(K) RFI Form.pdf
PDF 430 KB Posted
- Solicitation number
- ACQR6019786
About this file
This document is a Request for Information (RFI) related to a federal contract opportunity for the renovation of the Child Development Center Building B-1376 and Child and Youth Development Center Building 1297 at Naval Station Newport.
The key details are: The contract number is RFP 5997283, and the RFI number is not provided. The prime contractor and subcontractor/supplier are not named. The RFI is requesting information on drawings, details, specifications, cost effects, and a recommended solution. A response is required by a specified date. The RFI system does not authorize the contractor to proceed with work, and if the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days. The related federal contract opportunity is for a Design-Build (DB) / Design-Bid-Build (DBB), Indefinite Delivery / Indefinite Quantity (IDIQ), Multiple Award Construction Contract (MACC) for the New London, CT / Newport, RI areas, with specific contractors listed as eligible to bid.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NUMBER:
RFP 5997283
REQUEST FOR INFORMATION RFI NUMBER:
CONTRACT TITLE:
PRIME CONTRACTOR: SUBCONTRACTOR/SUPPLIER:
SUBJECT/TITLE OF RFI:
DRAWING(S): DETAIL(S): SPECIFICATION: CPM ACTIVITY NUMBER:
COST EFFECT: INCREASE: DECREASE: NONE:
INFORMATION REQUESTED & RECOMMENDED SOLUTION:
Date Response Required By: Date: Signature:
From:
To: Field Office Code
RECOMMENDATION:
Date: Signature:
From: Field Office To: Prime Contractor
REPLY:
Date: Signature:
This reply is given with the expressed understanding that it does not constitute basis for change in the amount or time of subject contract. If you do not concur, DO NOT PROCEED, and notify this office immediately.
Please assign PC # to this change. It is requested that a proposal be forwarded by . THIS DOES NOT
CONSTITUTE AUTHORIZATION TO PROCEED.
copy to: File 2L
Supv Civil Engineer Construction Representative
DLA Site Development
The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days.
DISTRIBUTION: Original to File via REICC PL/DM ET A/E PC # via AROICC/CONTRACT OFFICER
File details come from the government source that posted it. Updated .