J.3_PRELIMINARY CONSTRUCTION SITE PLAN.pdf

PDF 1 MB Posted

Attached to
Manchester Campus Addition Construction at the Manchester Research Station in Port Orchard, Washington
Solicitation number
1305M4-24-R-0071
Issued by

About this file

This is a preliminary construction site plan drawing showing the overall campus layout for the NOAA Manchester Research Station in Port Orchard, Washington. The plan depicts the locations of existing facilities including the main building, labs + offices building, and RAS (Recirculating Aquaculture System) building, along with various support structures numbered 1-30 in the campus legend.

The drawing indicates the base scope and RAS bid option scope areas, with red hatched sections showing potential contractor staging, laydown and parking areas. It includes primary vehicular pathways marked with red arrows, access lanes, and limits of disturbance. The site borders Clam Bay and includes topographical contour lines. Critical details such as emergency access requirements and security gate notes are marked on the plan. This drawing provides contractors with essential site logistics information needed to bid on the new 24,000 GSF campus addition construction project.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LABS + OFFICES

BUILDING

RAS BUILDING

NOAA MANCHESTER

RESEARCH STATION

29 19

12 28

15B

15A

15C

CLAM BAY

RAS BID OPTION SCOPE BASE SCOPE

amiezemer Snapshot amiezemer Snapshot amiezemer Text Box

CAMPUS LEGEND:

1 Main Building 2 Main Building 3 Main Building 4 Navy Annex I 5 Navy Annex II 6 Pathology Lab 8 Warehouse 9 Emergency Power Generator 10 Chemical Storage Container 11 Fish Rearing 12 Saltwater Marine Lab

13 BPA

14 Fish Behavior Lab 15A Ozone Generator 15B Oxygen Generator 15C Restroom 16 Stream Channel Electrical 17 Stream Channel support 18 Recirculation for B14 19 Shop AND storage building 21 Kenneth Chew Center 22 Nooksack 23 Salmon Stream 24 Storage and Kelp Lab 25 Behavior Ecology Covered Tanks 26 Algae Growing Building 27 Albalone/Sea Cucumber Nursery 28 Tarp Covered Work Area 29 Covered Storage 30 Pump House

Mark.Benne Polygon

Mark.Benne Polygon

Mark.Benne Polygon

Mark.Benne Text Box Area 1

Mark.Benne Text Box Area 2

Mark.Benne Text Box Area 7

Mark.Benne Polygon

Mark.Benne Text Box Area 4

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Line

Mark.Benne Line

Mark.Benne Arrow

Mark.Benne Text Box Primary NOAA/EPA Roadway. Minimum one-way traffic must remain open at all times during construction.

Limits of disturbance

Access Loop. Must maintain one way access to facilities at all times. One way access must be coordinated 7 days in advance.

Potential contractor laydown, field office and parking areas.

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Polygon

Mark.Benne Text Box Area 6

Mark.Benne Line

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Rectangle

Mark.Benne Polygon

Mark.Benne Callout Contractor Parking (16 stalls)

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Arrow

Mark.Benne Polygon

Mark.Benne Polygon

Mark.Benne Arrow

Mark.Benne Callout Maintain emergency access through this gate. Premission to temporarily restrict access must be coordinated 21 calendar days in advance.

Mark.Benne Text Box Area 3

Mark.Benne Text Box Area 5

Mark.Benne Line

Mark.Benne Callout Security Gate open from 5am - 6pm Monday thru Friday

Floor Plans (Site Plan)
SITE PLAN_Full Campus Copy 2

File details come from the government source that posted it. Updated .