JB2601 Project List cao20260210.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
FY26 Construction Forecast: Jefferson Barracks ANGS, St. Louis MO
Solicitation number
JB2601
Issued by

About this file

This is a FY26 Construction Forecast special notice and project list for Jefferson Barracks Air National Guard Station (ANGS) in St. Louis, Missouri, posted by the 131st Mission Support Group Contracting Office. The forecast encompasses eight construction and repair projects with estimated values ranging from less than $25,000 to between $1 million and $5 million. Key projects include: constructing two covered parking structures with rooftop solar panels (LTUY202005, $1M-$5M, 260-day performance period); repairing roof, roads, and grounds at Building 99 (LTUY202057, $500K-$1M, 180-day performance period); replacing a boiler at Building 290 (LTUY202129, $25K-$100K, awarded under solicitation W50S8K26RA001); repairing windows and dormers across multiple buildings (LTUY232044, $25K-$100K); and replacing shower stalls (LTUY242008, less than $25K). Additional smaller projects include renovating Building 50 for Civil Engineer Squadron and Combat Communications Squadron consolidation, repairing automatic transfer switch wiring, and replacing HVAC equipment. All procurements are set aside for small businesses and utilize Commercial Simplified Procedures with RFQs under FAR procedures, with anticipated release dates primarily in FY26 Q3 and Q4. Interested vendors must submit their SAM UEI number, bonding capacity, and in-house capabilities summary via email to the contracting office, with no submission deadline. The notice explicitly states that all projections are subject to revision or cancellation and are for informational purposes only.

View the file

Other files

File Type Posted
JB2601 Project List cao20260904.xlsx XLSX spreadsheet
JB2601 Project List cao20260807.xlsx XLSX spreadsheet
JB2601 Project List cao20260703.xlsx XLSX spreadsheet
JB2601 Project List cao20260605.xlsx XLSX spreadsheet
JB2601 Project List cao20260501.xlsx XLSX spreadsheet
JB2601 Project List cao20251203.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

FY26 Construction Forecast: Jefferson Barracks ANGS, St. Louis MO
Project NumberProject TitleDescriptionDisclosure of MagnitudeSolicitation No.Solicitation MethodSet-AsideStatus/Anticipated Solicitation Release
LTUY202005Construct Vehicle Operations Covered ParkingConstruct two covered parking structures with rooftop solar panels in existing parking lot adjacent to Building 41, Jefferson Barracks ANGS. The performance period for completion will be 260 days after issue of NTP.Between $1M and $5MTBDCommercial Simplified Procedures RFQ (RFO FAR)Small BusinessFY26 Q3
LTUY202057Repair Roof, Roads & Grounds Facility, B99Replace roofing shingles, restore siding to historical appearance, added vented soffits to roof structure, and make misc. repairs to Building 99, Jefferson Barracks ANGS. The performance period for completion will be 180 days after issue of NTP.Between $500K and $1MTBDCommercial Simplified Procedures RFQ (RFO FAR)Small BusinessFY26 Q3
LTUY202129Repair B290 BoilerReplace existing boiler and make associated repairs to mechanical room piping in Building 290, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP.Between $25K and $100KW50S8K26RA001Simplified Acquisition Request for ProposalSmall BusinessAwarded
LTUY232044Bldg 1, 28 and 36 Windows, 37 Dormer RepairRepair/replace damaged windows in multiple buildings and make repairs to water damaged dormer on Building 37, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP.Between $25K and $100KTBDCommercial Simplified Procedures RFQ (RFO FAR)TBDFY26 Q3
LTUY242008Replace B28 and B280 Shower StallsReplace shower stall finishes in multiple buildings for quality of life improvements for AOG personnel in Buildings 28 & 280, Jefferson Barracks ANGS. The performance period for completion will be 90 days after issue of NTP.Less than $25KTBDCommercial Simplified Procedures RFQ (RFO FAR)TBDFY26 Q4
LTUY252017Repair Bldg 50 for CES and CBCS ConsolidationRenovate building interior to configure space for consolidated power production shop of 131st Civil Engineer Squadron and 239th Combat Communications Squadron at Building 50, Jefferson Barracks ANGS. The performance period for completion will be 120 days after issue of NTP.Between $25K and $100KTBDCommercial Simplified Procedures RFQ (RFO FAR)TBDFY26 Q3
LTUY252022Repair B37 ATS ReprogrammingRepair automatic transfer switch wiring so genrator properly turns on during power outages to Building 37, Jefferson Barracks ANGS. The performance period for completion will be 45 days after issue of NTP.Less than $25KTBDCommercial Simplified Procedures RFQ (RFO FAR)TBDFY26 Q3
LTUY262003Replace Bldg 37 AHUReplace HVAC air handling unit in Building 37, Jefferson Barracks ANGS. The performance period for completion will be 60 days after issue of NTP.Less than $25KTBDSimplified Acquisition Request for ProposalTBDAwarded - Internal IDIQ