J.1 - 250530-PHASE 1 - GPO 4TH FLOOR-100% SPECIFICATIONS.pdf

PDF 16 MB Posted

Attached to
National Archives and Records Administration (NARA) 4TH FLOOR Renovation Project
Solicitation number
040ADV-26-R-0016
Issued by

About this file

This document comprises the 100% Construction Documents (specifications and technical requirements) for the National Archives and Records Administration (NARA) 4th Floor Renovation Project at the Government Publishing Office (GPO) main campus in Washington, DC. The specifications are organized into Division 00 (Procurement and Contracting Requirements) and Division 01 (General Requirements), followed by technical divisions covering all construction trades and systems.

The project requires comprehensive renovation work including selective demolition, structural modifications, mechanical/electrical/plumbing (MEP) systems installation, fire protection systems, and interior finishes. Key technical requirements include: cast-in-place concrete work, brick masonry repair, metal framing and slotted channel supports, wood rough carpentry, waterproofing, thermal insulation with vapor barriers, penetration and joint firestopping systems, joint sealants, hollow metal doors and frames, and door hardware. The specifications mandate compliance with ACI, ASTM, NFPA, and building code standards, with extensive quality control, testing, and inspection requirements. Critical administrative elements include detailed submittals procedures using Oracle Primavera Unifier project management software, a comprehensive Quality Control Plan with defined organizational roles (Project Manager, Superintendent, Quality Control Manager), phased construction scheduling with CPM requirements, operation and maintenance manual preparation, record documentation, and demonstration/training for facility operations. The contract requires the Contractor to provide labor, materials, equipment, and supervision; coordinate with GPO occupancy requirements; manage temporary facilities and utilities; and maintain full compliance with the GPO Construction Safety Manual and environmental protection standards throughout all construction phases.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SPECIFICATIONS

Division 00 - 28

Project No. 053-10073-103

National Archives and Records Administration At the Government Publishing Office Partial 4th Floor Renovation

732 North Capitol Street, NW.

WASHINGTON, DC 20401

CONSTRUCTION DOCUMENTS

100% CONSTRUCTION DOCUMENTS SUBMISSION

PHASE 1

May 30, 2025

053-10073-103 100% CONSTRUCTION DOCUMENTS

05/30/2025

SEALS PAGE 000000

NATIONAL ARCHIVES AND RECORDS ADMINISTRATION

At the Government Publishing Office

PARTIAL 4TH FLOOR RENOVATION

732 North Capitol Street, NW.

Washington, DC 20401

GOVERNMENT PUBLISHING OFFICE

732 North Capitol Street, NW.

Washington, DC 20401

ARCHITECT OF RECORD ENGINEER OF RECORD, MECHANICAL, PLUMBING

ENGINEER OF RECORD, LIFE SAFETY, FIRE ALARM & FIRE PROTECTION

ENGINEER OF RECORD, STRUCTURAL ENGINEER OF RECORD, ELECTRICAL

05/29/2025

TABLE OF CONTENTS 000110 - 1

TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

000000 COVER

000110 TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

012200 UNIT PRICES

012210 MEASUREMENT AND PAYMENT

012500 SUBSTITUTIONS PROCEDURES

012600 CONTRACT MODIFICATIONS PROCEDURES

012300 ALTERNATES

012900 APPLICATION FOR PAYMENT

013100 PROJECT MANAGEMENT AND CONSTRUCTION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013233 PHOTOGRAPHIC AND VIDEO RECORDING DOCUMENTATION

013300 SUBMITTALS

014000 QUALITY REQUIREMENTS

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

016000 PRODUCT REQUIREMENTS

017300 EXECUTION

017329 CUTTING AND PATCHING

017700 PROJECT CLOSEOUT

017823 OPERATION AND MAINTENANCE DATA

017839 PROJECT RECORD DOCUMENTS

017900 DEMONSTRATION AND TRAINING

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

033053 MISCELLANEOUS CAST-IN-PLACE CONCRETE

035416 HYDRAULIC CEMENT UNDERLAYMENT

DIVISION 04 - MASONRY

040120.63 BRICK MASONRY REPAIR

TABLE OF CONTENTS 000110 - 2

DIVISION 05 - METALS

054300 SLOTTED CHANNEL FRAMING

055000 METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

071416 COLD FLUID-APPLIED WATERPROOFING

072100 THERMAL INSULATION

078413 PENETRATION FIRESTOPPING

078443 JOINT FIRESTOPPING

079200 JOINT SEALANTS

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

087100 DOOR HARDWARE

088400 PLASTIC GLAZING

089000 LOUVERS AND VENTS

DIVISION 09 - FINISHES

092216 NON-STRUCTURAL METAL FRAMING

092900 GYPSUM BOARD

093013 CERAMIC TILING

095113 ACOUSTICAL PANEL CEILING

096513 RESILIENT BASE AND ACCESSORIES

096723 RESINOUS FLOORING

099123 INTERIOR PAINTING

DIVISION 10 - SPECIALTIES

102800 TOILET, BATH, AND LAUNDRY ACCESSORIES

104413 FIRE PROTECTION CABINETS

104416 FIRE EXTINGUISHERS

DIVISION 11 - EQUIPMENT

NOT USED

TABLE OF CONTENTS 000110 - 3

DIVISION 12 - FURNISHINGS

NOT USED

DIVISION 21 - FIRE SUPPRESSION

210000 BASIC FIRE SUPPRESSION REQUIREMENTS

210517 SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING

210529 HANGERS AND SUPPORTS FOR FIRE-SUPPRESSION PIPING AND

EQUIPMENT

210553 IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT

211313 WET-PIPE SPRINKLER SYSTEMS

DIVISION 22 - PLUMBING

220500 COMMON WORK RESULTS FOR PLUMBING

220523 VALVES FOR PLUMBING PIPING

221116 DOMESTIC WATER PIPING

221316 SANITARY WASTE AND VENT PIPING

224100 PLUMBING SPECIALTIES

224213.13 COMMERCIAL WATER CLOSETS

224216.13 COMMERCIAL LAVATORIES

224500 EMERGENCY PLUMBING FIXTURES

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230500 COMMON WORK RESULTS FOR MECHANICAL

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

230517 SLEEVES FOR HVAC PIPING

230518 ESCUTCHEONS FOR HVAC PIPING

230519 METERS AND GAGES FOR HVAC PIPING

230523 VALVES FOR HVAC PIPING

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

230548.13 VIBRATION CONTROLS FOR HVAC

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230700 HVAC INSULATION

230923 DIRECT DIGITAL CONTROL (DDC) SYSTEMS FOR HVAC

232113 HYDRONIC PIPING

232116 HYDRONIC PIPING SPECIALTIES

232123 HYDRONIC PUMPS

232533.13 REVERSE-OSMOSIS WATER PIPING FOR HUMIDIFICATION

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

TABLE OF CONTENTS 000110 - 4

233713 AIR DIFFUSERS, REGISTERS, AND GRILLES

234100 PARTICULATE AIR FILTRATION

237313.19 CUSTOM FACTORY FABRICATED AIR-HANDLING UNITS

238216 AIR COILS

238219 FAN COIL UNITS

238413 HUMIDIFIERS

DIVISION 26 - ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533.13 CONDUITS FOR ELECTRICAL SYSTEMS

260533.16 BOXES AND COVERS FOR ELECTRICAL SYSTEMS

260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND

CABLING

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260573.13 SHORT-CIRCUIT STUDIES

260573.16 COORDINATION STUDIES

260573.19 ARC-FLASH HAZARD ANALYSIS

260923 LIGHTING CONTROL DEVICES

262213 LOW-VOLTAGE DISTRIBUTION TRANSFORMERS

262416 PANELBOARDS

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

262913.03 MANUAL AND MAGNETIC MOTOR CONTROLLERS

265119 LED INTERIOR LIGHTING

265213 EMERGENCY AND EXIT LIGHTING

DIVISION 27 - COMMUNICATIONS

270500 COMMON WORK RESULTS FOR COMMUNICATIONS

271500 COMMUNICATIONS HORIZONTAL CABLING

271600 COMMUNICATIONS CONNECTING CORDS DEVICES AND ADAPTERS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

280500 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY

281000 ELECTRONIC ACCESS CONTROL AND INTRUSION DETECTION

282000 ELECTRONIC SURVEILLANCE

284621.11 ADDRESSABLE FIRE-ALARM SYSTEMS

SUMMARY 011000 - 1

V.1

DIVISION 01 – GENERAL REQUIREMENTS

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provision of the contract, including General and Supplementary conditions, other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Products ordered in advance.

5. GPO-furnished products.

6. Use of premises.

7. The GPO’s occupancy requirements.

8. Work restrictions.

9. Specification formats and conventions.

B. Related Sections include the following:

1. Division 01 Section “Temporary Facilities and Controls” for limitations and procedures governing temporary use of the GPO’s facilities.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. Program Identification: Program includes Task Order construction services associated with the

GPO Long-term Re-development.

1.4 WORK PHASES

A. Work phasing plans and information will be provided with each Task Order.

B. Work phasing plans and information that are provided are not intended to restrict the Contractor to this specific phasing. The Contractor may submit a re-phasing schedule at no additional cost to the GPO for review and written approval.

SUMMARY 011000 - 2

C. Schedule the execution of the Work according to the phasing sequence indicated and to avoid interference with normal functions of the GPO.

D. Before commencing the Work of each phase, submit a schedule to the COTR showing the sequence, the commencement and completion dates, and the move-out and move-in dates of personnel for the various phases of the Work.

E. On completion, each phase of the Work shall be fully operational.

1.5 PRODUCTS ORDERED IN ADVANCE BY THE GPO

A. General: The GPO may negotiate Purchase Orders with Suppliers of material and equipment to be incorporated into the Work. The GPO may assign these Purchase Orders to the Contractor.

Information regarding such Purchase Orders will be provided with each Task Order. Costs for receiving, handling, storage, and protection if required, and installation of material and equipment are to be included in the Task Order Price.

1. The Contractor’s responsibilities are the same as if the Contractor had negotiated the

Purchase Orders, including responsibility to renegotiate the purchase and to execute final

Purchase-Order agreements.

2. The Schedule of Products Ordered in Advance by the GPO will be provided with each Task

Order.

1.6 GPO FURNISHED PRODUCTS

A. The GPO may furnish products to the Contractor for incorporation into the Work. Information regarding such products will be provided with each Task Order. Costs for receiving, handling, storage, and protection if required, and installation of the products are to be included in the Task

Order Price. The following apply to GPO furnished products:

1. The GPO will arrange for and deliver Shop Drawings, Product Data, and Samples to the

Contractor.

2. The GPO will arrange and pay for the delivery of GPO-furnished products.

3. Upon delivery, the GPO will inspect the products for damage. The Contractor is to be present for and assist with the inspection.

4. If the GPO-furnished products are found to be damaged, defective, or missing at the time of delivery and inspection, the GPO will arrange for repair or replacement.

5. The GPO will arrange for manufacturer’s field services and for delivery of manufacturer’s warranties to the Contractor for incorporation in the Warranty Manual.

6. The GPO will furnish the Contractor the earliest possible delivery date for GPO-furnished products. Using the GPO-furnished earliest possible delivery dates, the Contractor is to designate the delivery date(s) for the GPO-furnished items in the Contractor’s CPM

Schedule.

7. The Contractor is to review the Shop Drawings, Product Data, and Samples and return them to COTR noting discrepancies or anticipated problems in use of the product.

8. The Contractor is responsible for receiving, unloading, and handling GPO-furnished items at the Jobsite or other agreed to delivery location. Upon inspection and acceptance, the

SUMMARY 011000 - 3

responsibility for the products will be assigned to the Contractor by the GPO using a materials transfer form, with signatures by authorized representatives of the GPO and the

Contractor.

9. The Contractor is responsible for protecting GPO-furnished items from damage during storage and handling, including damage from exposure to the elements.

10. The Contractor is to repair GPO-furnished items that are damaged as a result of

Contractor’s operations. Repair or replacement is at the Contractor’s expense.

1.7 CONTRACTOR’S USE OF GPO PREMISES

A. Contractor Use of the Jobsite: The Contractor’s use of premises is limited to work in the areas indicated in each Task Order. Do not disturb areas, facilities or operations beyond the Jobsite designated for the Work.

1. Limits: Confine constructions operations to the areas indicated in each Task Order.

2. GPO Occupancy: Allow for the GPO’s occupancy and use of all areas that are not designated and authorized for the Contractor’s construction operations.

3. The Contractor shall have full use of the Jobsite designated for construction operations within the limits indicated for each Task Order during the construction period, within the hours indicated, and as directed by the COTR. The Contractor’s use of the Jobsite is limited by the GPO’s right to perform work or to retain other contractors on portions of Program.

4. Driveways and Entrances: Keep entrances serving premises clear and available to the GPO, the GPO’s employees, tenants, and emergency vehicles at all times. Do not use driveways and entrances for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Utilize areas designated for Contractor staging, storage, and parking, as indicated. For additional requirements, see Section 007300 “Supplementary Conditions.”

C. Use of Existing Buildings: Maintain existing buildings in a weather tight condition throughout the construction period. The Contractor is responsible for the repair of all damage caused by the

Contractor’s construction operations, to include approval and acceptance by the GPO. The

Contractor is to protect the premises and their occupants during the construction period.

1. For additional requirements, see Section 007300 “Supplementary Conditions.”

1.8 OCCUPANCY REQUIREMENTS

A. Full GPO Occupancy: The GPO and/or its tenants will occupy the site and existing buildings during the entire construction period. The Contractor is to cooperate with the GPO during construction operations to minimize conflicts and facilitate the GPO usage, and perform the Work so as not to interfere with day-to-day GPO operations.

B. For additional requirements for tenant operational requirements, see Section 007300

SUMMARY 011000 - 4

“Supplementary Conditions.”

1.9 CONTRACTOR HOURS OF OPERATION

A. Contractor Working Hours: The Contract Work is subject to the schedule requirements and GPO operational restrictions, which will be provided with each Task Order. The Work may require that the Contractor’s staff and operate extended and or multiple shifts, such days, nights, weekends and holidays. The Contractor is to notify the COTR a minimum of 24-hours in advance of any change to the Contractor’s daily work plan.

1.10 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: With the exception of federal standard specifications and specifications will be organized into Divisions and Sections using the using the CSI/CSC’s “MasterFormat” numbering system.

1. Section Identification: The Specifications use Section titles to help with cross-referencing in the Contract Documents. Sections are in numeric sequence; however, the sequence is incomplete as all available Sections and Section numbers are not used and the CSI numbering system is not sequentially complete. Consult the table of contents at the beginning of the specifications for each Task Order to determine the numbers and names of sections in the applicable Construction Documents.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications is abbreviated. Interpret singular words as plural, and plural words as singular where applicable as the context of the Contract Documents indicates. Refer any questions to the COTR in writing for determination.

2. Imperative mood and streamlined language are used in these Specifications. This imperative language is directed to the Contractor, unless specifically noted otherwise.

Requirements expressed in the imperative mood are to be performed by the Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by the Contractor or by others when so noted.

a. The words “shall,” “shall be,” or “shall comply with,” depending on the context, are implied where a colon (:) is used within a sentence or phrase.

1.11 MARKING UTILITY SERVICES

A. The information in the Contract Documents concerning the type and location of underground utilities is neither guaranteed nor inclusive. The Contractor is responsible for determining the type and location of underground utilities, regardless of whether such utilities are indicated or not, so as to avoid damage thereto.

SUMMARY 011000 - 5

B. Employ a Subsurface Utility Engineering company to locate and mark the horizontal and vertical location of all utility lines in accordance with, ASCE C-I 38-02, Standard Guidelines for the

Collection and Depiction of Existing Subsurface Utility Data, Quality level-A. Utilities that might be impacted by construction activities, including but not limited to the following:

1. Electric power lines.

2. Natural gas lines.

3. Sanitary Sewers.

4. Storm Sewers.

5. Water supply piping.

6. Telephone lines.

7. Data lines.

8. Underground Storage Tanks.

9. High Temperature Hot Water (HTHW), steam lines and chilled water lines.

C. Quality level A locating involves the use of nondestructive digging equipment at critical points to determine the precise horizontal and vertical position of underground utilities, as well as the type, size, condition, material, and other characteristics.

1. For each Task Order, within 60 calendar days of Notice to Proceed, submit to the COTR a survey of all subsurface utility engineering results, indicating the horizontal and vertical location, coordinates and elevation of all utilities. No land disturbance shall be performed until the utility survey is approved.

D. Coordinate with the COTR, for access to and utilization of GPO facilities.

E. The Contractor is responsible for following the requirements of the DC Underground Utility

Damage Prevention Act. (Calling Miss Utility-DC811).

F. Report any unmarked utilities encountered during construction to the COTR immediately.

G. Repair any damage to utility lines due to construction operations at no expense to the GPO.

H. Submit to the COTR the name of the independent Subsurface Utility Engineering (SUE)

Company to be used. Individuals assigned by the SUE provider to carry out the work should be well-trained, experienced, and capable. Those in responsible charge of the work and responsible for certifying deliverables should be engineers, geologists, and land surveyors employed by the

SUE provider in accordance with state professional registration requirements.

1.12 PLANNING AND SCHEDULING UTILITY OUTAGES

A. Prior to any utility outage/interruption, prepare a plan and schedule of such outage. Include the outage schedule duration, identification of the service affected, temporary utility service to be provided, identification of available service alternative, and the action to be taken in any emergency. Apply for all outages of utility systems in writing. Fully coordinate outage requests with COTR. Obtain approval in writing from the GPO. Schedule all outages at least three (3) weeks in advance with a 96-hour notification provided by the Contractor confirming date, time, and duration. Outages will normally be scheduled on the weekends – Saturday and Sunday.

SUMMARY 011000 - 6

B. Provide a suction/pump truck during all sanitary sewer line outages to support the disabled lift stations. Transport sewage to alternate lift stations located on the GPO and dispose of in accordance with GPO procedures. Provide a suction/pump truck with a minimum capacity of

3,000 gallons or greater.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF PRODUCTS ORDERED IN ADVANCE

A. TBD

END OF SECTION 011000

053-10073-103 65% CONSTRUCTION DOCUMENTS

03/07/2025

UNIT PRICES 012200 - 7

SECTION 012200 - UNIT PRICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provision of the contract, including General and Supplementary conditions, other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for unit price items that may be established as part of a Task Order.

B. Related Sections include the following:

1. Division 01 Section “Measurement and Payment” for procedures for measurement and payment for unit-price items.

1.3 DEFINITIONS

A. “Unit Priced Line Item,” is a distinct portion of work that is measured and priced based on a defined unit of measure and an estimated quantity of the units of work required.

1.4 PROCEDURES

A. A unit price is an amount proposed by the Contractor and accepted by the GPO as the price per unit of measurement for a specific line item of materials or services. The unit priced line items and the estimated quantity for each unit price line item will be developed during design. The GPO does not expressly or by implication agree that the actual quantities involved will correspond exactly therewith; nor shall the Contractor plead misunderstanding or deception because of such estimates of quantities, or of the character, location, or other conditions pertaining to the work.

Payment to the Contractor will be made only for the actual quantities of work performed and measured according to the Construction Documents.

B. Adjustment of a unit price is limited to instances in which the actual unit quantity varies by more than fifteen-percent (15%) above or below the estimated quantity. Refer to Contract Section

11.9.

C. Unit prices include all of the Direct Cost for the defined work items.

D. Measurement and Payment: Refer to individual Specification Sections within the Construction

Documents for work that requires use of unit prices. Methods of measurement and payment for unit prices are specified in those Sections and in Division 01 Section “Measurement and

Payment.”

UNIT PRICES 012200 - 8

UNIT PRICES 012200 - 1

E. The GPO reserves the right to reject the Contractor’s measurement of work-in-place that involves use of established unit prices and to have this work measured, at the GPO’s expense, by an independent surveyor.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012200

MEASUREMENT AND PAYMENT 012210 - 1

SECTION 012210 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provision of the Contract, including General and Supplementary conditions, other Division 00 and 01 Specification Sections, and the Construction Documents apply to this

Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements governing methods of measurement and computations to be used in determination of quantities of material furnished and unit amount of Work performed under the Contract in order for the Contractor to receive payment according to pre-established unit prices. This Section only applies to unit price items included in the Construction Services Approved Direct Cost. This Section does not apply to the

Construction Services General Conditions Fee.

B. At the discretion of the COTR, payment may be reduced for any Work which is not in full compliance with the Contract Documents or which has been damaged or repaired by the

Contractor. Such action may be used when the end product may have a reduced service life or less than desirable aesthetic characteristics.

C. Descriptions and identification of unit-price items, if any, will be specified in Division 01 Section

“Unit Prices” for each applicable Task Order.

1.3 MEASUREMENT OF QUANTITIES

A. All volumes or quantities used to determine unit-price payment will be measured by COTR, or by COTR’s authorized representatives, using methods generally recognized as conforming to good engineering practice and as specified in Technical Specifications. Unless otherwise indicated, measurement shall be in U.S. Customary Units of Measurement.

B. Unless otherwise indicated, longitudinal measurements for area computations will be made horizontally, and no deductions will be made for individual fixtures (or leave-outs) having an area of 9 sq. ft. or less. Unless otherwise indicated, transverse measurements for area computations will be the neat dimensions shown on Drawings.

1. Structures will be measured according to neat lines shown on the plans or as altered to fit field conditions.

2. Measure all Contract items measured by the linear foot, such as electrical ducts, conduits, pipe culverts, under drains, and similar items, parallel to the base of foundation on which such items are placed, unless otherwise indicated.

MEASUREMENT AND PAYMENT 012210 - 2

3. In computing volumes of excavation, use the average end area method or other acceptable method.

C. The thickness of plates and galvanized sheet used in the manufacture of corrugated metal pipe, metal plate pipe culverts and arches, and metal cribbing will be specified and measured in decimal fraction of inches.

D. Haul materials, to be measured by volume in the hauling vehicle, in approved vehicles and measured therein at the point of delivery. Vehicles for this purpose may be of any size or type acceptable to and approved in advance by COTR, provided that the body is of such shape that the actual contents may be readily and accurately determined. Load all vehicles to at least their water-level capacity. Level loads when the vehicles arrive at the point of delivery.

1. When requested by the Contractor and approved by the COTR in writing, material specified to be measured by the cubic yard may be weighed, and such weights will be converted to cubic yards for payment purposes. Factors for conversion from weight measurement to volume measurement will be determined by COTR and agreed to by the Contractor before such method of measurement of pay quantities is used.

2. The term “ton” will mean the short ton consisting of 2000-lb avoirdupois. Weigh all materials, which are measured or proportioned by weights, on accurate, approved scales by competent, qualified personnel at locations designated by COTR.

a. If material is shipped by rail, the car weight may be accepted, provided that only the actual weight of material will be paid for. However, car weights will not be acceptable for material to be passed through mixing plants.

b. Weigh trucks used to haul material being paid for by weight empty daily at such times as COTR directs. Each truck shall bear a plainly legible identification mark.

E. Measure bituminous materials by the gallon or ton. When measured by volume, measure such volumes at 60 deg F or measure corrected to the volume at 60 deg F, using ASTM D 1250 for asphalts or ASTM D 633 for tars.

1. Net certified scale weights or weights based on certified volumes in the case of rail shipments will be used as a basis of measurement, subject to correction when bituminous material has been lost from the car or the distributor, wasted, or otherwise not incorporated into the Work.

2. When bituminous materials are shipped by truck or transport, net certified weights by volume, subject to correction for loss or foaming, may be used for computing quantities.

F. Concrete will be measured by the cubic yard in place, unless otherwise indicated.

G. The term “each” when used as an item of payment shall mean complete payment for the work described in the Construction Documents.

1. When a complete structure or structural unit is to be provided, and “each” is specified, as the unit of measurement, the unit will be construed to include all necessary fitting, accessories, and work incidental to the work item.

MEASUREMENT AND PAYMENT 012210 - 3

H. Rental of equipment will be measured by time in hours of actual working time and necessary traveling time of the equipment within the limits of the Work. Special equipment ordered by change order in connection with “force account work” will be measured as agreed in Contract

Modification authorizing such force account work as provided in the Contract Documents.

I. When standard manufactured items are specified such as fence, wire, plates, rolled shapes, pipe conduit, etc., and these items are identified by gage, unit weight, section dimensions, etc., such identification will be considered to be nominal weights or dimensions. Unless more stringently controlled by tolerances in cited Specifications, manufacturing tolerances established by the industries involved will be accepted.

J. When estimated quantities for a specific portion of the Work are designated as the pay quantities in the Contract, they shall be the final quantities for which payment for such specific portion of the Work will be made, unless the dimensions of said portions of the Work shown on Drawings are revised by Contract Modification signed by the Contracting Officer.

1. If revised dimensions result in an increase or decrease in quantities of such Work, final quantities for payment will be revised in the amount represented by the authorized changes in the dimensions.

1.4 SCALES

A. Scales for weighing materials, which are required to be proportioned or measured and paid for by weight, shall be furnished, erected, and maintained by the Contractor or be certified permanently installed commercial scales.

B. Scales shall be accurate within one-half percent of the current weight throughout the range of use.

The Contractor shall have scales checked under the observation of the inspector before beginning

Work and at such other times as requested. The intervals shall be uniform in spacing throughout the graduated or marked length of the beam or dial and shall not exceed one-tenth of 1 percent of the nominal rated capacity of the scale, but not less than 1 lb. The use of spring balances will not be permitted.

1. Beams, dials, platforms, and other scale equipment shall be so arranged that the operator and the inspector can safely and conveniently view them.

2. Scale installations shall have available 10 standard 50-lb weights for testing the weighing equipment or suitable weights and devices for other approved equipment.

3. Scales must be tested for accuracy and serviced before use at a new site. Platform scales shall be installed and maintained with the platform level and rigid bulkheads at each end.

4. Scales “overweighing” (indicating more than correct weight) will not be permitted to operate, and all materials received subsequent to the last previous correct weighing accuracy test will be reduced by the percentage of error in excess of one-half of 1 percent.

5. In the event inspection reveals the scales have been “under-weighing” (indicating less than correct weight), they shall be adjusted, and no additional payment to the Contractor will be allowed for materials previously weighted and recorded.

MEASUREMENT AND PAYMENT 012210 - 4

C. All costs in connection with furnishing, installing, certifying, testing, and maintaining scales; for furnishing check weights and scale house; and for all other items specified in this Section for the weighing of materials for proportioning or payment shall be included in the unit prices for the applicable line items.

1.5 PAYMENT FOR MATERIALS ON HAND

A. Partial payments may be made to the extent of the delivered cost of materials to be incorporated into the Work, provided that such materials meet the requirements of the Construction Documents and are delivered to acceptable sites on the GPO property or at other sites in the vicinity that are acceptable to the Contracting Officer. Such delivered costs of stored or stockpiled materials may be included in the next partial payment application after the following conditions are met:

1. The Contractor provides the Contracting Officer with acceptable evidence of quantity and quality of the materials.

2. The Contractor provides the Contracting Officer with acceptable evidence that the material and transportation costs have been paid.

3. The Contractor provides the Contracting Officer legal title, free of liens or encumbrances of any kind, to the material so stored and stockpiled.

4. The Contractor provides the evidence that the material so stored or stockpiled is insured against loss by damage to or disappearance of such materials at any time before use in the

Work.

5. The Contractor provides the Contracting Officer with manufacturer’s installation and maintenance information.

B. It is understood and agreed that the transfer of title and the GPO’s payment for such stored or stockpiled materials shall in no way relieve the Contractor of responsibilities for furnishing and placing such materials according to the requirements of the Contract Documents.

C. In no case will the amount of partial payments of materials on hand exceed the portion of the Task

Order Price allocated to such materials or the portion of the Task Order Price allocated to the item in which such materials are intended to be used.

D. Partial payment for stored or stockpiled materials is limited according to the provisions of this

Section and as approved by the Contracting Officer.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012210

SECTION 012500 – SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.

1.4 SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use Form included at end of this Section or request a copy from the COTR.

2. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the

Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the

Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume.

b. Contractor shall compensate Architect for any costs incurred for redesign and evaluation services related to the request for substitution.

c. Requested substitution does not require extensive revisions to the Contract

Documents.

d. Requested substitution is consistent with the Contract Documents and will produce indicated results.

e. Substitution request is fully documented and properly submitted.

f. Requested substitution will not adversely affect Contractor's construction schedule.

g. Requested substitution has received necessary approvals of authorities having jurisdiction.

h. Requested substitution is compatible with other portions of the Work.

i. Requested substitution has been coordinated with other portions of the

Work.

j. Requested substitution provides specified warranty.

k. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

END OF SECTION 012500

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

1.3 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on "Architect's

Supplemental Instructions" form.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the

Contract Time. If necessary, the description will include supplemental or revised

Drawings and Specifications.

1. Proposal Requests issued by Architect are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the

Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to

Architect.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

CONTRACT 012600 - 1

MODIFICATION

PROCEDURES

V.1

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Division 01 Section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.

C. Proposal Request Form: Use Document for Proposal Requests provided by Architect.

1.5 CHANGE ORDER PROCEDURES

A. On GPO's approval of a Proposal Request, Architect will issue a Change Order for signatures of GPO and Contractor.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Architect may issue a Construction Change Directive which instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the

Work. It also designates method to be followed to determine change in the Contract

Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

SECTION 012300 - ALTERNATES

1.1 RELATED DOCUMENTS

A. Drawings and general provision of the contract, including General and Supplementary conditions, other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for alternates.

1.3 DEFINITIONS

A. Alternate: An amount proposed by the Contractor and stated on the Proposal Form for certain work defined in the Construction Documents that may be added to or deducted from the Base

Proposal amount if the GPO decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. The cost or credit for each alternate is the net addition to or deduction from the Task Order

Price to incorporate the alternate into the Work. No other adjustments are made to the Task

Order Price.

1.4 PROCEDURES

A. Coordination: Modify or adjust affected adjacent work as necessary to completely integrate the work of the alternate into the Task Order.

1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.

B. Notification: Immediately following award of the Task Order, the GPO will notify the Contractor, in writing, of the status of each alternate. The notification will indicate whether alternates have been accepted, rejected, or deferred for later consideration; and will include a complete description of any negotiated adjustments to the alternates.

C. Accepted alternates will be included in the Task Order and subject to the conditions of the Task

Order and the Contract.

D. Schedule of Alternates: A Schedule of Alternates will be included at the end of this Section in the specifications for a Construction Work Package when alternates are in consideration for Task

Order pricing. Specification Sections referenced will contain requirements for materials necessary to achieve the work described under each alternate.

ALTERNATES 012300 - 1 PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. To be provided with construction services Task Order.

END OF SECTION 012300

APPLICATION FOR PAYMENT 012900 - 1

SECTION 012900 – APPLICATION FOR PAYMENT

1.1 RELATED DOCUMENTS

A. Drawings and general provision of the contract, including General and Supplementary conditions, other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process

Applications for Payment.

1. Coordinate the Schedule of Values and Applications for Payment with the Task Order CPM

Schedule, List of Subcontracts, and Submittal Log.

B. Related Sections include the following:

1. Division 01 Section “Unit Prices” for administrative requirements governing use of unit prices.

2. Division 01 Section “Measurement and Payment” for administrative requirements governing methods of measurement and determination of quantities of materials for use with unit prices.

3. Division 01 Section “Construction Progress Documentation” for administrative requirements governing preparation and submittal of the Contractor’s CPM Schedule and

Submittals Schedule.

4. Division 01 Section “Project Closeout” for submittal of items required before final payment.

5. Division 01 Section “Project Record Documents” for procedural requirements governing the submission of Project Record Documents.

6. Division 01 Section “Operation and Maintenance Data” for submittal of items required before final payment.

7. Contract Article 11.

1.3 DEFINITIONS

A. Schedule of Values: A written statement furnished by the Contractor allocating the entire Task

Order Price to the various portions of the Work for that Task Order and once accepted by the

Contracting Officer, to be used as the basis for reviewing the Contractor’s Applications for

Payment. Notwithstanding the foregoing, the Construction Services General Conditions Fee, and the incentive amount, if any, earned under Contract Section 6.2.2, shall be shown as separate line

APPLICATION FOR PAYMENT 012900 - 2

items in the Schedule of Values. A separate Schedule of Values shall be furnished by the

Contractor for each construction services Task Order.

1.4 SCHEDULE OF VALUES

A. Coordination: Coordinate the preparation of the Schedule of Values with the preparation of the

Contractor’s CPM Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with Continuation Sheets.

b. Submittals Schedule.

c. Contract CPM Schedule.

d. List of products.

e. List of principal Suppliers and fabricators.

2. Submit the Schedule of Values to Contracting Officer at earliest possible date, but no later than 14 calendar days after receiving the Task Order.

a. The cost-loaded CPM Schedule will satisfy the requirements for the Schedule of

Values.

3. Sub-schedules: Where the Work is separated into phases requiring separately phased payments, provide sub-schedules showing values correlated with each phase of payment.

B. Format and Content: Use the Construction Work Package Specifications table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each

Specification Section. Format and content is to be per AIA Document G703, Application and

Certificate for Payment – Continuation Sheet, or equivalent.

1. Identification: Include the following information on the Schedule of Values:

a. Contract number and name.

b. Task order number and name.

c. Contractor’s name.

d. Date of submittal.

2. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division.

b. Description of the Work.

c. Name of Subcontractor.

d. Name of manufacturer or fabricator.

e. Name of Supplier.

f. Task Order number and Contract Modification(s) that affect the schedule of values.

g. Dollar value.

APPLICATION FOR PAYMENT 012900 - 3

1) Percentage of the Task Order Price to the nearest one-hundredth percent, adjusted to total 100 percent.

3. Provide a breakdown of the Task Order Price in enough detail to facilitate continued evaluation of the Applications for Payment and progress reports. Coordinate with the

Construction Work Package Specifications table of contents. Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for the following items.

4. The value assigned to the total of these line items shall be a minimum of 5 percent of the

Task Order Price:

a. Start-up and commissioning activities.

b. Operation and Maintenance manuals.

c. Punch list activities.

d. Project Record Documents.

e. Warranties.

f. Demonstration and training.

5. Round amounts to nearest whole dollar. Total shall equal the Task Order Price.

6. The Contractor shall include all test and inspection activities in its CPM schedule and establish a Schedule of Values for all required QC documentation, all tests and inspection activities, reports, and procedures required in the Construction Documents on a Section by-

Section basis. Additionally, the Contractor shall include a pay line item specifically for

Quality activities and QC Organizational personnel.

7. Provide a separate line item in the Schedule of Values for each part of the Work where

Application for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between potential items stored on-site and items stored off-site. Include evidence of insurance or bonded warehousing if required.

8. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

9. Include a separate line item in the Schedule of Values for the Construction Services General

Conditions Fee.

10. Each item in the Schedule of Values and Application for Payment shall be complete as a requirement for payment.

11. Schedule of Values Updating: Update and resubmit the Schedule of Values with the next

Applications for Payment when Contract Modifications result in a change in the price of a

Task Order.

1.5 APPLICATION FOR PAYMENT

APPLICATION FOR PAYMENT 012900 - 4

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Contracting Officer Representative and paid for by the GPO.

1. Each Application for Payment shall be sub-divided by Task Order.

2. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: Application for Payment shall coincide with the monthly update of the Contractor’s CPM schedule. The period covered by each Application for Payment starts on the day following the end of the preceding period and shall not exceed one…