JB2601 Project List cao20251203.xlsx
XLSX spreadsheet 11 KB Posted
- Solicitation number
- JB2601
About this file
This document is a fiscal year 2026 construction forecast spreadsheet for Jefferson Barracks Air National Guard Station (ANGS) in St. Louis, Missouri, detailing multiple small business construction and repair projects. The forecast includes eight distinct projects ranging in estimated value from less than $25,000 to between $1-5 million, with anticipated solicitation releases scheduled across FY26 Q2-Q4. Projects encompass various facility improvements including vehicle parking structures with solar panels, roof and window repairs, HVAC replacements, mechanical system upgrades, and interior renovations for different buildings within the facility.
The special notice accompanying the spreadsheet indicates these are preliminary project forecasts subject to potential revision, targeting small business contractors. Interested vendors are encouraged to submit company information including SAM UEI Number, project bonding capacity, and in-house capabilities. The projects will be procured through different acquisition methods including sealed bid and simplified acquisition procedures, with set-aside status designated for small businesses. The contracting office is with the 131st Mission Support Group, under the Department of the Army Missouri Army National Guard, with project completion periods ranging from 45 to 260 days after notice to proceed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JB2601 Project List cao20260904.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260807.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260703.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260605.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260501.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260210.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FY26 Construction Forecast: Jefferson Barracks ANGS, St. Louis MO | |||||||
| Project Number | Project Title | Description | Disclosure of Magnitude | Solicitation No. | Solicitation Method | Set-Aside | Status/Anticipated Solicitation Release |
| LTUY202005 | Construct Vehicle Operations Covered Parking | Construct two covered parking structures with rooftop solar panels in existing parking lot adjacent to Building 41, Jefferson Barracks ANGS. The performance period for completion will be 260 days after issue of NTP. | Between $1M and $5M | TBD | Sealed Bid | Small Business | FY26 Q3 |
| LTUY202057 | Repair Roof, Roads & Grounds Facility, B99 | Replace roofing shingles, restore siding to historical appearance, added vented soffits to roof structure, and make misc. repairs to Building 99, Jefferson Barracks ANGS. The performance period for completion will be 180 days after issue of NTP. | Between $500K and $1M | TBD | Sealed Bid | Small Business | FY26 Q3 |
| LTUY202129 | Repair B290 Boiler | Replace existing boiler and make associated repairs to mechanical room piping in Building 290, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP. | Between $25K and $100K | W50S8K26RA001 | Simplified Acquisition Request for Proposal | TBD | FY26 Q2 |
| LTUY232044 | Bldg 1, 28 and 36 Windows, 37 Dormer Repair | Repair/replace damaged windows in multiple buildings and make repairs to water damaged dormer on Building 37, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP. | Between $25K and $100K | TBD | Simplified Acquisition Request for Proposal | TBD | FY26 Q3 |
| LTUY242008 | Replace B28 and B280 Shower Stalls | Replace shower stall finishes in multiple buildings for quality of life improvements for AOG personnel in Buildings 28 & 280, Jefferson Barracks ANGS. The performance period for completion will be 90 days after issue of NTP. | Less than $25K | TBD | Simplified Acquisition Request for Proposal | TBD | FY26 Q4 |
| LTUY252017 | Repair Bldg 50 for CES and CBCS Consolidation | Renovate building interior to configure space for consolidated power production shop of 131st Civil Engineer Squadron and 239th Combat Communications Squadron at Building 50, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP. | Between $25K and $100K | TBD | Simplified Acquisition Request for Proposal | TBD | FY26 Q3 |
| LTUY252022 | Repair B37 ATS Reprogramming | Repair automatic transfer switch wiring so genrator properly turns on during power outages to Building 37, Jefferson Barracks ANGS. The performance period for completion will be 45 days after issue of NTP. | Less than $25K | TBD | Simplified Acquisition Request for Proposal | TBD | FY26 Q3 |
| LTUY262003 | Replace Bldg 37 AHU | Replace HVAC air handling unit in Building 37, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP. | Less than $25K | TBD | Simplified Acquisition Request for Proposal | TBD | FY26 Q2 |