absorption when immersed in water for 24 hours with the ends sealed. The backer rod shall be of such a size that compression is required for installation in the crack, so that it maintains its position during the sealing operation. Backer rod shall be dry.

3. Optional Barrier Material – Hot Mix Asphalt (HMA): Any HMA placed in the bottom of a crack between 1.5 and 2 inches wide shall be HMA S0.25 Traffic Level 2 and shall meet all requirements of Section 4.06 - Bituminous Concrete.

Construction Methods: The crack sealing operation shall proceed in accordance with the requirements of the “Maintenance and Protection of Traffic” and “Prosecution and Progress” specifications.

1. Equipment: The equipment used by the Contractor shall include, but not be limited to, the following:

a. Melter Applicator: The unit shall consist of a boiler kettle equipped with pressure pump, hose, and applicator wand; the boiler kettle may be a combination melter and pressurized applicator of a double-boiler type with space between the inner and outer shells filled with heat transfer oil. Heat transfer oil shall have a flash point of not less than 600°F. The kettle shall include a temperature control indicator. The kettle shall be capable of maintaining the crack seal material at the manufacturer’s specified application temperature range. The kettle shall include an insulated applicator hose and application wand. The hose shall be equipped with a shutoff control. The kettle shall include a mechanical full sweep agitator to provide continuous blending. The unit shall be equipped with thermometers to monitor the material temperature and the heating oil temperature. The unit shall be equipped with thermostatic controls that allow the operator to regulate material temperature up to at least 425°F.

b. Application Wand and Squeegee Applicator: The material shall be applied with a wand followed by a squeegee applicator. The squeegee applicator shall be of commercial/industrial quality designed with a “U” shaped configuration. It shall be of a size adequate to strike off, flush with the surrounding pavement surface and without overflow around the sides, all crack seal material placed. This tool shall be either attached to the applicator wand or used separately as its own long handled tool.

c. Hot Air Lance: The unit shall be designed for cleaning and drying the pavement surface cracks. Minimum compressed air capacity shall be 100 psi. The compressed air emitted from the tip of the lance shall be capable of achieving a temperature of at least 1500°F.

d. Vertically Mounted Power Driven Wire Brush: This tool shall be used to remove any dirt, debris, or vegetation to the depths specified that cannot be removed by the hot air lance. It shall be of adequate size and power to remove all material from cracks as specified.

2. Weather Requirements: Work shall not be performed unless the pavement is dry. No frost, snow, ice, or standing water may be present on the roadway surface or within the cracks. The ambient temperature must be 40ºF and rising during the field application operations for work to proceed.

3. Material Mixing Procedure: The prepackaged material shall be added to the melter applicator in the presence of the Engineer. It shall then be mixed and heated to the recommended application temperature. The crack seal material shall never exceed 400°F.

4. Determination of Cracks to be Sealed: The width and depth requirements for cracks to be sealed are as follows:

All crack width determinations shall be made by measuring the crack width flush at the surface of the pavement prior to being sealed. A straightedge shall be used whenever necessary to establish the location or limits of the flush surface of the pavement.

All cracks from 1/8 inch up to 1.5 inches wide shall be prepared and sealed as stated below.

Cracks that are between 1/8 inch and 1.5 inches wide, but eventually taper in width below the minimum 1/8 inch, shall also be prepared and sealed as stated below. Only cracks that are less than 1/8 inch wide throughout their entire length shall be excluded.

Transverse cracks, where a portion of the crack (50% or less) exceeds a width of 1.5 inches, up to 2 inches, shall also be prepared and sealed as stated below.

All joints to be sealed that are raveled (loss of the pavement surface material) shall be at least

½ inch in depth at the joint’s deepest point. The minimum width of a raveled joint must be ½ inch. The maximum width of a raveled joint to be sealed is 3 inches.

Any cracks exceeding the width and depth requirements specified above shall be repaired using separate items.

5. Crack Preparation: Cracks to be sealed shall be treated with a hot air lance prior to application of the crack seal material. Two (2) passes minimum shall be made with the hot air lance. The hot air lance operation shall proceed at a rate no greater than 120 feet per minute. There shall be no more than 10 minutes between the second hot air lance treatment and the material application.

The use of the hot air lance is not intended to heat the crack. It is to be used to blow all debris from the crack to the depths specified below and to remove any latent moisture from the crack until the inside of the crack is completely dry as determined by the Engineer.

“Moisture” does not include standing water. The hot air lance is not to be used to boil off or blow standing water from the bottom of a crack. If standing water is present in the bottom of any crack, the sealing operation shall be postponed until such time that the standing water evaporates naturally. The Contractor may use compressed, oil-free air (not heated) to blow standing water from a crack to help accelerate the natural evaporation process. If standing water remains after using compressed air, the crack shall be allowed to dry naturally until remaining standing water evaporates. The hot air lance shall be used after visible water has evaporated. If a crack is already completely dry as determined by the Engineer, the hot air lance shall be operated at its lowest temperature possible.

The hot air lance is to be used to blow all debris from cracks (not including raveled joints) to a depth of at least ¾ inch for cracks between 1/8 inch and ¾ inch wide, and to a depth of 1.25 inches for cracks between ¾ inch and 2 inches wide. The hot air lance shall be used to blow all debris from raveled joints to a depth of 1 inch or the full depth of the joint, whichever is smaller.

In the event that cracks are packed tightly with debris, dirt, vegetation, or other material, except previously placed sealant or filler, the Contractor shall use a vertically mounted power driven wire brush to remove all material and burnish the sides of the crack to the depths specified above. Cracks treated with the power driven wire brush shall subsequently be treated with a hot air lance as described in this section. The use of both the power driven wire brush and the hot air lance shall result in the complete removal of all material in the crack

(except previously placed sealant or filler) to the depths specified above such that the sides of the crack are completely free and clean of any debris and moisture.

In the event that cracks have depths greater than 2 inches below the pavement surface, the

Contractor may place a barrier composed of backer rod as specified herein. The backer rod shall be placed in a manner leaving 1.25 inches below the elevation of the pavement surface for crack seal material. Use of backer rod will not be allowed for cracks wider than 1.5 inches or less than ½ inch wide. For cracks between 1.5 and 2 inches wide, HMA S0.25

Traffic Level 2 may be placed in the bottom of the prepared crack. HMA shall be placed and compacted with a steel T-bar approved by the Engineer in a manner leaving 1.25 inches below the elevation of the pavement surface for crack seal material.

6. Crack Sealing: As soon as cracks have been prepared, they shall be filled to refusal along their entire length with the crack sealant material. The treatment material shall be maintained at the manufacturer’s specified/recommended application temperature range at all times. The sealing operation shall be suspended if the temperature of the crack seal material falls outside the specified temperature range and shall remain suspended until the crack seal material is brought within the specified temperature range. Sealed cracks are to be squeegeed immediately following application of the crack seal material, striking excess sealer flat to the adjacent pavement surface. There shall be no build-up of treatment material above or adjacent to the crack at any time. If the initial application of crack sealant material fails to fill the crack or shrinks upon cooling such that there is a depression formed of at least ¼ inch or greater, a second application of sealant shall be placed over the first application.

7. Protection of Sealed Cracks: Traffic shall not be permitted on the pavement until the crack seal material is set so that the material does not track and is not deformed or pulled out by tires. If the work under this item is being performed prior to placing a hot mix overlay or other surface treatment, a detackifier or blotting agent will not be allowed. If work under this item is not followed by placement of an overlay of any kind, a detackifier or blotting agent may be used. If a detackifier or blotting agent is used, it shall be one recommended by the supplier of the crack seal material and shall be used as recommended by the supplier, except that no paper, cotton, or other organic materials shall be allowed. Information on the type and usage of a detackifier or blotting agent shall be submitted to the Engineer prior to use.

8. Removal and Disposal of Material: All debris generated from the operations described above shall be removed from the roadway by the Contractor.

Treatment material remaining in the Contractor’s kettle at the close of the daily work session shall be discarded. At no time shall treatment material be re-heated for use in subsequent crack sealing applications unless permitted by the Engineer following a review of specific circumstances.

All debris and surplus treatment material shall be properly disposed in accordance with

Article 1.10.03 and State of Connecticut law.

9. Acceptance of Work: When work is complete, an inspection shall be scheduled with the

Engineer. The Engineer will note all deficiencies including, but not limited to, areas exhibiting adhesion failure, cohesion failure, tracking of sealant material, and missed cracks.

Work identified by the Engineer as not acceptable shall be repaired at the Contractor’s expense. The Contractor shall notify the Engineer upon completion of any corrective work performed.

Method of Measurement: This work will be measured by the total number of linear feet of cracks sealed of bituminous concrete roadway surface, as indicated in the Contract plans and as measured, verified, and accepted by the Engineer.

Basis of Payment: This work will be paid for at the Contract unit price per linear foot for “Joint and Crack Sealing of Bituminous Concrete Pavement” complete and accepted in place. The price shall include all submittals, materials, equipment, tools, and labor incidental thereto. No payment will be made to the Contractor prior to submittal of required documents.

Joint and Crack Sealing of Bituminous Concrete Pavement l.f.

Rev. 03/19/2024

L079-0004 ITEM #0406312A

ITEM #0406312A – GUTTER LINE SEALING FOR BRIDGES

Description: This work shall consist of applying hot-applied asphalt crack sealant along the gutter line of bridges after paving to seal the joint between the bituminous concrete overlay and parapet, curb, or barrier at the locations and to the limits shown on the Plans.

1. Crack Seal: The crack seal material shall be composed of a hot-applied asphalt meeting ASTM

D6690 Type II requirements.

Prior to the start of work, the Contractor shall submit a Materials Certification (MC) in accordance with Article 1.06.07 certifying the joint seal material meets these requirements.

The Contractor must submit to the Engineer all Safety Data Sheets (SDS) from the material manufacturer prior to the commencement of work.

2. Blotting Agent – Detackifier: This material shall be a fine-graded granular material with 100% aggregate passing the 3/16-inch sieve and no more than 5% passing the #200 sieve when tested in accordance with AASHTO T 27 and T 11.

The material shall be as recommended by the supplier of the crack sealant and shall be used as recommended by the supplier, except that no paper, cotton, or other organic materials will be allowed. Product Data shall be submitted to the Engineer for review in accordance with Article

1.05.02.

Construction Methods: The sealing operation shall proceed in accordance with the requirements of the “Maintenance and Protection of Traffic” and “Prosecution and Progress” specifications.

1. Equipment: The equipment used by the Contractor shall include the following:

a. Melter Applicator: This shall consist of a boiler kettle equipped with pressure pump, hose, and applicator wand; the boiler kettle may be a combination melter and pressurized applicator of a double-boiler type with space between the inner and outer shells filled with heat transfer oil. Heat transfer oil shall have a flash point of not less than 600°F. The kettle shall include a temperature control indicator. The kettle shall be capable of maintaining the crack seal material at the manufacturer’s specified application temperature range. The kettle shall include an insulated applicator hose and application wand. The hose shall be equipped with a shutoff control. The kettle shall include a mechanical full sweep agitator to provide continuous blending.

Thermometers shall monitor the material temperature and the heating oil temperature.

Thermostatic controls shall allow the operator to regulate material temperature up to at least 425°F.

b. Application Wand and Squeegee Applicator: The material shall be applied with a wand followed by a squeegee applicator. The squeegee applicator shall be of commercial/industrial quality and be designed with a configuration to properly strike off the sealant placed along the gutter line of the bridge, adjacent bituminous concrete overlay and parapet, curb, or barrier to the dimensions specified. It shall be of a size adequate to strike off, flush with the surrounding areas, all crack seal material placed.

This tool shall be either attached to the applicator wand or be a separate long handled tool.

c. Hot Air Lance: This shall be designed for cleaning and drying the pavement edge along the curb parapet or barrier. Minimum compressed air capacity shall be 100 psi. The oil-free compressed air emitted from the tip of the lance shall be oil free and capable of achieving a temperature of at least 1500°F.

2. Weather Requirements: The pavement shall be dry without frost, snow, ice, or standing water on the roadway surface and within the areas to be sealed. The ambient temperature must be at least 40ºF and rising during application.

3. Material Mixing Procedure: The prepackaged material shall be added to the melter applicator in the presence of the Engineer. It shall then be mixed and heated to the recommended application temperature. The crack sealant shall never exceed 400°F. The treatment material shall be maintained at the manufacturer’s specified/recommended application temperature range during application. The sealing operation shall be suspended if the temperature of the crack sealant falls outside the specified temperature range and shall remain suspended until the crack sealant is brought within the specified range.

4. Delineation of Areas to be Sealed: Prior to the sealing operation, the Contractor shall locate and mark out the start and end limits of the work. The sealing shall span the entire length of the structure and be done along each side of the bridge such that both gutter lines are completely sealed, as shown on the Plans.