John Day STS Crane Full Solicitation and Work Specs.pdf

PDF 7 MB Posted

Attached to
JOHN DAY LOCK & DAM POWERHOUSE SUBMERGED TRAVELING SCREEN (STS), NEW 130 TON GANTRY CRANE
Solicitation number
W9127N20R0005
Issued by

About this file

This solicitation is for a new 130-ton Submerged Traveling Screen (STS) gantry crane at the John Day Lock and Dam near Rufus, Oregon. The U.S. Army Corps of Engineers, Portland District is seeking to replace the existing 90-ton STS crane. The selected contractor will design, manufacture, test, transport, erect and test the new 130-ton outdoor gantry crane. Additional work includes deconstructing and removing the existing 90-ton crane. The new crane must be assembled and the existing crane dismantled in a manner that keeps one crane operational at all times to access the main units. Completion of the new crane is required by April 15, 2022, and existing crane removal is scheduled between August 1-31, 2022. This solicitation will use the FAR Part 15.101-1 Best Value Tradeoff process and provide for full and open competition. The primary point of contact is the listed contract specialist and secondary contact is the contracting officer, both located at the Portland District office.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL

W9127N20R0005

JOHN DAY DAM

SUBMERGED TRAVELING SCREEN (STS) CRANE

REPLACEMENT

PROJECT MANUAL

TOC-1

SUBMERGED TRAVELING SCREEN (STS) CRANE REPLACEMENT

JOHN DAY DAM

TABLE OF CONTENTS

A SOLICITATION/CONTRACT/ORDER FORM (SF 33)/AMENDMENT FORM (SF30)

B SUPPLIES OR SERVICE AND PRICES

C DESCRIPTION/SPECIFICATIONS

GENERAL AND TECHNICAL SPECIFICATION REQUIREMENTS

D INSPECTION AND ACCEPTANCE TERMS

E INSPECTION AND ACCEPTANCE TERMS

F DELIVERIES OR PERFORMANCE

G CONTRACT ADMINISTRATION DATA

H SPECIAL CONTRACT REQUIREMENTS

I CONTRACT CLAUSES

J LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

J1: Submittal Register (ENG Form 4288-R)

J2: Transmittal Form (ENG Form 4025-R)

K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS

L INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS

M EVALUATION FACTORS FOR AWARDS

J3: Transmittal Form (ENG Form 4025-R)

CODE

(Hour)

PAGE(S)

until 02:00 PM local time 27 Aug 2020

X

A X B X C

D

EX

X G F 42 - 49

50 - 67 X H 68 - 74

Melanie.A.Barrett@usace.army.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 74

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

W9127N 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

MELANIE A BARRETT

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 4

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

5 J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

7 - 8

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 9 - 10 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 11 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

12 - 31

PART II - CONTRACT CLAUSES

USACE PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204-3440

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

32 - 41

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

28 Jul 2020

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

W9127N20R0005

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Design New 130 Ton STS Gantry Crane

FFP

Design New 130 Ton Submerged Traveling Screen (STS) Gantry Crane for John Day Dam & Lock; Section 01 22 00.00 25, Paragraph 1.4.1; Supply CLIN.

FOB: Destination

PSC CD: 3950

NET AMT

0002 1 Job Manufacture & Deliver New Gantry Crane

FFP

Manufacture and Deliver New 130 Ton STS Gantry Crane; Section 01 22 00.00 25, Paragraph 1.4.2; Supply CLIN.

SECTION B-1

0003 1 Job Install & Testing of New STS Crane

FFP

Installation and Testing of New 130 Ton STS Gantry Crane, Section 01 22 00.00 25, Paragraph 1.4.3; Construction CLIN.

0004 1 Job Removal of Existing 90 Ton Gantry Crane

FFP

Removal of Existing John Day 90-Ton Gantry Crane, Section 01 22 00.00 25, Paragraph 1.4.4; Construction CLIN. Demolition of Existing crane shall occur between 01 August 2022 and 31 August 2022.

SECTION B-2

0005 1 Job Design New Lifting Beams - JD Dam Crane

FFP

Design New Auxiliary Lifting Beams for John Day Dam Crane, Section 01 22

00.00 25, Paragraph 1.4.5, Supply CLIN.

0006 1 Job Manufacture, Fabricate & Test Beams

FFP

Manufacture, Fabricate & Testing of New Auxiliary Lifting Beams for John Day Dam Crane, Section 01 22 00.00 25, Paragraph 1.4.6; Construction CLIN

SECTION B-3

Section C - Descriptions and Specifications

SUPPLY CONSTRUCTION CONTRACT

Contract Type The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

This is a firm fixed price hybrid Supply / Construction Contract.

Provisions and clauses applicable to Supply only apply to the supply of a new crane and lifting beams (CLINs 0001, 0002, and 0005).

Provisions and clauses applicable to construction only apply to the Construction installation of the supplied crane, removal of the existing crane, and installation of the lifting beams (CLINs 0003, 0004, and 0006).

Provisions and clauses that do not differentiate between supply and construction apply to all CLINs (i.e., all phases of the contract), when applicable.

SECTION C-1

John Day Submerged Traveling Screen (STS) Crane Replacement

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00.00 25 CONTRACT ADMINISTRATION DATA

01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS

01 11 00.00 25 SUMMARY OF WORK

01 22 00.00 25 MEASUREMENT AND PAYMENT

01 32 01.00 25 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 25 QUALITY CONTROL

01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 23.00 25 OPERATION AND MAINTENANCE DATA

01 78 39.00 25 PROJECT RECORD DOCUMENTS

DIVISION 02 - EXISTING CONDITIONS

02 41 16.00 26 REMOVAL AND DISPOSITION OF EXISTING GANTRY AND DELIVERY

OF NEW CRANE

DIVISION 05 - METALS

05 05 23.17 26 GANTRY CRANE AND LIFTING BEAM STRUCTURAL STEEL WELDING

AND FABRICATION

05 50 04.00 26 METALS: MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED

ITEMS

DIVISION 09 - FINISHES

09 97 02.00 26 PAINTING: HYDRAULIC STRUCTURES

DIVISION 22 - PLUMBING

22 15 14.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS, LOW PRESSURE

DIVISION 26 - ELECTRICAL

26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS

26 32 15.00 26 NEW SUBMERGED TRAVELING SCREEN (STS) GANTRY CRANE DIESEL

GENERATOR SET

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 01 20.71 26 SUBMERGED TRAVELING SCREEN (STS) GANTRY CRANE DATA,

TESTING AND TRAINING

41 01 20.73 26 NEW SUBMERGED TRAVELING SCREEN (STS) GANTRY CRANE

ELECTRICAL WORK

41 01 20.74 26 NEW SUBMERGED TRAVELING SCREEN (STS) GANTRY CRANE

MECHANICAL AND STRUCTURAL WORK

41 01 20.75 26 STRUCTURAL CRANE APPURTENANCES

41 22 13.76 26 NEW LIFTING BEAMS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION C-1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 00.00 25

CONTRACT ADMINISTRATION DATA

PART 1 GENERAL

1.1 REFERENCES

1.2 MEANING OF TERMS

1.3 CONTRACTING OFFICER

1.4 SERIAL LETTER CORRESPONDENCE

1.4.1 Numbering

1.4.2 Subcontractors

1.4.3 Transmittals

1.5 EM 385-1-1 SAFETY AND HEALTH REQUIREMENTS MANUAL

1.6 PROJECT-SPECIFIC MANAGEMENT PLAN

1.7 LETTERS OF AUTHORITY

1.8 LABOR STANDARDS

1.8.1 Coverage

1.8.2 Wages

1.8.3 Overtime

1.8.4 Deductions

1.8.5 Apprentices

1.8.6 Payrolls

1.8.7 Records

1.8.8 Job Interviews

1.9 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section Table of Contents --

SECTION 01 10 00.00 25 Page 1

SECTION C-2

SECTION 01 10 00.00 25

CONTRACT ADMINISTRATION DATA

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 MEANING OF TERMS

a. Specification Sections of this Contract are generally written in the imperative mood. In sentences using the imperative mood, the subject, "the Contractor," is implied. Also implied in this language are "shall," "shall be," "must," or similar words and phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.

b. Wherever "directed," "required," "prescribed," or other similar words are used, the "direction," "requirement," or "order" of the Contracting Officer is intended. Similarly, wherever "approved," "acceptable," "suitable," "satisfactory," or similar words are used, the words mean "approved by," "acceptable to," or "satisfactory to" the Contracting Officer.

c. The word "will" generally pertains to decisions or actions of the Contracting Officer.

1.3 CONTRACTING OFFICER

The Contracting Officer (CO) who signed this Contract is the primary Contracting Officer for the Contract. Nevertheless, any CO assigned to the Portland District and acting within his/her authority may take formal action on this Contract when a Contract action needs to be taken and the primary Contracting Officer is unavailable. All correspondence must be through the Contracting Officer or, upon notification, their authorized Representative (COR).

1.4 SERIAL LETTER CORRESPONDENCE

All letters must be electronically submitted to the Government and must be sent to designated parties via email and exported via the RMS interface.

All letters must be signed in accordance with the letters of authority.

Send any documents requiring original hardcopy/signatures to: Vancouver Resident Office, 4480 SE Columbia Way, Vancouver, WA 98661.

SECTION 01 10 00.00 25 Page 2

SECTION C-3

1.4.1 Numbering

All serial letter correspondence must be independently numbered sequentially with no numbers missing or duplicated, commencing with number one. Each letter must show the Contract number, description, and subject matter. Only one subject should be covered in the same letter.

1.4.2 Subcontractors

Subcontractors must not correspond with either the Resident or District offices; the Prime Contractor must handle all correspondence.

1.4.3 Transmittals

Transmittals of signed pay estimates, payrolls, submittals, and other similar correspondence will not require a Serial Letter.

1.5 EM 385-1-1 SAFETY AND HEALTH REQUIREMENTS MANUAL

The latest version in effect on the date of the Solicitation for this Contract (in accordance with EM 385-1-1 Paragraph 4 General, subparagraphs b.(1) and c.) will be contractually binding as part of this Contract. The latest version, including all errata and changes, must be used for this Contract and is obtainable at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals /EM_385-1-1.pdf .

1.6 PROJECT-SPECIFIC MANAGEMENT PLAN

Submit SD-01, Preconstruction Submittals (listed on the preliminary submittal register, Attachment A1, and defined in Section 01 33 00, SUBMITTAL PROCEDURES). The listed components of the Project-Specific Management Plan (PSMP) must be submitted separately under the appropriate specifications section. Upon approval, the components must be combined into a single PSMP binder that will be kept onsite. Update the PSMP whenever the plans contained within are updated or amended. The COR will periodically review the onsite copy of the PSMP. If a current version of the PSMP is not available and up to date, site work may be stopped until deficiencies are corrected. Acceptance of the PSMP is required prior to mobilization.

The PSMP must include:

a. Section I - Accident Prevention Program.

(1) Accident Prevention Plan ( EM 385-1-1 and Section 01 35 26.00 25, GOVERNMENTAL SAFETY REQUIREMENTS).

(2) Drug-free workplace policy.

(3) Global Harmonization program ( EM 385-1-1 ). Note: Replaces hazard communication program.

(4) Activity hazard analysis ( EM 385-1-1 ).

(5) Equipment certification.

b. Section II - Environmental Protection Plan (Section 01 57 19.00 25, TEMPORARY ENVIRONMENTAL CONTROLS).

SECTION 01 10 00.00 25 Page 3

SECTION C-4

c. Section III - Construction Quality Control System (Section 01 45 00.00 25, QUALITY CONTROL).

(1) Contractor's quality control (CQC) plan.

(2) CQC Daily Report form.

d. Project Work Plan. The following are examples:

(1) Roadway Access Agreement.

(2) Temporary electrical systems.

(3) Welder qualifications.

(4) Welding procedures.

(5) Bolt pre-tensioning procedure.

e. Schedule for Construction.

f. Submittal Register.

1.7 LETTERS OF AUTHORITY

a. To authenticate actions required under terms of this Contract, furnish a letter of authority to the CO and Resident Engineer that indicates the names of individual or individuals who are authorized to perform the following functions on behalf of the company:

(1) Sign progress payment estimates.

(2) Sign final payment estimate.

(3) Accept Government-furnished property (if applicable).

(4) Sign Contract modifications, supplemental agreements and consent of surety.

(5) Monitor and report on the environmental protection plan, management plan, quality control plan, and safety plan.

(6) Supervise the field activities.

(7) Sign Release of Claims.

(8) Sign Correspondence.

b. This letter of authority must bear the typewritten names and the handwritten signatures of each individual and be signed by the person whose signature appears on the final Contract.

1.8 LABOR STANDARDS

The Contractor and all subcontractors must comply with the following labor standards, statutes, and regulations: Davis-Bacon Act; Contract Work Hours and Safety Standards Act; Copeland Act; Secretary of Labor's regulations (Parts 3 and 5, Subtitle A, Title 29, Code of Federal Regulations). Submit

SECTION 01 10 00.00 25 Page 4

SECTION C-5

a serial letter identifying the crafts and wage rates for all prime and subcontractor employees to whom the contract's construction wage rate requirements apply. The Government will review these crafts and rates for conformance with the wage determination.

1.8.1 Coverage

Contract provisions relating to wages, overtime, payroll deductions, and other labor standards requirements cover foremen, laborers, and mechanics, including owner-operators of other than hauling equipment and other individual enterprises performing the duties of a laborer or mechanic.

Bona fide owner-operators of hauling equipment, such as trucks, who are independent contractors, are not covered, and the certified payrolls, including the names of such owner-operators, need not show hours worked nor rates paid, but only the notation "owner-operator".

1.8.2 Wages

Wages must be paid at least once a week and be computed at hourly rates not less than those set forth in the Contract wage schedule, as set by the Davis-Bacon Act wage determinations, for the particular classifications of work performed.

1.8.3 Overtime

Pay overtime for work in excess of 40 hours in any workweek at not less than 1-1/2 times the basic rate of pay. Rates paid for fringe benefits are excluded in the computations of overtime.

1.8.4 Deductions

Deductions from wages earned may be only those that are permitted by the Copeland Act (Anti-Kickback) regulations.

1.8.5 Apprentices

Comply with the requirements of 29 CFR 5.5(a)(4)(i) with respect to apprentices.

1.8.6 Payrolls

Prepare and submit correct Weekly Payrolls, including those of subcontractors. Incorrect and delinquent payrolls will delay processing of partial payment estimates.

1.8.7 Records

Maintain payroll and Employment Records during the course of work and for three years thereafter. They are subject to inspection by the Contracting Officer and the U.S. Department of Labor.

1.8.8 Job Interviews

A Government representative will interview Contractor and subcontractor employees from time to time during working hours on the job.

1.9 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, SECTION 01 10 00.00 25 Page 5

SECTION C-6

FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

a. U.S. Department of Labor Veterans employment: www.vets.gov/

b. Federal veteran employment information:

www.fedshirevets.gov/index.aspx

c. Veterans' Employment and Training Service (VETS):

http://www.dol.gov/vets/

d. Veterans Opportunity to Work (VOW) Program:

http://benefits.va.gov/vow/

e. U.S. Army Warrior Transition Command Employment Index:

http://www.wct.army.mil/modules/employers/index.html

f. Hiring Our Heroes initiative:

www.uschamberfoundation.org/hiring-our-heroes

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

SECTION 01 10 00.00 25 Page 6

SECTION C-7

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 10.00 25

CONTRACTOR'S OPERATIONS AND REQUIREMENTS

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.2 REFERENCES

1.3 SUBMITTALS

1.4 SCHEDULE FOR CONSTRUCTION

1.5 DEMOLITION OF EXISTING AND INSTALLATION OF NEW STS CRANE

1.6 CONCURRENT WORK AT JOHN DAY DAM

1.7 FINAL INSPECTION AND ACCEPTANCE TESTING SCHEDULE

1.8 ACCESS RESTRICTIONS

1.9 NOTIFICATION OF EQUIPMENT OUTAGE

1.10 NOTIFICATION OF EQUIPMENT OUTAGE TO BPA

1.11 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

1.12 INCLEMENT WEATHER CONSTRUCTION

1.13 WEEKLY COORDINATION MEETINGS

1.14 CONTRACTOR EMPLOYEES

1.15 PAGERS

1.16 ACCESS AGREEMENTS AND WORK AREAS

1.16.1 Access Agreements

1.16.2 Work Areas

1.16.3 Employee Access and Parking

1.17 SECURITY PROCEDURES

1.17.1 Project Security

1.17.2 Contractor's General Personnel

1.17.3 Verification of Employment Eligibility

1.17.4 Identification of Employees

1.17.5 Non-US Citizens

1.17.6 Safeguarding of Information

1.18 SUPPLEMENTAL SECURITY REQUIREMENTS

1.18.1 7 Year Criminal Background Check

1.18.2 NERC Critical Infrastructure Protection (CIP) Training

1.18.3 Quarterly NERC CIP Security Awareness Program

1.19 SECURITY TRAINING

1.20 DECK ACCESS RESTRICTIONS

1.21 CONSTRUCTION PROJECT IDENTIFICATION SIGN

1.22 UTILITIES

1.22.1 Sanitary Facilities

1.22.2 Electrical Power

1.22.2.1 General

1.22.2.2 Temporary Electrical Wiring

1.22.3 Telephone

1.22.4 Water

1.23 CONTRACTOR'S EQUIPMENT

1.23.1 Contractor's Planned Equipment Methods

1.23.2 Plant and Equipment List

1.23.3 Movement of Equipment by the Contractor

1.24 CONTRACTOR USE OF GOVERNMENT CRANES

1.25 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS

SECTION 01 10 10.00 25 Page 1

SECTION C-8

1.26 USE OF EXPLOSIVES

1.27 DAILY CLEANUP AND DISPOSAL

1.28 DISPOSAL AND SALVAGE OF EQUIPMENT AND MISCELLANEOUS MATERIALS

1.29 PROTECTION OF MATERIAL AND WORK

1.30 PROTECTION OF EXISTING UTILITIES

1.31 PROTECTION AND RESTORATION OF EXISTING FACILITIES

1.32 RESTORATION OF PROJECT ROADS

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section Table of Contents --

SECTION 01 10 10.00 25 Page 2

SECTION C-9

SECTION 01 10 10.00 25

CONTRACTOR'S OPERATIONS AND REQUIREMENTS

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

This Section covers general requirements applicable to specific Contractor's operations and equipment.

1.2 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

EP 310-1-6A (2006) Sign Standards Manual, VOL 1

U.S. DEPARTMENT OF TRANSPORTATION (DOT)

AASHTO LRFDUS (2012, ERTA 1) Bridge Design Specifications, 6th ed.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule for Construction; G

Access Agreements and Work Areas ; G

Security Procedures; G

Security Training; G

Temporary Electrical Wiring Plan; G

Contractor's Planned Equipment Methods; G

Plant and Equipment List; G

Loading Diagram; G

Notification Of Equipment Outage To BPA; G

Notification Of Equipment Outage

SECTION 01 10 10.00 25 Page 3

SECTION C-10

1.4 SCHEDULE FOR CONSTRUCTION

In accordance with Section 00 72 00 Contract Clause 52.236-15, SCHEDULES FOR CONSTRUCTION CONTRACTS, submit a schedule for accomplishing the work in this Contract. The schedule will not be used by the Government to select a Contractor; rather it will be used to ensure that the Contractor is capable of accomplishing the necessary work in the allotted time periods. The schedule must be consistent with the completion dates as specified in Section 00 73 00 Contract Clause 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK. Other Contractor's work must also be coordinated in accordance with Contract Clause 52.236-8, OTHER CONTRACTS.

1.5 DEMOLITION OF EXISTING AND INSTALLATION OF NEW STS CRANE

The new STS Gantry Crane must be assembled at the south end of the rails so that the existing STS gantry crane can be used by the Government to access all of the main units during the assembly of the new crane.

Demolition of the existing crane will also be at the approved south end of the rails as located on the contract drawings. This will block the new STS Gantry Crane at the south end taking both STS cranes out of service but this is necessary to keep the Intake Gantry Crane operational.

1.6 CONCURRENT WORK AT JOHN DAY DAM

The John Day Navlock is taken out of service every year during the month of March. Plan accordingly if barge transportation is to be used.

1.7 FINAL INSPECTION AND ACCEPTANCE TESTING SCHEDULE

Final Inspection and Acceptance testing for the crane shall not occur during the week of a Federal Holiday. The Final Inspection must begin on a Monday and start no earlier than 0800. Government personnel will be available for the Final Inspection and Acceptance testing for a maximum of 11 continuous hours in a 24 hour time period and work must be accomplished on a Monday through Thursday schedule. Coordination of schedule for the testing must be made with the Contracting Officer. Written approval to deviate from the above daily work hour restrictions or weekly schedule restrictions will be required from the Contracting Officer.

1.8 ACCESS RESTRICTIONS

a. During the construction and demolition phases of the work, road access across the top deck of the dam must be maintained outside of approved closure windows.

b. Road closure timing must be coordinated with the COR and Operations.

c. Foreign nationals must have their paperwork submitted in a timely manner, it can sometimes up to 60 days to process. Foreign nationals are not allowed to be on project until their security paperwork has been approved by district security. Please note that having a greencard is NOT the same as having citizenship and anyone who has a greencard will need to go through the same process as all other foreign nationals.

SECTION 01 10 10.00 25 Page 4

SECTION C-11

1.9 NOTIFICATION OF EQUIPMENT OUTAGE

Where an equipment outage is required to accomplish the work outlined in this contract, notify the Government 22 days in advance prior to the week of the work being conducting. This will allow the Government to de-energize the equipment for Contractor access.

1.10 NOTIFICATION OF EQUIPMENT OUTAGE TO BPA

For outages required to a generator or line, submit a request in writing to the CO at least 90 calendar days in advance of the time required.

1.11 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

The Government will limit interference with the Contractor's work to themaximum reasonable extent and the Government and Contractor will coordinate as necessary.

1.12 INCLEMENT WEATHER CONSTRUCTION

The Contractor's schedule must reflect adverse weather days in all weather dependent activities as defined in Contract Clause 52.236-4, PHYSICAL DATA. Protect work areas from inclement weather, wind damage, and precipitation so that no delay in the prosecution of critical work items, or damage to USACE property occurs. No time extensions will be authorized for materials, work in place, or equipment damaged due to negligence during periods of inclement weather.

1.13 WEEKLY COORDINATION MEETINGS

Weekly coordination meetings must be held between the Contractor and the Government. This meeting will be used to discuss Contractor's safety, Quality Control Program, submittals, deficiencies, Contract administration, schedule, actual progress in the last week, and work planned in the upcoming two weeks. Any work requiring Project support or potential impacts to Project operations or maintenance must be noted.

During the Preconstruction Meeting, the Government will determine responsibility of running this meeting. If the Government elects to run the coordination meeting, the Contractor must provide a two week look ahead, with the previous week as-builts, 48 hours before each weekly meeting to the Government representative. The responsible party must prepare and distribute, by e-mail, the coordination meeting agenda with a two week look ahead no later than 24 hours before each meeting. A meeting time and place will be mutually agreed upon for the same time each week.

Distribute weekly coordination meeting minutes no later than the close of business the next business day.

1.14 CONTRACTOR EMPLOYEES

Ensure that all employees are capable of demonstrating adequate knowledge of tools, supplies, equipment, and techniques necessary to competently perform the work. All personnel employed by the Contractor must be fully qualified in their respective fields to render the services necessary.

The Government may require the Contractor to discontinue using any employee in the performance of the work specified in this Contract determined by the Government to be unsatisfactory. Contractor employees will not be permitted to bring guests, family members, or non-employees to the job site at any time.

SECTION 01 10 10.00 25 Page 5

SECTION C-12

1.15 PAGERS

All Contractor employees who perform work on-site at John Day Dam must wear a pager that is fully compatible with the Project's message/transmitting and programming system (Turn-Key Technologies' TTI Ovation 3 Pager Receiver, Frequency 173.4875 mhz). This is a mandatory safety requirement that allows emergency notification of all persons within the Powerhouse and other work areas. No Contractor employee will be allowed to work on-Project without wearing a pager unless specifically so permitted by the CO. In the event of fire or other danger, the Control Room will notify all personnel by pager. Provide one pager for each employee, one week prior to working inside Powerhouse. The Project will program all pagers before site work begins. At the end of the onsite work, the pagers will become the property of the Government. If the pager receivers are lost, not operable, or substantially damaged through use, the Contractor must, at the Government's discretion, repair or replace the units at the Contractor's cost.

1.16 ACCESS AGREEMENTS AND WORK AREAS

1.16.1 Access Agreements

a. Submit access procedures to and from the work site after the Contractor, the Contracting Officer, and the Project's Representative have coordinated and determined the most advantageous access to, and staging of, the Contractor's assets deployed to the work site.

b. The right-of-way for the work (or delivery site) and access thereto will be furnished as stated in this paragraph subject to mutual agreement between the Contractor and the Government concerning the specific route the Contractor is to use. Such mutual agreement must be reached prior to initiation, construction, or delivery.

c. The existing access roadway and any associated access roads on the Project, must not be closed as a result of construction or delivery activities associated with this Contract unless previously coordinated and approved by the Government. Traffic delays will only be permitted in accordance with the provisions of this Section.

d. When necessary to operate on or to cross existing highways or roads, all necessary permits must be obtained from the appropriate private or public authority.

e. In accordance with Section 00 72 00 Contract Clause 52.236-13 Alt I, ACCIDENT PREVENTION - ALTERNATE I, and EM 385-1-1 , flaggers, signs, lights, and/or other safeguards must be provided to safely control and direct the flow of traffic when necessary for equipment to operate on or to cross access roads, arterial roads, or highways.

f. Spillage on Project roads and state or county roads will not be permitted, and the spillage must be immediately cleaned up at the expense of the Contractor.

g. No cleated or crawler-type equipment is to be operated on paved surfaces.

h. Damage to all roads caused by the Contractor's operations must be repaired to pre-existing conditions at the expense of the Contractor.

SECTION 01 10 10.00 25 Page 6

SECTION C-13

i. Road closure requests must be coordinated with the Contracting Officer's Representative (COR) and the Operations point of contact.

j. For longer term road closures, through access may be limited to the start, middle, and end of the work day.

k. At the end of the Contractor's work day the road access must be passable.

l. Operation of the Emergency Gantry Crane may require immediate removal of any interferences.

1.16.2 Work Areas

a. Drawings showing the layout of the area proposed for use must be submitted for review and approval and comply with Contract Clause 52.236-10 OPERATIONS AND STORAGE AREAS. The drawing(s) must show the location of the principal components: offices, access roads, parking, storage facilities and disposal areas, which the Contractor proposes to construct within the designated limits.

b. Only Contractor and subcontractor parts trailers and lunch trailers may be allowed in the Contractor work areas and these must be subject to CO and Project approval. All Contractor and subcontractor trailers are required to be adequately and physically anchored to prevent overturning due to high winds. Electrical supply for Contractor trailers is 480V, 30Amp, 3 Phase, ungrounded delta. Contractor must provide transformer. No water supply is available at the trailer area.

c. Should additional working space or lands within the Government right-of-way be required for material yards, job offices, or other purposes obtain prior Government approval in writing. When directed at any time during the progress of the work when space is needed within the right-of-way for other purposes, any part of the grounds that have been in use must be promptly vacated and cleaned up.

However, it is not the intent to require the Contractor's plant or material to be removed from an area while such plant, material, or area is still being actively used.

d. The Project staff will brief the Contractor on security procedures. Any such procedures will not be the basis for claims for additional money or time. The Project areas off limits to Contractor personnel will also be designated.

1.16.3 Employee Access and Parking

Contractor's employee private vehicle parking areas must be restricted to the area as agreed upon before construction or delivery. All Contractor vehicles used for prosecuting the work must have a Contractor sign or other permanent identification and must carry the required insurance.

Private vehicles not owned by the Prime Contractor or subcontractors must not be used for prosecuting the work. Private vehicles of the Contractor and its employees must enter and leave the project as directed. Keep the parking areas free of litter and debris. An adequate number and size of trash receptacles must be placed in the parking areas and emptied, as necessary to avoid overflowing. Trash receptacles must be adequately secured to provide protection from the wind and animals.

SECTION 01 10 10.00 25 Page 7

SECTION C-14

1.17 SECURITY PROCEDURES

1.17.1 Project Security

a. John Day and The Dalles Lock and Dams are not open to the public.

Security gates are locked and the Oregon access gate is manned at all times. Certain internal gates are locked at all times and require approved access to pass through. After crossing through any gate that is locked and unattended, all personnel are required to wait for the gate to close before proceeding. Notify the Control Room if the gate fails to close.

b. Arrangement and scheduling of working hours and crews must be coordinated through the CO with the Project Staff. The working hours of the Project Staff are Mondays through Thursdays from 6:30 a.m.

until 5:00 p.m. Fridays are non-working days. Working hours that extend past 5:00 p.m. weekdays or on weekends and holidays must be coordinated through the CO and approved by the Project Staff. Submit the intended working hours of staff on site and identify any employees working in any capacity in accordance with the subparagraph entitled Identification of Employees .

c. Security of the Contractor's property and items furnished under this Contract, until the Government accepts items, are the Contractor's responsibility.

d. All Contractor personnel, subcontractor personnel, suppliers, etc.

must comply with the Project's security policies. Salespersons or personnel seeking employment will not be permitted inside the Project. Costs associated with Contractor failure to comply with the Project security policies must be at the expense of the Contractor.

e. Salespersons, personnel seeking employment, and personal visitors are not authorized to enter non-public areas of the Project.

f. Signs may be erected outside the project containing instructions for personnel seeking the Contractor. The content and location of the signs will be approved by the CO prior to erection. Posts or other means of support, if required, must be provided by the Contractor and removed when the Contract is completed. Any open post holes must be suitably backfilled, prior to the end of the shift in which posts are removed, and any other damage must be repaired to preconstruction conditions.

1.17.2 Contractor's General Personnel

Prepare an organizational chart and revise whatever organizational changes occur. Maintain a complete organizational chart of all positions that will be working on the project.

1.17.3 Verification of Employment Eligibility

The Contractor is responsible to pre-screen Contractor and subcontractor personnel using the E-Verify Program at http://www.uscis.gov/E-verify to meet the established employment eligibility requirements. Two valid forms of Government issued identification will be required per individual to ensure the correct information is entered into the E-verify system.

SECTION 01 10 10.00 25 Page 8

SECTION C-15

Submit a roster of Contractor and subcontractor personnel with verified or eligible employment eligibility to the CO within three days of Notice to Proceed.

1.17.4 Identification of Employees

a. Submit a complete, dated and signed, list of all Contractor and subcontractor personnel and their titles who will be working on the project at the Weekly Coordination Meeting. This listing must be revised and resubmitted when personnel changes occur.

b. Each person requiring access for this contract must obtain Government-prescribed ID/access cards (and keys if applicable) from the Project security office. For each person requiring access, submit a Project-approved access request form and all accompanying documents to the Project security office not less than one week prior to the date when access is needed. For contracts requiring access for more than 10 employees starting in the same week, provide all documents not less than two weeks prior to the date when access is required.

c. Return of Government-prescribed cards/keys:

(1) Contractor must notify the Project security office immediately in the event of a termination for cause, reassignment, or a lost or stolen security item.

(2) Within 24 hours of personnel changes or the release of any employee and within seven days of the end of construction completion or termination of Contract, collect and return all Government-prescribed cards/keys to the Project Security Office.

Failure to return any Government-prescribed cards or keys will result in a $1000 per item charge to the Contractor and may delay final payment. These fees will be deducted from the Contractor's monthly payment at no additional cost to the Government.

d. Personnel Identity Verification (PIV) - All personnel, including visitors, must provide positive verification of individual identity, in the form of a valid government-issued photo ID prior to being granted access to non-public areas. Driver licenses that do not comply with the REAL ID Act of 2005 cannot be used as the sole source for identity proofing, and a second form of photo ID will be required. For details and current information, see the Department of Homeland Security website https://www.dhs.gov/secure-drivers-licenses .

e. Personally Identifiable Information (PII) - All transmissions containing PII must be encrypted or the document(s) containing PII must be encrypted or password protected. All documents containing PII must be sent directly to the Project RCC and/or Security Specialist.

1.17.5 Non-US Citizens

Submit a scanned legible color copy of the Permanent Resident Card and passport to the CO of all personnel who are non-US citizens working on this contract. The CO will provide the Portland District Security Office the submitted copies at least one month (30 calendar days) in advance of the start of work by the employees. Contractor personnel who are non-US citizens must not be permitted access to the Project until the Foreign Visitor Authorization is received from HQUSACE. Contractor personnel who are non-US citizens must not be permitted to work on the contract at all

SECTION 01 10 10.00 25 Page 9

SECTION C-16

until Foreign Visitor Authorization is received.

1.17.6 Safeguarding of Information

a. The personnel employed on this contract may, in the performance of their assigned duties, have access to data and information pertaining to location of goods, supplies, parts, equipment, and vehicles.

Knowledge of this nature is considered restricted security information. This information must be protected and safeguarded against disclosure to any unauthorized person or party and must be furnished or used on an official "need to know" basis only.

Safeguarding of information is extended to dependents and guests of employees who may, in any manner, obtain any of the above-specified knowledge.

b. The Contractor must coordinate with the CO for release of information to the public concerning this contract or any program related to this contract. This clause covers Media Relations and Printed Materials.

1.18 SUPPLEMENTAL SECURITY REQUIREMENTS

Powerhouses, security badging, and security monitoring areas are subject to additional security requirements, including those in NERC CIP-004, Personnel and Training. The following additional requirements apply where unescorted access to any of these areas is required. Documents specified below must be submitted along with the Project approved access request forms, not less than one week before the date when access is required. If unescorted access to these areas is required, the access request will not be processed until all required documentation has been provided.

1.18.1 7 Year Criminal Background Check

a. For each person requiring unescorted access to the Powerhouse or to designated security areas, Contractor must provide a seven-year criminal background check. All costs associated with obtaining the criminal background report must be at the expense of the Contractor.

The Project RCC or Security Specialist must review the report, and Project management will approve, disapprove, or revoke authorization for unescorted access based on the findings of the report.

b. The report must be based on a positive ID match using Social Security Number and/or fingerprints, and must include all of the following:

(1) State and county check for the current residence, regardless of duration, and for each jurisdiction where the subject has lived or worked for 6 months or longer during the seven years immediately preceding the investigation.

(2) A search of federal criminal records, a national crime index search of all US states and territories, and (where possible) an Office of Foreign Assets Control (OFAC) search for terrorists, narcotics traffickers, and blocked persons.

(3) For contracts extending beyond seven years, the seven year criminal background check must be updated at least once every seven years for personnel requiring unescorted access to Powerhouses or other areas subject to NERC CIP regulations.

SECTION 01 10 10.00 25 Page 10

SECTION C-17

1.18.2 NERC Critical Infrastructure Protection (CIP) Training

Prior to being authorized for unescorted access, and annually thereafter, each person requiring unescorted access to the Powerhouse or to designated security areas must review the Government-provided NERC CIP training material, and must complete the quiz with a passing score of not less than 70%. The Project RCC will provide the training, curriculum, and materials. Costs associated with the execution of this training must be at the expense of the contractor.

1.18.3 Quarterly NERC CIP Security Awareness Program

The Project maintains a quarterly awareness program for personnel requiring unescorted access to areas subject to NERC CIP regulations.

Awareness materials will be furnished by the Project Reliability Compliance Coordinator, and must be distributed to Contractor personnel by the Contractor. Costs associated with the distribution of the security awareness documents must be at the expense of the Contractor.

1.19 SECURITY TRAINING

Costs associated with the following execution of training and verification requirements must be at the expense of the Contractor. Facilitate the following training and submit the following:

a. AT Level 1 Training - Thirty calendar days prior to mobilization, all Contractor employees, to include subcontractor employees, requiring access to army installations, facilities, and controlled access areas must complete AT Level 1 Training. Submit a roster of training completion for each Contractor employee and subcontractor employee to the CO within five calendar days after completion of training of all employees and subcontractor personnel. Obtain training DVD from the CO through the Portland District Security Office. (Estimated training time is ten minutes per individual).

b. iWATCH or CorpsWatch Training - Thirty calendar days prior to mobilization, all Contractor employees, to include subcontractor employees, requiring access to army installations, facilities, and controlled access areas must complete iWatch or CorpsWatch Training.

Submit a roster of training completion for each Contractor employee and subcontractor employee to the CO within five calendar days after completion of training of all employees and subcontractor personnel.

Obtain training DVD from the CO through the Portland District Security Office. (Estimated training time is five minutes per individual).

c. Operations Security (OPSEC) Training - Thirty calendar days prior to mobilization, all Contractor employees, to include subcontractor employees, requiring access to army installations, facilities, and controlled access areas must complete OPSEC Training. Submit a roster of training completion for each Contractor employee and subcontractor employee to the CO within five calendar days after completion of training of all employees and subcontractor personnel. Obtain training DVD from the CO through the Portland District Security Office. (Estimated training time is 15 minutes per individual).

SECTION 01 10 10.00 25 Page 11

SECTION C-18

1.20 DECK ACCESS RESTRICTIONS

Do not block operational areas of the deck gantry crane at any time. With prior coordination and approval, the deck gantry crane may be blocked for a period no longer than four hours. One lane of traffic must be left open at all times.

1.21 CONSTRUCTION PROJECT IDENTIFICATION SIGN

Fabricate and install one construction project identification sign in accordance with EP 310-1-6A , Attachment A3, within three days of beginning site work.

1.22 UTILITIES

Provide utilities required for the performance of work under this Contract, except Government-furnished electrical power, and water as described below.

1.22.1 Sanitary Facilities

Use of the Project restroom by Contractor personnel will not be permitted. Provide portable, temporary sanitary facilities in accordance with EM 385-1-1 .

1.22.2 Electrical Power

1.22.2.1 General

Use of existing 120V and 480V electrical receptacles is allowed. Take special care not to overload receptacle circuits. Contractor must be responsible for all accessories, such as extension cords, adapters, and raceways for road crossings. Extension cords must not be allowed to cross crane rails.

1.22.2.2 Temporary Electrical Wiring

Submit a Temporary Electrical Wiring Plan for temporary electrical wiring. Install all temporary electrical wiring in accordance with EM 385-1-1 and as approved. All temporary electrical wiring must be removed prior to completion of the Contract. Include load calculations to ensure conduit capacity is not exceeded.

1.22.3 Telephone

Telephone will not be available for Contractor use.

1.22.4 Water

Reasonable amounts of water for domestic use will be made available from existing outlets and supplies. No charge will be made for the water.

1.23 CONTRACTOR'S EQUIPMENT

1.23.1 Contractor's Planned Equipment Methods

Submit proposed methods of transportation and operation of cranes and other heavy equipment for approval prior to commencement of those operations. Submittals must include the type, size, loadings of

SECTION 01 10 10.00 25 Page 12

SECTION C-19

equipment, placement of outriggers, and the proposed transportation routes and work areas to be used on the project. Operation of heavy equipment adjacent to existing structures must be avoided when possible. Testing requirements and operation of cranes and other heavy equipment must be in accordance with EM 385-1-1 . All cranes, rigging, lifts, operators, vehicles, and other necessary means to move equipment or items must be Contractor-furnished as required to pursue and complete the work and must comply with EM 385-1-1 .

1.23.2 Plant and Equipment List

Within seven days prior to commencing site operations, provide a complete list of all plant and equipment to be used on the job site, exclusive of shop equipment. Throughout the life of the Contract, submit an up-to-date plant and equipment list with each progress payment request. Include rented equipment as well as lease purchase or sale leaseback equipment on the lists. Initial list and the revised monthly lists must indicate dates equipment is assigned to or removed from the project; deadline dates for repairs and returned for use; dates of the most recent and planned inspections; and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.

1.23.3 Movement of Equipment by the Contractor

a. Unless otherwise noted, any vehicle crossing a project bridge is limited to AASHTO LRFDUS, HL-93 vehicle and load requirements. Submit a loading diagram for approval showing wheel loads, wheel spacing, and travel speed a minimum of 30 days prior to operating any equipment or vehicles whose loading conditions are in excess of a HL-93 vehicle.

Prior coordination and approval for such loads must be obtained before proceeding. No exclusion trucks, multi-axle specialized hauling vehicles (SHV) or mobile cranes will be allowed on a bridge deck without prior review and approval. At a minimum, the loading diagram must include but not be limited to the following information:

(1) A typical section and plan view of the bridge, the position of the wheel loads and wheel spacing of the truck or crane.

(2) The GVW of the vehicle and all axle weights.

(3) For cranes, the location and weight of axles before and after counter weights are installed, all outrigger loads, required crane boom length, weight and location of center of gravity. This should also include the effects of guy lines, upper spreader and jib mast. If using a jib, show the length, weight, and location of the center of gravity.

b. Any SHV's authorized to drive on the bridge deck…

This is the start of the file's text. The full file is on GovTribe.