JB2601 Project List cao20260605.xlsx
XLSX spreadsheet 19 KB Posted
- Solicitation number
- JB2601
About this file
This is a project list spreadsheet supporting a FY26 Construction Forecast special notice for Jefferson Barracks Air National Guard Station (ANGS) in St. Louis, Missouri, issued by the 131st Mission Support Group Contracting Office under Solicitation Number JB2601. The spreadsheet details upcoming construction and repair contract opportunities planned for execution throughout fiscal year 2026, with projects subject to revision or cancellation. The notice has been updated multiple times, most recently on 5 June 2026, to reflect project status changes, awarded projects, updated solicitation numbers, and revised set-asides based on new RFO FAR procedures.
Interested small businesses are invited to submit their SAM UEI Number, single project and aggregate bonding capacity, and summary of in-house capabilities via email to the designated points of contact. There is no submission deadline for this preliminary interest notification. The special notice is informational only and does not constitute a commitment to award contracts or establish binding procurement terms. Final determinations regarding competition scope, small business set-asides, estimated contract values, and execution methods will be made when individual solicitations are posted to SAM.gov. Planned execution methods have been updated to incorporate commercial services RFQ procedures rather than traditional sealed bidding approaches.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JB2601 Project List cao20260904.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260807.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260703.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260501.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260210.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20251203.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FY26 Construction Forecast: Jefferson Barracks ANGS, St. Louis MO | |||||||
| Project Number | Project Title | Description | Disclosure of Magnitude | Solicitation No. | Solicitation Method | Set-Aside | Status/Anticipated Solicitation Release |
| LTUY202005 | Construct Vehicle Operations Covered Parking | Construct two covered parking structures with rooftop solar panels in existing parking lot adjacent to Building 41, Jefferson Barracks ANGS. The performance period for completion will be 260 days after issue of NTP. | Between $500K and $1M | W50S8K26QA002 | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | FY26 Q3 |
| LTUY202057 | Repair Roof, Roads & Grounds Facility, B99 | Replace roofing shingles, restore siding to historical appearance, added vented soffits to roof structure, and make misc. repairs to Building 99, Jefferson Barracks ANGS. The performance period for completion will be 180 days after issue of NTP. | Between $500K and $1M | TBD | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | FY26 Q3 |
| LTUY202129 | Repair B290 Boiler | Replace existing boiler and make associated repairs to mechanical room piping in Building 290, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP. | Between $25K and $100K | W50S8K26RA001 | Simplified Acquisition Request for Proposal | Small Business | Awarded |
| LTUY232044 | Bldg 1, 28 and 36 Windows, 37 Dormer Repair | Repair/replace damaged windows in multiple buildings and make repairs to water damaged dormer on Building 37, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP. | Between $25K and $100K | TBD | Commercial Simplified Procedures RFQ (RFO FAR) | TBD | FY26 Q3 |
| LTUY242008 | Replace B28 and B280 Shower Stalls | Replace shower stall finishes in multiple buildings for quality of life improvements for AOG personnel in Buildings 28 & 280, Jefferson Barracks ANGS. The performance period for completion will be 90 days after issue of NTP. | Less than $25K | TBD | Commercial Simplified Procedures RFQ (RFO FAR) | TBD | FY26 Q4 |
| LTUY252017 | Repair Bldg 50 for CES and CBCS Consolidation | Renovate building interior to configure space for consolidated power production shop of 131st Civil Engineer Squadron and 239th Combat Communications Squadron at Building 50, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP. | Between $25K and $100K | TBD | Commercial Simplified Procedures RFQ (RFO FAR) | TBD | FY26 Q3 |
| LTUY252022 | Repair B37 MTS | Repair transfer switch wiring so generator properly turns on during power outages to Building 37, Jefferson Barracks ANGS. The performance period for completion will be 45 days after issue of NTP. | Less than $25K | W50S8K26QA001 | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | Solicitation Closed |
| LTUY262003 | Replace Bldg 37 AHU | Replace HVAC air handling unit in Building 37, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP. | Less than $25K | N/A | Simplified Acquisition Request for Proposal | Small Business | Awarded - Internal IDIQ |