J-8 SDSSS RFP Materials Schedule.pdf

PDF 133 KB Posted

Attached to
Steel Storage Services for LBNF/DUNE US Project Federal contract opportunity
Solicitation number
LBNF-343096-JD
Issued by
Department of Energy Fermi National Accelerator Laboratory

About this file

This estimated materials schedule provides details for a federal contract opportunity to provide steel storage services for the Long Baseline Neutrino Facility/Deep Underground Neutrino Experiment US Project. The schedule outlines the estimated tonnage and delivery timelines for structural steel, skin components, and fasteners needed for two cryostats. It estimates that 2526 US tons of red structure steel, 656 tons of warm skin components, and 276 tons of fasteners will be required with the first cryostat's components to be delivered between April 2024 and August 2025 and the second cryostat's between January 2025 and September 2026. The related solicitation was issued by the Department of Energy Fermi National Accelerator Laboratory seeking storage services for these steel components to support the LBNF/DUNE US Project with an anticipated award period between August 2024 and September 2026.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-8

South Dakota Steel Storage Services Estimated Materials Schedule

Materials ETA:

Storage Period:

Installation Period:

Components US Ton

Red Structure Steel Components 2526

Warm Skin Componenets 656

Fasteners 276

Total 3458

Materials ETA:

Storage Period:

Installation Period:

Components US Ton

Red Structure Steel Components: 2526

Warm Skin Componenets: 656

Fasteners 276

Total: 3458

Cryostat #2

January 2025

Volume:

CRYOSTAT STEEL COMPONENTS DELVERY SCHEDULE

Cryostat #1

April 2024

August 2024 – August 2025

Volume:

May 2025 – September 2026

April 2024 – August 2025

January 2025 – September 2026