JUN 2026 Equipment Only Consolidation Schedule.pdf
PDF 211 KB Posted
- Attached to
- 6525--JUN 2026 Equipment Only Consolidation
- Solicitation number
- 36A79726Q0011
About this file
This document is a consolidation schedule for a June 2026 equipment-only procurement. The schedule outlines key milestones for all modalities across a ten-month period beginning June 30, 2026, when requirements are due to the NAC (National Acquisition Center) in FORCE. The pre-solicitation notice is scheduled for publication on August 5, 2026, followed by posting of requirements and a Request for Offers (RFO) on August 12, 2026.
The vendor response phase begins with an equipment questions deadline of August 26, 2026, with NAC publishing responses via amendment on September 16, 2026. Vendors must submit offers to the NAC by October 14, 2026, and customers will receive vendor offers via shared drive by October 21, 2026. Customers are required to submit technical evaluations and best value selections by November 12, 2026. Following NAC assignment of contracting officer workload on November 18, 2026, the goal for awarding delivery orders is February 16, 2027, which represents a 90-day timeline from workload assignment. All dates listed are estimates and subject to change.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Copy of JUN 2026 EQ CONSOLIDATION - Schedule of Line Items with QA _Updated_HTM.xlsx | XLSX spreadsheet | |
| 36A79726Q0011 0001.docx | DOCX document | |
| Updated Tech Specs.zip | ZIP file | |
| 662B60031-757B60015.zip | ZIP file | |
| 589B69013- 662B60015.zip | ZIP file | |
| EQ JUN 2026 CONSOLIDATION - Schedule of Line Items with QA Template-.xlsx | XLSX spreadsheet | |
| 36A79726Q0011_1.docx | DOCX document | |
| Memorandum for Training.pdf | ||
| Vendor Folders.zip | ZIP file | |
| 570B60012- 589B63022.zip | ZIP file | |
| 402B61001-570B60011.zip | ZIP file | |
| JUN 2026 EQ Consolidation - RFO.pdf | ||
| VA Directive 6550 - New Appendix A - published Jun. 2023.pdf | ||
| Vendor Workup Spreadsheet - 36A79726Q0011.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUN 2026 Equipment Only Consolidation Schedule
Dates* Milestone – All Modalities
6/30/2026 Requirements due to the NAC in FORCE
8/05/2026 Publish Pre-Solicitation Notice
8/12/2026 Post Requirements and Request for Offers (RFO)
8/26/2026 Vendors to submit Equipment Questions to NAC
9/16/2026 NAC Published Responses to Vendor Questions via Amendment
10/14/2026 Vendors to Submit Offers to NAC
10/21/2026 Customers Receive Vendor Offers via the Shared Drive
11/12/2026 Customers Submit Technical Evaluations (Best Value Selections)
11/18/2026 NAC Assigns CO Workload
2/16/2027 Goal to Award Delivery Orders (90 Days from Assignment)
*Dates are estimates and are subject to change