This is a Statement of Work (SOW) for repairing the cooling system in building 556 at Grand Forks Air Force Base. The primary objective is to rent a 55-ton chiller from 16 June 2025 to 03 November 2025 to address a failing cooling system that is insufficient for the building's new occupants. The contractor must provide and install the chiller, connecting it to the existing chilled water loop and power supply with 480v/3 ph/60 Hz electrical connection, using existing penetrations in the mechanical room.
Key requirements include placing the rental chiller in a specified laydown area without damaging landscaping, performing all necessary preventative maintenance, and coordinating maintenance visits with the government technical representative at least one week in advance. The contractor must also obtain all required permits, comply with base security regulations, obtain visitor passes, and be prepared to stop work and contact representatives immediately if any suspected hazardous materials are discovered during the project. The chiller must meet specific technical specifications, including maintaining a 10℉ temperature drop and 10' max head loss across the system, with a flow rate of 200 gpm.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 of 6 JFSD250007 Repair Cooling Ops Town for Operations 25
March 2025, rev2 13 May 2025
STATEMENT OF WORK
Repair Cooling Ops Town for Operations JFSD250007
Rev.2 13 May 2025
1. GENERAL: The contractor shall provide all materials, plans, labor, equipment, and supervision necessary to do the following:
1.1. This project’s purpose is to address the failed cooling system in building 556, located at 656 Alert Ave, Grand Forks AFB, ND 58205. The existing cooling system is failing, beyond its useful life, and insufficient for the cooling needs of the new occupants. The primary feature of this effort is the rental of an appropriately sized chiller for the estimated period of 16 June 2025 to 03 November 2025 and install within submitted quote and evaluated by the government to be found acceptable.
2. PRINCIPAL FEATURES: The work to be performed includes, but is not limited to, the following:
2.1.1. Services
2.1.1.1. Provide a chiller that can provide at least 55 tons of cooling.
2.1.1.1.1. Connect rental chiller to facility chilled water loop and power
2.1.1.1.1.1. Existing chiller power is available at the existing chiller shutoff switch. Use existing penetrations into mechanical room (See 18. Figure 3). Existing power is 480v/3 ph/60 Hz, on a 120A circuit breaker. Electrical connection point is within 50’ of chiller laydown location.
2.1.1.1.1.2. Connection to chilled water loop should be made inside the mechanical room. Use existing penetrations into mechanical room to connect at existing shutoff switch (see 18.
Figures 3 and 4). Existing chilled water loop uses grooved pipe and couplings, and has a 10℉ temperature drop and 10’ max head loss across the chiller. Existing chiller water system flow rate is 200 gpm. Chilled water connection points are within 50’ of chiller laydown location.
2.1.1.1.1.3. Place rental chiller in the location specified on the photos in 18. Figure 1. Avoid damaging landscaping. Contractor shall repair any damages made to landscaping during rental chiller placement and removal.
2.1.1.1.1.4. Perform all required preventative maintenance during rental period. Coordinate visits with government technical representative at least 1 week in advance.
2.1.1.1.1.5. Remove chiller and associated connections at the end of the rental period.
3. CONSTRUCTION/SITE MANAGEMENT: The contractor shall perform a pre-work inspection of the work area.
Items not within the scope of the task order but found to be in defective shall be documented and sent to the government’s technical representative. Any damage that occurs as a result of the contractor’s work shall be repaired and returned to conditions matching those before the contractor began work on this task order. The Contractor shall
2 of 6 JFSD250007
March 2025, rev2 13 May 2025 coordinate with the Contracting Officer (CO) and Civil Engineering (CE) personnel to the extent necessary to provide area access. This coordination shall be completed and approved by CES 319 and the CO prior to the start of on-site work. Preliminary site investigations shall be coordinated with the CO.
4. PERMITS: The contractor shall obtain all applicable construction permits for each task order, including but limited to utility prints for the work site, welding and burn permits, and any permits of licenses required for the removal of hazardous materials. An AF Form 103, Base Civil Engineer Work Clearance Request, must be submitted and approved through CE Customer Service and submitted to the CO prior to beginning any on-site work. Contact CE Customer Service at 319ces.ceoer.customerservice@us.af.mil or 701-747-5210 to start the AF 103.
5. HAZARDOUS MATERIALS: It is not anticipated that this work include hazardous material remediation. Records indicate that these facilities may contain hazardous materials. If a suspected hazardous material is discovered during this effort, stop work and contact 319 CES representative immediately at 319ces.ceoer.customerservice@us.af.mil or 701-747-5210.
6. GENERAL SECURITY: Security requirements for Air Force facilities under control of Grand Forks Air Force Base are specific and rigidly enforced. Levels of security include Restricted and Controlled areas. Differing degrees of security are enforced at each area. Minimum security requirements, common not only to each of these secure areas, are also required for entry onto Grand Forks AFB. These minimum requirements are outlined below.
7. RESTRICTED AREAS: Restricted areas identified in GFAFBI 31-101 include the Command Post (CP) and Mass
Parking Area (MPA). Each area is fenced or conspicuously identified by posted signs.
8. CONTROLLED AREAS: Controlled areas include more than 33 user-controlled base facilities; only a few of which include all hangars, buildings, and communications facilities located within the base aircraft flight-line controlled area.
Each of these areas is identified in GFAFBI 31-101 and is conspicuously identified by posted signs.
8.1. Free Zone: Not Used
9. PROJECT AREA: This contract will entail work in Base Entry only.
10. MINIMUM SECURITY REQUIREMENTS (All Areas Including Base Entry):
10.1. Visitor Passes: The Commercial Visitor Control Center will issue a 319 SFS/SFSP SF Form 74 (Visitor Pass) to the contractor and contractor employees upon completion of the screening process for the duration of contract.
Coordinate with the government’s technical representative Ryan McDaniel at ryan.mcdaniel.12@us.af.mil or 7017473814.
10.1.1. Although contractors will not be issued vehicles passes, vehicles are subject to search while on the installation. Contractor personnel are required to obtain a contractor visitor pass.
11. CONDUCT REQUIREMENTS: The contractor’s employees shall comply with all base traffic regulations and properly conduct themselves while on this base.
12. RESTRICTIONS: When working on base, all security regulations shall be obeyed.
13. PHOTOS:
mailto:319ces.ceoer.customerservice@us.af.mil mailto:319ces.ceoer.customerservice@us.af.mil mailto:ryan.mcdaniel.12@us.af.mil
3 of 6 JFSD250007
Figure 1 Chiller Laydown Area
N
Rental chiller laydown
Mechanical room
4 of 6 JFSD250007
Figure 2 Mechanical Room Location
N
Existing chiller and shutoff
5 of 6 JFSD250007
Figure 3 Existing Penetrations (existing lines will be demo'd)
6 of 6 JFSD250007
Figure 4 Chiller Shutoff Switch
File details come from the government source that posted it. Updated .