J-1501000-02 NSWC Demolition Statement of Work_Site Visit.pdf

PDF 7 MB Posted

Attached to
FY24 Demolition Contract – Multiple Buildings (B116A, B217, B312, B360, B1312, & B2014) Federal contract opportunity
Solicitation number
N4008024B5092
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document is a Request for Demolition Package for the FY24 Demolition Contract - Multiple Buildings (B116A, B217, B312, B360, B1312, & B2014) at the Naval Support Facility (NSF) in Dahlgren, VA. The solicitation includes the demolition and removal of several buildings and associated site features on the naval installation. Key details include:

The base scope is to completely demolish the identified buildings, including removal of all foundations, utilities, site amenities, and site restoration activities. The project requires asbestos, lead, and other hazardous materials abatement prior to demolition. Specific requirements are outlined for disposal of hazardous waste, refrigerants, and other regulated materials. The contractor must coordinate closely with the government's cultural resources and natural resources programs due to historic buildings and protected species. Unexploded ordnance procedures and safety precautions are also required. The contractor must submit a detailed demolition plan for government approval prior to start of work. The solicitation is being issued as an Invitation for Bid (IFB) under Solicitation Number N4008024B5092.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST DEMO PACKAGE Eprojects #: 1799880

NAVFAC South Potomac Dahlgren

Facilities Engineering Division

WORK DESCRIPTION

Demolish Buildings 116A, 217, 312, 360, 1312, & 2014

1. PROJECT DESCRIPTION:

a. The base scope of this project is to completely demolish buildings/structures 116A (Electric distribution Bldg/storage Building), 217 (BOQ), 312 (RDT&E storage lab), 360 (Screen Tower), 1312 (MWD kennel), and 2014 – (Press Box/Score Board Building) and restore sites.

Project will consist of complete facility demolition, including the total removal of all foundations, removal and disposal of all utilities, site amenities, and associated site features.

Demolition will include the termination of all site utilities (water, power, telecommunications etc.). Hazardous material testing and containment will be performed at all sites prior to the start of demolition. Site restoration activities will include back filling, grading and seeding the disturbed sites.

b. Building Descriptions The descriptions below for all facilities are brief. Please refer to attachment A for more detailed building descriptions.

a. Building 116A – Electric distribution Bldg/storage Building - an existing one- story building, on a slab on grade. The building footprint is approximately 240 square feet. This building acted as an electric distribution Bldg and then was converted to a storage Bldg administrative storage (RDY ISS/shop Str/misc). It has two storage rooms. This building was built in 1921 and has a historical status of NCE Non-Contributing Element of NHL/NRL/NRE District. The facility is not in use due to condition and “spaces are too small to be effectively used for any purpose. Abandoned electrical equipment takes up half the space.”

b. Building 217 - BOQ - an existing two-story building, on a slab on grade. The building is 181'x 139' x 31' height with a total internal area of approximately 19,932 square feet. This building has been vacant for over 8 years and has severe mold and does not meet code compliance for OSHA and fire. The building interior configuration does not meet market standards for BOQ. This building was built in 1942.

c. Building 312 - RDT&E storage lab (adjacent to Building 441) - an existing one- story building, on a concrete pier foundation approximately 3' above grade. The building dimensions are 29'x21'x13'H with a total internal area of approximately 814 square feet. The building currently has a partially collapsed roof. The building was built in 1943.

d. Building 360 - Screen Tower (Located on Main Range) - is an existing 120' tall exposed metal framed tower. The footprint of the structure is approximately 20'x20' (400 square feet).

This structure was built in 1936.

e. Building 1312 - MWD kennel (working animal support building) - an existing one story structure that is approximately 24'x6' with 8' high metal fence enclosed runs all on an approximate 30'x24'x6" concrete slab. The structure has a 6" concrete turn down foundation.

This building was built in 1969. The existing yard hydrant and the associated underground supply line will also be demolished.

f. Building 2014 - Press Box/Score Board Building (adjacent to Fire Department Baseball field) - an existing two-story building, on a slab on grade with a single room on each story.

The building is 16'x12'x20'H and footprint of approximately 192 square feet. The exterior stairs to the second floor is currently missing. This building was built in 1993.

c. Working Hours

All work is to take place at Naval Support Activity South Potomac (NSASP) Dahlgren, VA for Buildings 116A, 217, 312, 360, 1312, and 2014. Any work done during normal working hours shall be done in a manner with minimal disturbance to the buildings occupants. Normal working hours are defined as Monday – Friday 0700-1600. Any building escorts are to be provided by the end user.

d. Access and Passes All Contractor employees, including subcontractors, subcontractors’ employees, suppliers, and suppliers’ employees are required to comply with the Installation Security Requirements regarding personnel, vehicle, and equipment security passes and access to the jobsite. Nothing in the contract is to be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons or personnel and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard the station.

Coordinate with the Contracting Officer for specific security and access requirements.

a. Access to Buildings/Occupied Buildings: The Contractor may work in or around occupied buildings. The Contractor is responsible, via the Contracting Officer, to obtain access to the building and facilities and arrange for them to be opened and closed. Do not enter the building(s) without prior approval of the Contracting Officer. Contract personnel will not be permitted in security-regulated buildings or areas unless cleared by the Security Officer. In addition, buildings located within operational areas of the station, must be given approval by Range Control and therefore, must work with the Contracting Officers Representative (COR) to arrange for access to these facilities.

b. Passes and Badges: Contractor employees and representatives performing work under this contract are required to be either United States citizens or documented legal residents (status verified by the prime contractor). All Contractor employees must obtain the required contractor employee and vehicle passes. Each employee is required to wear and display the

Government issued badge over the front of outer clothing. Failure to obtain security and base access passes must not be a cause for contract performance time extension(s) or delays in performance of the contract. The Contractor is required to immediately turn in all terminated employee's badges to the issuing office.

c. Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential. Participation in DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access the installation. Registration for DBIDS includes: Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer that provides personnel the purpose for access to the base Visitor Control Center representative.

a. Present valid identification, such as a passport or Real ID Act- compliant state driver's license.

b. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html.

c. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.

d. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to the work site.

1.1 Dig Permit Approval

The Contractor is required to obtain a dig permit prior to the start of any construction or demolition related activities on-site. In order to obtain the dig permit, the Contractor must first obtain Miss Utility Ticket for the project site(s), so outside utilities such as, Verizon telephone and Comcast cable can be marked by the service provider. Once the utility ticket is obtained and the service provider has marked the utilities, then the utility ticket is forwarded to the Contracting Officer’s Representative (COR), so that the COR can have base utilities personnel mark all Government Owned utilities. At the conclusion of the utility markings, a dig permit will be issued to the Contractor via the COR. The permit is good for two (2) weeks at a time and will be re-issued by the Government; however, once marked, the Contractor is now responsible for up-keeping the utility makings throughout the contract duration.

1.2 Hot Work Permit

Prior to performing any “Hot Work” (e.g. welding, cutting or torching) or operating other flame-producing/spark-producing devices, request a written permit from the Fire Division.

CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE A PERMIT IS

ISSUED. It is mandatory to have a designated FIRE WATCH for any “Hot Work” done on this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site as required after completion of the task or as specified on the hot work permit.

2. APPLICABLE CODES AND STANDARDS:

The design and construction shall be in accordance with the latest revision/edition of the following referenced codes and standards. The term "Latest Revision/Edition" is defined as the version as of the project award date.

1. International Mechanical Code (IMC)

2. International Building Code (IBC)

3. National Electrical Code (NEC)

4. International Plumbing Code (IPC)

5. Unified Facilities Guide Specifications (UFGS)

6. Unified Facilities Criteria (UFC)

7. ASHREA Standards

8. US Army Corps of Engineers Safety and Health Requirements Manual EM 385

3. Site Demolition Work:

a. Existing building utility connections, including water, power and communications shall be removed from the building/tower back to the nearest supplying manholes or transformers and water/sanitary sewer lines removed back to main lines and suitably plugged or capped at the removal limits as shown in the Notional Demo Plan Attachment 3.

b. Utility demolition and removal must be coordinated with on-site personnel for planned outages. Contractor personnel shall allow at least two weeks for outage request approvals prior to performing the work. The contractor shall take additional care to not damage utilities located within the demolition site area that are not building specific and that are to remain in use throughout the project and in the future. If the contractor is unsure which utilities are to remain, they should submit an RFI to allow NAVFAC to clarify.

c. Existing sidewalks, pavement and other associated features will be completely removed.

d. Contractor shall install and maintain sediment and erosion control measures, such as, silt fence and storm water inlet protection prior to the start of site demolition work.

4. Building/Structure Demolition Work:

1. Demolish the structures to include the tower truss, porches, stairs and landings, walls, slab, footings and foundation.

2. Structures shall be demolished in a systematic manner, from the top of the structure to the ground.

Mechanical Work:

1. Remove all mechanical, plumbing, and fire protection systems and equipment completely, including but not limited to: air compressor units, exhaust fans, unit heaters, pumps, water heaters, air handling equipment, sprinkler system components, ductwork and diffusers, mechanical and plumbing piping, valves, control components, panels and wiring. Remove any existing, external, above-ground piping routing to facility and support structures.

2. Remove air conditioning, refrigeration, and other equipment containing refrigerants without releasing chlorofluorocarbon refrigerants to the atmosphere in accordance with the Clean Air Act Amendment of 1990. Recover all refrigerants prior to removing any air conditioning, refrigeration, and other equipment containing refrigerants and dispose of in accordance with Class I and Class II ODS as defined in Section 602 (a) and (b) of the Clean Air Act. Place recovered ODS in cylinders meeting AHRI Guidelines K suitable for type ODS (filled to no more than 80% capacity) and provide appropriate labeling and turn into the Navy as directed by the Contracting Officer.

Electrical Work:

1. Remove all electrical systems and equipment completely, including but not limited to:

lighting, receptacles, disconnects, electrical wiring and conduit.

5. CONTRACTOR CLEANUP:

Contractor shall be responsible for and not limited to:

a. Providing necessary safety to protect any adjacent existing buildings, landscape ad associated features.

b. Cleaning up debris on project site at the end of each working day.

c. Properly dispose of removed materials and debris at completion of project.

d. Disposal of demolished material and equipment.

6. SITE RESTORATION:

Contractor shall be responsible for and not limited to:

a. After completion of the demolition, all disturbed areas shall be re-graded to restore natural drainage patterns and returned to open turf cover with topsoil or clean fill and seeding. The demolition site shall be compacted, graded and free from protrusions, demolition debris and abrupt edges.

b. Once seed is established and approval is given by the Environmental Department Representative, Contractor shall remove sediment and erosion control devices.

7. OTHER PROJECT REQUIREMENTS:

Cultural Resources:

Buildings 312 and 360 are both historic and contributing elements of the Mainside Historic District. A Memorandum of Agreement has been developed to mitigate the adverse effects associated with their demolition that will require certain stipulations related to the demolitions.

This MOA will need to be executed prior to the demolition of these two specific buildings.

Coordinate with the Cultural Resources Program Manager prior to any work commencing on B.

312 or B. 360. Ground disturbance related to the demolitions should not impact cultural resources since the areas around the buildings are already heavily disturbed by construction and infrastructure. If suspected artifacts are discovered, stop work and contact the Cultural Resources Program Manager at 540-850-0698.

Natural Resources/Species Protection Conditions:

1. All buildings scheduled for demolition shall be inspected by the NRM prior to beginning activities for the presence of bat colonies or hibernating bats (depending on the time of year).

During the active colony season (01 March – 31 August), bat colonies shall not be removed/excluded without approval from Virginia Department of Wildlife Resources (VDWR) and work shall be conducted by a licensed nuisance wildlife control cooperator that is specifically authorized to conduct bat work. Demolition of buildings between 01 September and 28 February will require an inspection by the NRM to ensure hibernating bats are not present. A supplemental bat box of appropriate size shall be erected in close proximity to any building that is determined to be a bat roosting site and is scheduled for demolition prior to the beginning of demolition.

2. There is an osprey nest that is rebuilt and used each year at building 220 which is adjacent to building 217. If the nest is deemed active and contains eggs or young, then demolition of 217 would need to occur after the osprey nesting season to avoid impacting the nest efforts. If demo is slated to occur during the nesting season, then the nest can be removed as often as needed as long as there are no eggs and young present.

3. There has been historical evidence that ospreys nest on building 360 (Screen Tower) and similar time of year restrictions would need to be adhered to if a nest is established prior to demolition.

Earth Disturbance Conditions:

- Seed and straw disturbed areas. Seed mix shall not contain sericea lespedeza or Kentucky 31.

- If erosion control matting is needed, the use of 100% biodegradable material such as jute matting is required (non-biodegradable synthetic fiber erosion control matting is not permitted).

General Hazardous Component Abatement:

Reports, performed in 1990, identify that ACM are present in the B217 facility. A report for each of the following: asbestos, lead based paint, mercury, and PCBs will need to be performed to support this project at all demolition locations. The General Contractor is required to hire, as a first tier subcontractor, a PQP to ensure compliance with the approved work plans and perform independent inspections, testing and verification, and abatement of the hazardous components work including: asbestos, lead containing paint, mercury containing equipment, LLR components, PCBs, animal droppings, molds and spores. B116A is suspected to have ACM siding, but no report exists to substantiate.

Waste (Hazard and Non-Hazard) Conditions:

Worker Safety Lead and Asbestos Contamination:

- Lead and asbestos surveys must be performed on the work area prior to start of work. Asbestos surveys shall be performed by certified EPA AHERA Inspectors and lead surveys shall be performed by certified Lead Inspectors or Risk Assessors. Digital copies of laboratory analysis (asbestos/lead) from samples shall be forwarded to the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger ), Dahlgren Environmental POC (Brendon Harp), and Safety Specialist (Jim Cole). If lead and/or asbestos-containing materials are identified the following conditions apply:

- Federal and State requirements for proper management of asbestos for demolition and disposal, included in (VSWMR) 9VAC20-81-620, and the National Emission Standard for Hazardous Air Pollutants (NESHAP) regulations, 40 CFR Part 61 Subpart M, contain standards for managing asbestos-containing waste materials (ACM). Requirements include: completion of proper surveys prior to work, development of proper work plans, notifications to regulators, implementation of proper controls and worker protection, proper supervisor and work licensing, waste disposal, and record keeping.

- A digital copy of the work plan for asbestos abatement/removal shall be submitted to the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Attn: Paul

Wenninger, Paul.s.wenninger.civ@us.nay.mil, 301-885-6963), Safety Specialist (Attn: Jim Cole), and Dahlgren Environmental POC (Attn: Brendon Harp) for review and acceptance. NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager will review reports, submit comments (if any), and provide final acceptance.

Upon acceptance of the work plan, contractor shall develop appropriate regulatory notifications.

Submit a minimum of 15 working days prior to intended activity. Notification to VDEQ will be required if greater than 10 square feet (or 20 linear feet) of asbestos will be disturbed. Appropriate notification to both VDEQ and EPA shall be made if greater than 160 square feet, 260 linear feet or 35 cubic feet of asbestos will be disturbed.

- Contractor must notify the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger ) and Dahlgren Environmental POC (Brendon Harp, 202-718-0655) prior to contacting or notifying VDEQ or EPA of any abatement activity.

- Records for the asbestos project must be maintained by the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger ) for at least 6 years. Records must include the location and description of the project, the estimated amount of asbestos removed, start/completion dates, summary procedures used to comply with regulations, and disposal manifest with name/address of disposal site.

- Contractor must follow the Unified Facilities Guide Specifications, 02 82 16. 0020,“Engineering Control of Asbestos Containing Materials.” Contractor's worker safety plan for asbestos abatement must be submitted to the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Attn: Paul Wenninger ) and Dahlgren Environmental POC (Attn: Brendon Harp, 202-718- 0655) prior to project execution.

- Contractor must follow the Unified Facilities Guide Specifications, 02 83 13.0020 "Lead In Construction." Contractor’s worker safety plans for lead abatement must be submitted to the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger ) prior to project execution.

- A digital final copy of the contractor's final lead and asbestos clearance and analysis report must be provided to the Supervisor of the Industrial Hygiene Office (Attn: Kenneth D. Waits, Kenneth.d.waits4.civ@mail.mil, 301-744-4855) for review and records maintenance. Waste (Hazard and Non-Hazard) Conditions

- Metal should be recovered from demolition for recycling to the maximum extent possible. Any recyclable metal with lead paint does not require removal of that lead paint prior to recycling. The lead paint may remain on the metal parts (stairs, window/door frames, metal siding, crane components, structural supports, etc.). Some of the remaining building materials contain lead. The entire waste stream for the demolition project will require TCLP testing for lead. If the entire waste stream TCLP's positive for lead, review the lead survey and remove all highly leachable lead components from the waste stream, then retest. Consult the NSF Dahlgren Environmental Office (Brendon Harp, 202-718-0655) for guidance.

- Contractor must coordinate storage of any generated hazardous waste with the NSF Dahlgren Environmental Office. Offsite shipments of any hazardous waste remain the responsibility of the contractor and may only be signed by a government employee specifically authorized by the Installation Commanding Officer, coordinated by the NSF Dahlgren Environmental Office. Brendon Harp will be the primary point of contact for government signature of the asbestos shipping documents, please coordinate with Mr. Harp prior to the shipment date to arrange specifics.

Air

- For any project involving demolition and/or renovation activities, 40 CFR 61, Subpart M must be complied with to ensure asbestos does not become airborne.

Lead CWAP Language Worker Safety Lead Contamination:

- Lead surveys must be performed on the work area prior to start of work. Lead surveys shall be performed by certified Lead Inspectors or Risk Assessors. Digital copies of laboratory analysis from samples shall be forwarded to the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger), Dahlgren Environmental POC (Brendon Harp, 202-718-0655), and Safety Specialist (Jim Cole, 540-653-3281). If lead is identified the following conditions apply:

- Contractor must notify the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger) and Dahlgren Environmental POC (Brendon Harp, 202-718-0655) prior to contacting or notifying VDEQ or EPA of any abatement activity.

- Contractor must follow the Unified Facilities Guide Specifications, 02 83 13.0020 "Lead In Construction." Contractor’s worker safety plans for lead abatement must be submitted to the NAVFAC South Potomac Lead Based Paint and Asbestos Program Manager (Paul Wenninger) prior to project execution.

- A digital final copy of the contractor's final lead clearance and analysis report must be provided to the Supervisor of the Industrial Hygiene Office (Attn: Kenneth D. Waits, kenneth.d.waits4.civ@mail.mil, 301-744-4855) for review and records maintenance.

Other Work Restrictions Contact the GIS Analyst upon project completion so that the Navy's GIS geodatabase can be updated (ie. buildings, structures, utilities, etc) Note:

GIS Analyst position is currently vacant, Interim POC: Rob Hupp, 201-757-4863 Buried Utilities Conditions

- Utility Location Required - No later than 5 business days prior to project execution, project manager must submit a request to Miss Utility for phone line location and submit a utility location request to the service desk (540-653-8230) for Mark Shelton (540-653-2766) to perform base utility location.

- PDS & TPDS Required - If site markings are purple, no excavation without prior notification from NSWCDD 1041 (540-653-3142/6309).

General Explosive Contamination Abatement:

Structures, in which explosive materials have been managed and/or stored, may contain explosive residues hidden within cracks, crevices, under flooring, in ventilation ducts, behind wall panels, etc. Friction or impact from dismantling the structural components can present a potential detonation hazard that must be evaluated and addressed prior to dismantling/demolition operations.

The decommissioning and demolition of an explosives- contaminated structure may present unobvious hazards requiring application of specialized knowledge and expertise as well as implementation of established regulatory safety programs. Consequently, the decommissioning and demolition of structures should be preceded by a comprehensive planning process and be conducted in accordance with both established and project-specific safety procedures. This process shall include a Safety and Environmental Hazard Review and Site Inspection, Work Plan Development, Obtain Permits, Gain Approval, Implementation of Work Plan, Test Debris and Soil for Reactivity/Toxicity. Activities involving ammunition and explosives or their constituents or chemical warfare agents have additional requirements as specified in EM 385-1-97, Explosives Safety and Health Requirements Manual. If tests show no reactivity/toxicity in

Structures Containing Blasting Agents:

Decontamination of structures that have contained blasting agents composed of high percentages of water soluble, hygroscopic salts such as ammonium nitrate and fuels may be achieved by sweeping or other physical means. Water wash down usually results in the safe decontamination of this building category. In certain cases, collecting and treating the wash down water may be required.

Open burning is not recommended for this explosives contaminated building category. Structures Containing Black Powder and Pyrotechnic Mixtures: Decontamination of black powder and similar pyrotechnic mixtures may also be achieved by mechanical cleaning followed by water wash down.

However, due to the ease of ignition after drying, burning is recommended for this building category.

Structures Containing Other Explosive Chemicals and Compounds:

Water insoluble molecular explosives such as nitroglycerin, tetryl, TNT, PETN, RDX, and HMX require special decontamination and dismantling procedures. These procedures may include sweeping and physical removal followed by steam cleaning of equipment and the use of solvents, such as acetone, or a desensitizing oil prior to the removal of threaded fittings. Trinitroresorcinol, lead styphnate, lead azide, mercury fulminate and other initiating explosives are quite sensitive to initiation by heat, impact and friction. These materials present the supplemental problem of residual metal contamination after the criteria of reactivity is eliminated. Structures that have contained these two groups of explosives require soil monitoring to assure complete, safe closure of the site.

Bioremediation or ash and soil removal may be required. It is highly recommended that buildings used to manufacture or process any of these two groups of explosives be burned to eliminate possible hazards associated with reactive materials that may have accumulated in cracks, crevices or larger spaces within the floors and walls.

Unexploded Ordinance (UXO)/Munitions & Explosives of Concern (MEC) Monitoring & Clearance:

- Bldg. 102 shall be downloaded of all explosives while facilities 312 and 360 are being demoed.

- All ammunition and explosives shall remain at rest inside of Magazine Area 2 while facility 1312 is being demoed.

- A UXO surface sweep shall be conducted by EOD or a Certified UXO Technician prior to the demolition of facility 360 (Main Range Tower) to ensure the area of work is clear of UXO/MEC.

- To avoid concurrent explosive operations, all work shall be coordinated and scheduled with Range Control (x540-653-8791) at least 5 days in advance. POC for scheduling is Michael White.

- There shall not be any ammunition/exploisve testing conducted on Main Range while facilities 312 and 360 are being demoed.

- Onsite Construction Workers shall contact Range Control (x540-653-8791) daily prior to the start of work to ensure explosive operations are not being conducted in the areas of facilities 312, 360, and 1312.

- Onsite Construction Workers shall adhere to range barricades and postings at all times, and shall only gain permission from Range Control prior to entering an area that has been barricaded.

- The likelihood of encountering UXO/MEC in the area of facilities 1312, 217, 2014, and 116A is very low. In the unlikely event a suspect explosive item is found, contact Range Control @540-653- 8791 or Dispatch @ 540-653-8291/8095 for EOD support.

- If MEC is found for any of the facilities being demoed, then work will not recommence until follow-up actions by the NSWCDD/NSASP ESO have taken place.

- See attached ESR MEMO for any additional Explosive Safety comments/requirements.

8. Required Contractor Submittals:

a. Demolition Plan: Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal, separation and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations.

b. See section C and Section F for additional information.

GENERAL NOTES:

1. Job site and field conditions shall be verified prior to beginning work. Plans herein are schematic in nature. The layout is based on the best available information.

Existing conditions and field conditions shall be verified by the contractor.

2. Assume that there are electrical wires to be capped and or removed located underground.

3. ALL utilities and associated equipment are to be removed and sealed/capped.

4. Unless otherwise noted foundations and pavements are to be completely removed.

5. Buildings/Structures have been clearly listed and identified in documents. Any additional buildings shown in maps are for reference only.

BUILDING/STRUCTURE DETAILS FOR BUILDINGS

116A, 217, 312, 360, 1312 & 2014

Building 116A (Electric Distribution Bldg/Storage Building):

CURRENT CONDITIONS

Building 116A is an existing one-story building, on a slab on grade. The building footprint is approximately 240 square feet. This building acted as an electric distribution Bldg and then was converted to a storage Bldg administrative storage (RDY ISS/shop Str/misc). It has two storage rooms. This building was built in 1921 and has a historical status of NCE Non-Contributing Element of NHL/NRL/NRE District. The facility is not in use due to condition and “spaces are too small to be effectively used for any purpose. Abandoned electrical equipment takes up half the space.”

Substructure General:

1. The substructure consists of reinforced concrete slab on grade and concrete foundation walls.

Superstructure General:

1. The exterior walls primarily consist of 2x4 wood studs, at 16”o.c. with ½” gypsum wall board. The framing of this structure, for the most part, utilizes dimensional lumber. The crawl space is covered by ½” thick steel plates in the electrical room.

2. The roof framing consists of wood roof trusses that span from exterior wall to exterior wall. The roof is an asphalt shingle roof.

3. This structure shall be demolished in a systematic manner, from the top of the structure to the ground.

Interior General:

1. The interior construction and finishes at Building 116A are wood stud, gypsum board walls and gypsum board ceilings.

Figure 1 ‐ Building 116A (Electric Distribution Bldg/Storage Building) Partial Interior

Mechanical General:

1. Mechanical equipment includes but is not limited to: unit heater, wall unit AC, ventilation fan, control components, panels, and wiring.

Electrical General:

1. Electrical systems and equipment includes but is not limited to: panel boards, lighting, receptacles, disconnects, electrical wiring and conduit, wiring, and backbone, devices and associated wiring.

Figure 2 ‐ Building 116A (Electric Distribution Bldg/Storage Building) Partial Interior

Figure 3 ‐ Building 116A (Electric Distribution Bldg/Storage Building)

ADDITIONAL DETAILS:

See Attachment # 5 for images of historical construction drawings. If readability is an issue the contractor may request to see the physical drawings located in building 182 by contacting James Johnson (202-812-2953).

The work to be performed includes but is not limited to:

1. Prior to any demolition activities the contractor shall install approximately 100 linear feet of construction and silt fence around each demolition site.

2. Assume that demolition includes the removal of at least 20 square yards of concrete pavement.

3. Assume that demolition includes the removal of at least 100 square yards of bituminous pavement.

Figure 4 ‐ Building 116A (Electric Distribution Bldg/Storage Building)

Figure 5‐ Building 116A (Electric Distribution Bldg/Storage Building) Map View

Building 217 (BOQ):

CURRENT CONDITIONS

Building 217 – BOQ - an existing two-story building, on a slab on grade. The building is 181’x 139’ x 31’ height with a total internal area of approximately 19,932 square feet. This building has been vacant for over 8 years and has severe mold and does not meet code compliance for OSHA and fire. The building interior configuration does not meet market standards for BOQ. This building was built in 1942.

Substructure General:

1. See attached drawings in Section J- Attachment 4 B217 Historical Drawings

Superstructure General:

1. See attached drawings in Section J- Attachment 4 B217 Historical Drawings

Interior General:

1. The interior construction and finishes at Building 217 reflects gypsum board and Vermiculite walls, gypsum board, acoustical tile, and fiberglass ceilings. Floor finishes include carpet, vinyl tile, wood, and vinyl sheet.

2. See attached drawings in Section J- Attachment 4 B217 Historical Drawings

Mechanical General:

1. See attached drawings in Section J- Attachment 4 B217 Historical Drawings

Electrical General:

1. Electrical systems and equipment includes but is not limited to: lighting, receptacles, disconnects, electrical wiring and conduit.

2. See attached drawings in Section J- Attachment 4 B217 Historical Drawings

ADDITIONAL DETAILS:

The contractor shall remove all associated utilities, sidewalk, signage, and landscaping as part of this

SOW.

Any earth exposed during the demolition process should be stabilized the same day as exposure from excavation or prior to the next expected rain event.

See Sections J-Attachment # 4 for images of historical construction drawings. If readability is an issue the contractor may request to see the physical drawings located in building 182 by contacting James Johnson (202-812-2953).

See Section J-Attachment #2-B217 Executive Summary Asbestos Inspection. The contractor will be responsible for abatement of all hazardous materials identified in the previous inspection as well as any additional hazardous materials identified during the contractor’s required testing as part of this contract.

The contractor shall take additional care to not damage utilities located within the demolition site area that are not building specific and that are to remain in use throughout the project and in the future. If the contractor is unsure which utilities are to remain, they should submit an RFI to allow NAVFAC to clarify.

Figure 6 ‐ Building 217 (BOQ)

Figure 7 ‐ Building 217 (BOQ) Map View

Building 312 (RDT&E_Storage Lab):

CURRENT CONDITIONS:

Building 312 – RDT&E storage lab (adjacent to Building 441) - an existing one- story building, on a concrete pier foundation approximately 3’ above grade. The building dimensions are 29’x21’x13’H with a total internal area of approximately 814 square feet. The building currently has a partially collapsed roof. The building was built in 1943.

1. The substructure consists of reinforced concrete pier foundation with a crawl space.

Superstructure General:

1. The exterior walls primarily consist of 6” wood framed dimension lumber, with 1”x10” lumber wood walls.

2. The roof framing consists of wood trusses.

Interior General:

1. The interior construction and finishes at Building 312 reflects exposed wood framed and metal wire cage screening partitions. Floor finishes include exposed wood.

1. Mechanical equipment includes but is not limited to: Exhaust Fan, unit heater and wiring.

1. Electrical systems and equipment includes but is not limited to: lighting, receptacles, See Section J-Attachment # 6 for images of historical construction drawings. If readability is an issue the contractor may request to see the physical drawings located in building 182 by contacting James Johnson (202-812-2953).

Figure 8 ‐ Building 312 (RDT&E Storage Lab)

Figure 9 ‐ Building 312 (RDT&E Storage Lab)

Figure 10 ‐ Building 312 (RDT&E Storage Lab) Map View

Building 360 (Screen Tower):

Building 360 – Screen Tower (Located on Main Range) – is an existing 120’ tall exposed metal framed tower. The footprint of the structure is approximately 20’x20’ (400 square feet). This structure was built in 1936.

1. The substructure consists of reinforced concrete footers that are 3’ x 3’ wide with an unknown depth.

Superstructure General:

1. The metal tower structure is primarily built out of angle iron. The corner supports are C channel welded to angle to make an almost fully enclosed 8”x5” box tube with 3/8” wall. The primary horizontal members are 4”x4” angle iron approximately 3/8” thick. The diagonal support members are 3”x3” angle iron approximately 3/8” thick. These structures shall be demolished in a systematic manner, which will be up to the contractor to submit their plan for NAVFAC review and approval.

Electrical systems and equipment includes but is not limited to: lighting, disconnects, electrical wiring and conduit. This SOW also includes the demolition of the buried electrical wire and conduit that terminates at an above ground junction stub up, but all digging must be done by E40 personnel due to the location being on the Main Range.

Figure 11 ‐ Building 360 (Screen Tower)

Figure 12 ‐Building 360 (Screen Tower) Map View

Building 1312 (MWD Kennel (working animal support building)):

Building 1312 – MWD kennel (working animal support building) - an existing one story structure that is approximately 24’x6’ with 8’ high metal fence enclosed runs all on an approximate 30’x24’x8” concrete slab. The structure has a 8” concrete turn down foundation. This building was built in 1969.

1. The substructure consists of reinforced concrete, 30’x24’x8” turn-down footings with a slab on grade.

Superstructure General:

1. These structures consist of concrete block walls, chain link fencing, metal doors and a flat EPDM roof that is covered with vegetation.

2. These structures shall be demolished in a systematic manner, from the top of the structure to the ground.

Figure 13‐ Building 1312 (MWD kennel (working animal support building)

1. Floor finishes include an exposed concrete slab.

Figure 14‐ Building 1312 (MWD kennel (working animal support building) interior

1. None

1. Electrical systems and equipment includes but is not limited to:

Figure 15‐ Building 1312 (MWD kennel (working animal support building) electrical

1. The existing free standing frost free yard hydrant and bollards shall be demolished as a part of this SOW. The contractor shall remove underground water line back to the valve located outside of the fence of the range boat storage lot. Excavated material shall be re-compacted in 12” lifts during backfill to a 90 % compaction of ASTM D-1550.

2. The existing electrical service shall be demolished as part of this SOW. The contractor shall remove underground electrical line and conduit from the building to Autumn Lane.

Figure 16‐ Building 1312 (MWD kennel (working animal support building)

Figure 17‐ Building 1312 (MWD kennel (working animal support building) free standing hydrant.

Figure 18‐ Building 1312 (MWD kennel (working animal support building) Map View

Building 2014 (Press Box/Score Board Building):

Building 2014 – Press Box/Score Board Building (adjacent to Fire Department Baseball field) – an existing two-story building, on a slab on grade with a single room on each story. The building is 16’x12’x20’H and footprint of approximately 192 square feet. The exterior stairs to the second floor is currently missing. This building was built in 1993.

1. The substructure consists of reinforced concrete spread footings and concrete masonry foundation walls with a 6” slab on grade.

Superstructure General:

1. The exterior walls primarily consist of 8” concrete masonry units covered in stucco.

2. The roof is flat and the framing consists of 2x6 wood ceiling rafters

1. The interior construction and finishes reflect concrete masonry unit partitions. Floor finished includes exposed concrete.

1. Mechanical systems and equipment include but is not limited to: Exhaust Fans, unit heater and wiring.

Electrical General:

1. Electrical systems and equipment includes but is not limited to: lighting, receptacles, disconnects, electrical wiring and conduit.

1. Provisions to block off parking spots in lot adjacent to press box.

2. Contacting police to move trucks that are parked in lot to ensure no damage to vehicles and room for demo work.

Figure 19 ‐ Building 2014 – Press Box/Score Board Building

Figure 20 ‐ Building 2014 – Press Box/Score Board Building Map View

REQUEST DEMO PACKAGE eProjects #: 1799880

SECTION 02 41 00 Page 1

SECTION 02 41 00

DEMOLITION

05/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

AHRI Guideline K (2009) Guideline for Containers for

Recovered Non-Flammable Fluorocarbon Refrigerants

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.6 (2006) Safety & Health Program

Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

40 CFR 82 Protection of Stratospheric Ozone

1.2 PROJECT DESCRIPTION

1.2.1 Definitions

1.2.1.1 Demolition

Demolition is the process of wrecking or taking out any load-supporting structural member of a facility together with any related handling and disposal operations.

1.2.1.2 Demolition Plan

Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.

1.2.2 Demolition/Deconstruction Plan

Prepare a Demolition Plan and submit proposed demolition, and removal

SECTION 02 41 00 Page 2 procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations.

Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use. Coordinate with Waste Management Plan in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Plan shall be approved by Contracting Officer prior to work beginning.

1.2.3 General Requirements

Do not begin demolition until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes the value derived from the salvage and recycling of materials. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.

1.3 ITEMS TO REMAIN IN PLACE

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.

Coordinate the work of this section with all other work indicated.

Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.

1.3.2 Trees

Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.

SECTION 02 41 00 Page 3

1.3.3 Utility Service

Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor.

1.3.4 Facilities

Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.

1.4 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan; G

Existing Conditions

SD-07 Certificates

Notification; G

SD-11 Closeout Submittals

Receipts

1.6 QUALITY ASSURANCE

Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61, Subpart M.

Notify the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M.Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6. Comply with the Environmental

SECTION 02 41 00 Page 4

Protection Agency requirements specified. Use of explosives will not be permitted.

1.6.1 Dust and Debris Control

Prevent the spread of dust and debris and avoid the creation of a nuisance in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.

1.7 PROTECTION

1.7.1 Traffic Control Signs

a. Where safety is endangered in the area of removal work, use traffic barricades with flashing lights. Notify the Contracting Officer prior to beginning such work.

1.7.2 Protection of Personnel

Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.

1.8 FOREIGN OBJECT DAMAGE (FOD)

Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations. If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris.