This is a Bid Addendum No. 1 issued by Gordon State College in Barnesville, Georgia for Project No. J-432, a Campuswide HVAC and Electrical System Renewal project. The addendum establishes a second mandatory site visit scheduled for Tuesday, July 22, 2025, from 9:00 AM to 11:00 AM, during which Buildings 2, 6, and 27 on the GSC campus will be open for contractor inspection. The original bid deadline has been extended to July 30, 2025, at 2:00 PM. The question deadline has been extended to 2:00 PM on July 23, 2025, with formal responses to be posted the following day. Supplemental drawings and specifications will be posted concurrently with the formal responses to bidder inquiries.
No information regarding pricing terms, set-asides, incumbents, funding sources, or contract renewal options is included in this addendum document. The file contains a reference to Exhibit 1, identified as a Contractor Sign-In Sheet dated July 3, 2025, though the detailed contents of that exhibit are not provided in the available text.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sample Contract.pdf | ||
| GSC J_432 Project Manual.pdf | ||
| GSC J_432 DBB Award.docx | DOCX document | |
| J_432 GSC GC _ ADDENDUM 2.pdf | ||
| Bid Tab.pdf | ||
| J_432 GSC _ GC ADDENDUM 3.pdf | ||
| J_432 GSC GC _ ADDENDUM 4.pdf | ||
| GSC J_432 Drawings.pdf | ||
| GSC J_432 Bid Package.pdf | ||
| GSC J_432 DBB_Award.docx | DOCX document | |
| J432 2025_07_14_GSC_Hvac_ElecRenewal_Add_2_NB.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID ADDENDUM NO. 1
July 15, 2025
Project No.: J-432
Campuswide HVAC and Electrical System Renewal Gordon State College, Barnesville, Georgia
Invitation to Bid
Campus will host a second mandatory site visit for all interested contractors:
Date: Tuesday, July 22, 2025 Time: 9:00 AM to 11:00 AM Location: Buildings 2, 6, and 27 (on GSC Campus) will be open for inspection
See enclosed map for building locations
Bid Date has been extended to July 30th, 2025, at 2:00 PM
The question deadline extended to 2:00 PM on July 23, 2025, and formal responds will be posted the following day. Supplemental drawings and specifications to be posted with formal responses.
Exhibit 1: Contractor Sign-In Sheet (7/3/2025)
END OF BID ADDENDUM #1