JB2601 Project List cao20260904.xlsx
XLSX spreadsheet 19 KB Posted
- Solicitation number
- JB2601
About this file
This is a FY26 construction forecast special notice and project list for the 131st Mission Support Group Contracting Office at Jefferson Barracks Air National Guard Station in St. Louis, Missouri. The notice forecasts eight construction and repair projects with estimated values ranging from less than $25,000 to $1 million. All projects are set aside for small businesses and will be executed using Commercial Simplified Procedures with RFQs under the RFO FAR framework, except for two projects utilizing Simplified Acquisition Requests for Proposals.
The projects include: (1) constructing two covered parking structures with rooftop solar panels (LTUY202005, $500K–$1M, 260-day performance period, Solicitation W50S8K26QA002, Closed); (2) repairing roof, roads, and grounds at Building 99 (LTUY202057, $400K–$600K, 180 days, W50S8K26QA003, Closed); (3) replacing a boiler in Building 290 (LTUY202129, $25K–$100K, 60 days, W50S8K26RA001, Awarded); (4) repairing/replacing windows in multiple buildings and dormer repairs (LTUY232044, $25K–$100K, 120 days, W50S8K26QA004, Closed); (5) replacing shower stall finishes (LTUY242008, <$25K, 90 days, Cancelled); (6) renovating Building 50 for consolidation (LTUY252017, $25K–$100K, 120 days, Cancelled); (7) repairing a transfer switch in Building 37 (LTUY252022, <$25K, 45 days, W50S8K26QA001, Awarded); and (8) replacing an HVAC unit in Building 37 (LTUY262003, <$25K, 60 days, Awarded through Internal IDIQ). Interested vendors must submit SAM UEI numbers, bonding capacity information, and in-house capability summaries via email; there is no submission deadline. The special notice has been updated multiple times through September 2026 to reflect project status changes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JB2601 Project List cao20260807.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260703.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260605.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260501.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20260210.xlsx | XLSX spreadsheet | |
| JB2601 Project List cao20251203.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FY26 Construction Forecast: Jefferson Barracks ANGS, St. Louis MO | |||||||
| Project Number | Project Title | Description | Disclosure of Magnitude | Solicitation No. | Solicitation Method | Set-Aside | Status/Anticipated Solicitation Release |
| LTUY202005 | Construct Vehicle Operations Covered Parking | Construct two covered parking structures with rooftop solar panels in existing parking lot adjacent to Building 41, Jefferson Barracks ANGS. The performance period for completion will be 260 days after issue of NTP. | Between $500K and $1M | W50S8K26QA002 | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | Solicitation Closed |
| LTUY202057 | Repair Roof, Roads & Grounds Facility, B99 | Replace roofing shingles, restore siding to historical appearance, added vented soffits to roof structure, and make misc. repairs to Building 99, Jefferson Barracks ANGS. The performance period for completion will be 180 days after issue of NTP. | Between $400K and $600K | W50S8K26QA003 | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | Solicitation Closed |
| LTUY202129 | Repair B290 Boiler | Replace existing boiler and make associated repairs to mechanical room piping in Building 290, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP. | Between $25K and $100K | W50S8K26RA001 | Simplified Acquisition Request for Proposal | Small Business | Awarded |
| LTUY232044 | Bldg 1, 28 and 36 Windows, 37 Dormer Repair | Repair/replace damaged windows in multiple buildings and make repairs to water damaged dormer on Building 37, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP. | Between $25K and $100K | W50S8K26QA004 | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | Solicitation Closed |
| LTUY242008 | Replace B28 and B280 Shower Stalls | Replace shower stall finishes in multiple buildings for quality of life improvements for AOG personnel in Buildings 28 & 280, Jefferson Barracks ANGS. The performance period for completion will be 90 days after issue of NTP. | Less than $25K | TBD | Commercial Simplified Procedures RFQ (RFO FAR) | TBD | Cancelled |
| LTUY252017 | Repair Bldg 50 for CES and CBCS Consolidation | Renovate building interior to configure space for consolidated power production shop of 131st Civil Engineer Squadron and 239th Combat Communications Squadron at Building 50, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP. | Between $25K and $100K | TBD | Commercial Simplified Procedures RFQ (RFO FAR) | TBD | Cancelled |
| LTUY252022 | Repair B37 MTS | Repair transfer switch wiring so generator properly turns on during power outages to Building 37, Jefferson Barracks ANGS. The performance period for completion will be 45 days after issue of NTP. | Less than $25K | W50S8K26QA001 | Commercial Simplified Procedures RFQ (RFO FAR) | Small Business | Awarded |
| LTUY262003 | Replace Bldg 37 AHU | Replace HVAC air handling unit in Building 37, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP. | Less than $25K | N/A | Simplified Acquisition Request for Proposal | Small Business | Awarded - Internal IDIQ |
File details come from the government source that posted it. Updated .