This past performance reference form is used to evaluate contractors for a roof metalwork construction project at the Honolulu Control Facility in Honolulu, Hawaii. The solicitation is for base building roof metalwork and requires adherence to specifications, drawings, contract clauses and wage rates. Respondents are to fill out contact and project details and have a point of contact from the owner's entity evaluate the contractor's past performance on a similar project using a rating scale. Evaluated areas include resources, responsiveness, commitments, coordination, safety, change orders and personnel. Additional commentary is requested on project accuracy, performance and quality of work. The form requests the evaluator's signature and contact information and permission for the Federal Aviation Administration to follow up.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAST PROJECT PERFORMANCE REFERENCE FORM
For FAA Construction Services Solicitation RFO 697DCK-23-R-00XXX
1. Contractor Name:
2. Contractor Location (City, State):
3. Title of Construction Project:
4. Location of Construction Project
(City, State):
5. This Contractor was:
___ Prime Contractor
___ A Sub-Contractor
Prospective Contractor or Subcontractor, please fill out the above information and provide the following two items to a POC of the Owner Entity who is familiar with your work on this past project and can fill out this performance survey form and respond:
(1) A copy of the Past Project Record for this project that is being submitted for this Solicitation.
(2) This Past Project Performance Reference Form.
Survey respondent, please return the completed survey by e-mail to:
Darren Odegard, FAA Contracting Office
206-231-3002, darren.odegard.faa.gov
Owner’s POC’s Evaluation and Commentary regarding
Contractor’s Performance on This Project
1 - Unsatisfactory, 2 - Marginal, 3 - Satisfactory, 4 - Good, 5 - Outstanding, N/A - Not Applicable 1.
Did the Contractor provide adequate resources in timely fashion to meet the requirements and complete the work?
1( 2( 3( 4( 5( N/A( 2.
To what extent did the Contractor respond positively and promptly to technical direction, information requests, issues or problems needing correction, etc., during the course of the Work?
1( 2( 3( 4( 5( N/A( 3.
How reliably did the Contractor follow through on commitments?
1( 2( 3( 4( 5( N/A( 4.
Did the Contractor’s work coordinate with, accommodate, and not disrupt the ongoing operation of the facility during construction?
1( 2( 3( 4( 5( N/A( 5.
Did the Contractor comply with construction safety requirements?
6.
Were any requests for change order Contract amount increases justified, reasonably costed, and, if necessary, negotiated with prompt, acceptable resolution?
6.
Were the Contractor’s project management, site supervision and work crews capable, experienced and consistence throughout the course of the project? Was there no turnover or low turnover in the Contractor’s project personnel?
7.
What was your level of satisfaction with the Contractor’s project management?
1( 2( 3( 4( 5( N/A( 8.
What was your level of satisfaction with the Contractor’s on-site supervision?
1( 2( 3( 4( 5( N/A( 9.
What was the quality of the project construction Work?
1( 2( 3( 4( 5( N/A( 10.
Was this Contractor professional, positive and easy to work with?
1( 2( 3( 4( 5( N/A( 11.
Extent you would recommend this Contractor for a similar construction project?
1( 2( 3( 4( 5( N/A( To the extent you know, is the project information on the Contractor’s Past Project Report accurate?
___ Yes ___ No ___ I have insufficient knowledge of the project details to know.
If no, do you have any more accurate information:
Comments on the Contractor’s Performance and their Work:
Responding POC’s Name: ______________________________________________ Project Owner Entity and responding POC’s work role within the Owner Entity:
Responding POC’s work role on the project:
Responding POC’s Contact Phone Number(s) and E-mail:
Can the FAA contact you by telephone with any additional reference questions?
____ Yes. ____ No.
Signature: _____________________________________ Date: _____________________________________ HCF Roof Solicitation / Past Performance Reference Form / DRAFT 10-31- 2022 / Page 1 of 3