FAALC Enhancement Program 2475 Henderson Way Monterey, CA 93940
STATEMENT OF WORK
MRY
Monterey, CA
PURPOSE: FAALC Enhancement Program (Beautification).
STATEMENT OF WORK:
The contractor will provide labor, travel, permits/application fees, mobilization costs and tools for technicians to travel to the Monterey, CA – MRY site for the purpose of renovating first floor bathroom facility; Contractor will ensure compliance with ADA standards. All work shall be completed by a licensed contractor in the state of California and completed in accordance with local, state, federal and industry standard requirements. Contractor work schedule will have to be approved by local FAA POC (point of contact). Contractor will provide samples of paint, tile, grout, and fixtures to FAA for approval. Paint will be matched as closely as feasible to current paint color(s) of the bathroom door trim, walls, and ceiling. Reference attached photo and drawings.
COVID Consideration(s): Contractor will follow all facility, local, state, and federal COVID protocols; utilizing entrance and exit point established by local FAA representative. Contractor will be required to create safe work area utilizing barriers and/or materials for separation based upon COVID protocols during execution of enhancement described in this document.
Scope of Work:
(a) Demolition:
1. 4” x 4” ceramic floor tile
2. 6” x 6” ceramic floor splash guard tile
3. Toilet “B”
4. Urinal “C”
5. Sink “D”
6. Toilet stall divider wall “E”
7. Hanging wall storage cabinet
8. Mirror
9. Entrance foyer wall “J”
10. Paper towel dispenser
11. Vent fan
12. Center ceiling light fixture
13. Vanity light fixture
14. Shelf next to sink.
15. Toilet seat cover dispenser
(b) Remediation:
1. Remove foyer wall “J”
2. Widen entrance door to 36” and to swing “I & L” (inward & left)
3. Repair water damaged wall below sink and urinal
4. Remove toilet stall wall “E”
5. Repair wall board and paint in hallway leading to bathroom from door change out
6. Change out center floor drain cover
(c) Install Work:
1. Install new 36” entrance door with ADA compliant hardware to swing “I & L” (inward and left) with inside lock
2. Install new 12” x 24” ceramic floor tile with 1/8” grout lines (MSI Cementino Grey Matte – Part # Unknown or equivalent)
3. Install new 6” x 6” floor drain cover (Jay R Smith Mfg., Co, Part # B06PBG or equivalent)
4. Install new 12” x 24” ceramic wall tile to a height of 48” from floor with 1/8” grout lines (MSI Matte White - Part # NWH1224-N or equivalent)
5. Install new comfort height ADA Compliant toilet (American Standard Madera One- Piece Toilet, Part # 3043.660.020 or equivalent)
6. Install new ADA Compliant grab bar with leg support (Signature Hardware, Part # 920109 or equivalent)
7. Install new ADA Compliant wall mounted 36” grab bar (Moen Home Care, Part # R8936 or equivalent)
8. Paint interior walls and ceiling
9. Install new exhaust fan
10. Install new 27” LED ceiling mount light fixture (AFX Flush Mount LED Light Fixture, Part # SLF12241800L30D1SN or equivalent)
11. Install new 24” x 36” vanity mirror (Bradley, Part # 780-024360 or equivalent)
12. Install new 26” LED wall mounted light fixture above new vanity mirror (Kuzco
Lighting-ALBERNI, Part # VL61626 or equivalent)
13. Install new touchless urinal (American Standard, Part # 6590.525.020 or equivalent)
14. Install new ADA Compliant vanity sink (American Standard, Part # 0356.041.020 or equivalent)
15. Install new touchless water faucet (Sloan, Part # EAF-275-ISM or equivalent)
16. Install new 36” x 18” x 72” wall storage cabinet (option #1) (Global Industrial, Part
# T9F237635GY or equivalent) or new 24” x 18” x 66” wall storage cabinet (option #2) (Uline, Part # H-6317 or equivalent)
17. Install new touchless soap dispenser (GoJo LTX, Part # H-5066 or equivalent)
18. Install new touchless paper towel dispenser (Global Industrial, Part # T9640932 or equivalent)
19. Install new toilet seat cover dispenser (Uline, Part # H-1592 or equivalent)
20. Installed new recessed dual tissue roll dispenser (Bobrick, Part # B6997 or equivalent)
21. Install new bag and coat hanging hooks on wall
22. Install new UNISEX Bathroom Sign
23. Install new Handicap Accessible Sign
LOCATION:
ATC Facility Monterey, CA Airport
PERIOD OF PERFORMANCE:
Completion within 30 days from start of project. Any deviation of the period of performance timeline will require the prior approval of the CO (contract officer).
SECURITY REQUIREMENTS:
Approved entrance from facility manager. FAA personnel will escort contractor, sub-contractor, delivery, and vendor personnel while on site; contractor will arrange with FAA POC for delivery schedule and daily work schedule.
SPECIAL REQUIREMENTS:
Contractor will provide portable latrine and sanitation/wash station. Contractor will ensure regular servicing of portable latrine is performed.
The contractor will provide waste removal container and removal from site in accordance it local sanitary rules and regulations.
Local SSC/Stakeholder will contact EOSH representative to determine requirements and/or submittals that must be reviewed and approved prior to implementation. Demolition work will be performed at this site creating dust and debris in the ATC (Air Traffic Control) facility.
SUBMITTALS:
1. Warranty documentation on all newly installed equipment, fixtures, and furnishings.
2. Owner’s manuals for newly installed equipment, fixtures, and furnishings.
3. Disposal receipt will be required.
4. Provide “as installed drawings”.
https://www.airnav.com/airport/KMGM
| Scope of Work: |
| 1. 4” x 4” ceramic floor tile |