J2. Operational Risk Management Plan.pdf
PDF 451 KB Posted
- Attached to
- TMB ATCT Rehabilitation Federal contract opportunity
- Solicitation number
- 697DCK-22-R-00166
About this file
This document contains an operational risk management plan and related federal contract solicitation for repairs to the Miami Executive Airport Air Traffic Control Tower. Key details include the identification of various construction risks such as use of heavy equipment, demolition, roofing and electrical work. Mitigation actions are defined including coordination of activities, use of protective equipment, shutdown of systems and compliance with permits. The federal contract opportunity is solicitation number 697DCK-22-R-00166 from the Federal Aviation Administration seeking proposals for repairs to the Miami Executive Airport Air Traffic Control Tower located in Miami, Florida. Proposals are due by the date specified in the solicitation. Offerors must be registered in the System for Award Management to be eligible for award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI Set 2.pdf | ||
| RFI Set 2 Photos.pdf | ||
| 697DCK-22-R-00166 Amend 0002.pdf | ||
| RFI Set 1.pdf | ||
| 697DCK-22-R-00166 0001.pdf | ||
| J1. TMB ATCT Facility Rehab Final Specifications 12.01.20.pdf | ||
| J1a. TMB - Addendum #1 - 031721.pdf | ||
| L1. BidBond.pdf | ||
| J1b. TMB ATCT Facility Rehab Final Drawings 12.01.20.pdf | ||
| L3. Price Proposal - TMB ATCT Rehab.xlsx | XLSX spreadsheet | |
| 697DCK-22-R-00166 Final.pdf | ||
| J4. Wage Rate.pdf | ||
| L2. TMB Past Performance Questionnaire.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Index
ID #
Activity or Description of Risk Identification of Consequences and the NAS systems/service impacted Scheduled
Outage Date of Review
Individual responsible for mitigation action(s)
Mitigation Action
Timeline
MSOW
Register
ID #
001 Use of heavy equipment. Damage to underground cables. RE, Contractor 1
101 Demolition of roofing materials Noise disrupting Air Traffic operations in Cab.
RE, Air Traffic, Contractor 3,12
Relocation of antennas/equipment Disruption of Air Traffic operations.
RE, SSC, Air Traffic, Contractor
2,9
Installation of new roofing system Noise disrupting Air Traffic operations in Cab.
Odors/VOCs from adhesives and sealants.
RE, Contractor, Air
Traffic 3,4,5,6,7, 9,12,13
Installation of fall protection system Noise disrupting Air Traffic operations in Cab.
Welding risk of fire and Air Traffic interuption.
RE, Contractor, SSC
3,7,10
Installation of lightning protection system Odors/VOCs from adhesives. Damage to underground cables.
RE, Contractor 4,5,6,8
201 Welding Risk of fire and Air Traffic interruption.
RE, Contractor, SSC
7,9,10,13
301 Control Panel installation in Cab Distruption to Air Traffic operations in Cab.
RE, Contractor, Air
Traffic
302 Electrical Panel Connection Outage of Electrical Panel H X SSC 14 303 Soldering Risk of fire and Air Traffic interruption. RE, Contractor 7,9,16
401 Egress Obstruction Workers in emergency egress path. RE, Air Traffic 11 402 Lighting Replacement Breaker Lock Out, Tag Out Contractor, SSC 15
501 Electrical Panel Connection Outage of Electrical Panel H X SSC 14
601 Electrical Panel Connection Outage of Electrical Panel H X SSC 14
TMB ATCT Rehab Risk Register
100 - Cab Roof Replacement
600 - Installation of New Security Camera Cab Entry Door
700 -
000 - Mobilization
400 - Admin Building Entrance Canopy Erection
500 - Installation of Additional 20A Power Feed into Cab for additional AC receptacles and power strips
300 - Catwalk Cab Window Washing System Installation
200 - Cab Roof Ladder Installation
ID # Mitigation (including resources, equipment required)
Contractor must coordinate location of staging area, and proposed crane, lift or other heavy machinery working locations with RE who will coordinate with local SSC to verify there are no known cables in the vicinity. If advised Contractor must utilize plywood to distribute loads and minimize risk of damage to underground cables.
RE will coordinate with SSC and Contractor regarding relocation of antennas and other equipment mounted on roof for the demolition and replacement of the roofing system and guardrail. The SSC will coordinate the reinstallation after the completion of the roofing system and guardrail.
Contractor will complete activities above 85 dB when the ATCT is closed. Work exceeding 85 dB for short periods of time will be coordinated with the RE and Air Traffic.
Sealants, adhesives, and paints must be water based and lowest VOC products available WHERE POSSIBLE. High wind region of Miami limits roofing product availability meeting wind uplift strength requirements to 250 g/L. All adhesives, sealants, paints, solvents, and cleansers must have SDS submitted to both the ES EOSH Specialist and Miami District SECM for approval prior to the RE allowing a product on the project site. RE will verify all products on site against the approved SDSs. The RE will maintain a SDS binder on site.
A PID will be used by the RE 1-2 days prior to the start of roof construction to establish a baseline reading for reference if any air quality complaints should be submitted by Air Traffic.*
Hydroxyl generators must run in the Cab and on 7th floor during roof replacement activities.
A back-up hydroxyl generator will be kept on site.
Contractor must seal air intake vents on 7th floor. Provide fresh air to Cab for positive pressurization. Fresh air supply should be from upwind direction of work area.
Prior to any excavation the Contractor must conduct an underground utility location survey and mark any locations found. Public utilities and the FAA SSC must also be consulted and their cables identified and marked.
A daily meeting will be held between the Contractor, RE, AT and SSC prior to each work shift to discuss approved work activities from the Risk Register for the day. Any sensitive unforseen AT activities that require an adjustment to previously planned work will be identified.
A Miami Dade Aviation Department and FAA Hot Work Permit will be completed by the RE.
All welding will be completed at night when the ATCT is closed. The Contractor must place a smoke eater in the Cab during welding activities. Fire extinguishers must be staged in the welding area and in the Cab and a Fire Watch must be employed. Contractor must use an in-line fan to redirect smoke from welding.
11 Route emergency egress through EG Room exit door.
Contractor and RE must verify with ZMA/National Weather Service any rain forecast before allowing the Contractor to begin roof replacement activities.
13 Work must be completed when ATCT is closed, between 11pm and 6am.
DBRITE, STARS, Obstruction Lights, Air Conditioning etc. will be effected by shutdown of Panel H. Coordinate shutdown with SSC, Air Traffic, Jose Hernandez at Miami Nav SSC and Jose Rodriguez Miami Radar SSC. Explore UPS borrow(Jeff Whitten?) or purchase (Purchase Card) for reboot of STARS.
15 Contractor must follow Lock Out/Tag Out procetures for electrical breaker.
Soldering must be performed away from the building when possible. IF soldering is required in place, a Miami Dade Aviation Department and FAA Hot Work Permit will be completed by the RE. All soldering must be completed at night when the ATCT is closed. The Contractor must place a smoke eater in the Cab during soldering activities. Fire extinguishers must be staged in the soldering area and in the Cab and a Fire Watch must be employed. Contractor must use an in-line fan to redirect smoke from soldering.
Mitigation Scope of Work Register (MSOW)
*PID Baseline will consist of readings 1 time per hour throughout a typical work day throughout the facility. The SECM will provide instruction to the RE on use of the PID and establishing the PID baseline. Each reading will include the time, location, and reading.