JUN 2026 Equipment Only Consolidation Schedule.pdf
PDF 211 KB Posted
- Attached to
- 6525--JUN 2026 Equipment Only Consolidation
- Solicitation number
- 36A79726Q0011
About this file
This document is a consolidation schedule for a June 2026 Equipment Only procurement. The schedule outlines key milestones across all modalities for a federal contracting process managed by a Contracting Officer (CO) and the NAC (likely a Network Acquisition Center). Requirements must be submitted to the NAC in FORCE by June 30, 2026, followed by publication of a Pre-Solicitation Notice on August 5, 2026. The Request for Offers (RFO) and requirements will be posted on August 12, 2026, with vendors having until August 26, 2026 to submit equipment-related questions to the NAC. Responses to vendor questions will be published via amendment on September 16, 2026.
Vendors must submit their offers to the NAC by October 14, 2026, with customers receiving vendor offers via shared drive on October 21, 2026. Technical evaluations and best value selections from customers are due November 12, 2026. The NAC will assign CO workload on November 18, 2026, with a target award date for delivery orders of February 16, 2027—approximately 90 days from workload assignment. All dates are estimates and subject to change. The consolidation applies to equipment procurement only across all modalities within this initiative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 662B60031-757B60015.zip | ZIP file | |
| 589B69013- 662B60015.zip | ZIP file | |
| Vendor Workup Spreadsheet - 36A79726Q0011.xlsx | XLSX spreadsheet | |
| Vendor Folders.zip | ZIP file | |
| 402B61001-570B60011.zip | ZIP file | |
| EQ JUN 2026 CONSOLIDATION - Schedule of Line Items with QA Template-.xlsx | XLSX spreadsheet | |
| JUN 2026 EQ Consolidation - RFO.pdf | ||
| 36A79726Q0011_1.docx | DOCX document | |
| Memorandum for Training.pdf | ||
| VA Directive 6550 - New Appendix A - published Jun. 2023.pdf | ||
| 570B60012- 589B63022.zip | ZIP file |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUN 2026 Equipment Only Consolidation Schedule
Dates* Milestone – All Modalities
6/30/2026 Requirements due to the NAC in FORCE
8/05/2026 Publish Pre-Solicitation Notice
8/12/2026 Post Requirements and Request for Offers (RFO)
8/26/2026 Vendors to submit Equipment Questions to NAC
9/16/2026 NAC Published Responses to Vendor Questions via Amendment
10/14/2026 Vendors to Submit Offers to NAC
10/21/2026 Customers Receive Vendor Offers via the Shared Drive
11/12/2026 Customers Submit Technical Evaluations (Best Value Selections)
11/18/2026 NAC Assigns CO Workload
2/16/2027 Goal to Award Delivery Orders (90 Days from Assignment)
*Dates are estimates and are subject to change