- FACILITIES OPERATIONS AND MAINTENANCE (O&M) SERVICES Federal contract opportunity
- Solicitation number
- DRAFT19AQMM24R0191
About this file
This document is the Section J Attachment 14 Deliverables Matrix for a federal contract opportunity for Facilities Operations and Maintenance (O&M) services.
The Deliverables Matrix outlines the required reports, plans, and other deliverables the contractor must provide under the contract, including monthly status updates, quality control reports, safety and environmental plans, transition plans, equipment inventories, and various other documents. The matrix specifies the due dates, frequency, and points of contact for each deliverable.
The related federal contract opportunity is for O&M services covering over 40 Department of State facilities across the United States. The Office of Facilities Management Services within the Department of State's Bureau of Administration is seeking contractors to provide these services, which include safety, facilities management, environmental compliance, and other functions. The pre-solicitation notice provides a draft Request for Proposal for industry review and feedback.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| J-23.pdf | ||
| J-20.pdf | ||
| J-16.pdf | ||
| J-5.pdf | ||
| J-2.pdf | ||
| J-12.pdf | ||
| J-10.pdf | ||
| J-8.pdf | ||
| J-18.pdf | ||
| J-17.pdf | ||
| J-1.pdf | ||
| J-15.pdf | ||
| J-7.pdf | ||
| DRAFT_19AQMM24R0191.pdf | ||
| J-21.pdf | ||
| J-11.xlsx | XLSX spreadsheet | |
| J-3.pdf | ||
| J-6.pdf | ||
| J-19.pdf | ||
| 00 CFS Performance Work Statement DRAFT.pdf | ||
| J-22.pdf | ||
| J-4.pdf | ||
| J-9.pdf | ||
| J-13.pdf |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section J Attachment 14 Deliverables Matrix
Section J – Deliverables Matrix - Attachment 14
Contract Section
Name Include in bid
Due Frequency Point of Contact(s)
C.3 PgMO Monthly report
Monthly contract status update to include efficiency analysis
Monthly • Contracting Officer
• Contracting Officer’s
Representative
• FMS Leadership
• Facility Manager
C.3.1 PgMO QA/QC Report
QASP, KPI/AQL report Monthly • Contracting Officer’s Representative
• FMS Leadership
• Facility Manager
C.3.5 PgMO monthly Health and Safety Report Attachment 16
Contractor shall provide a monthly report including all actions taken, in progress or planned, involving health and safety
Monthly • Contracting Officer’s Representative
• Building Manager
• Safety branch
C.3.6 and C.4 PgMO monthly Environmental Stewardship Report
Contractor shall provide a monthly report including all actions taken, in progress or planned, involving environmental stewardship
Monthly • Contracting Officer’s Representative
• Building Manager
• Safety branch
C.4.2.1 Attachment 09 Program Management Plan Template
Program Management Plan (PMP)
X Contractor shall provide a DRAFT to the CO, ten (10) calendar days after Contract award for review and shall submit a final plan sixty (60) calendar days after Contract Award for USG approval.
Annual review
• Contracting Officer
• Contracting Officer’s
Representative
C.4.2.2 Attachment 10 CFS Plan Template
Operations and Maintenance (CFS) Plan
X A DRAFT CFS plan shall be delivered to the CO, COR and Building Manager for review thirty (30) calendar days after task order award for approval forty-five (45) calendar days after task order award.
Reviewed and audited monthly
• Contracting Officer
• Contracting Officer’s
Representative
C.4.1.1 Operations & Maintenance Service
Defined at the task order level.
DRAFT due thirty (30) days after task order award for approval.
Final due forty-five (45) days after task order award.
Annual review and within thirty (30) days of task order modification or notable change.
• Contracting Officer
• Contracting Officer’s
Representative
• Building Manager
DRAFT
C.4.2.3
CFS Plan in
ERPS
Details of the CFS plan shall be incorporated in the ERPS system within 60 days of CO approval of the final plan.
• Contracting Officer
• Contracting Officer’s
Representative
C.4.2.4
Quality Control Plan (QCP)
X Contractor shall provide a DRAFT to the CO, ten (10) calendar days after task order award and the final QCP shall be submitted for approval thirty (30) calendar days after task order award.
30 calendar days after task order award
Annual review
• Contracting Officer
• Contracting Officer’s
C.4.2.5
Cost Control Plan (CCP)
X Thirty (30) calendar days after task order award.
Annual review • Contracting Officer
• Contracting Officer’s
Representative C.4.2.6 Attachment 06 List of Codes and Regulations
Occupational Safety and Health Plan
DRAFT Safety Plan submitted to the CO and the COR thirty (30) calendar days after task order award for review and acceptance. The Contractor shall submit the final plan ninety (90) calendar days after the task order award.
Random system audits
Annual review
• Contracting Officer
• Contracting Officer’s
Representative
• Safety branch
C.4.5 Initial Inspection and Deficiency List
Thirty (30) calendar days after Task Order Start
Annually • Contracting Officer
• Contracting Officer’s
Representative
• Building Manager
C.4.6.1 Transition Plan X The Contractor shall submit a Phased Transition Plan to the CO for approval within ten (10) calendar days after Task Order Award.
Review 60 days after Task Order award.
• Contracting Officer
C.4.6.1 Transition Plan X Initial transition shall consist of the first set of key personnel arriving on site within forty-five
(45) calendar days after Task Order Award. Second set no later than sixty (60) calendar days after Task Order Award.
Review 60 days after Task Order award.
• Contracting Officer
C.4.6.3 Demobilization Plan
X Within 45 days of termination of CFS Task Order
• Contracting Officer
• Contracting Officer’s
Representative C.4.8 Call Center
Management Site specific playbook to be created in conjunction with USGOV within 90 days of task order award.
Review annually and within thirty
(30) days of any noted change.
• Contracting Officer
• Contracting Officer’s
Representative
C.4.9.2 Equipment Inventory
Contractor shall provide an initial update and verification of the equipment inventory upon thirty (30) calendar days after task order award
Annually, the contractor must validate inventory.
Monthly reports of all equipment added into
ERPS
• Contracting Officer
• Contracting Officer’s
C.4.10.2
Inventory of Hazardous Material
The Contractor shall submit this plan to the CO and COR thirty
(30) days after task order award.
Monthly reports
• Contracting Officer
• Contracting Officer’s
Representative
C.4.12.5 Minimum Lead Time for Vetting
Contractor shall ensure contractor personnel submit MRPT packages eighty (80) days prior to expected performance at the site
All changes to the staffing plan must be approved by
COR
C.5.3.1 Water Sampling and Flushing Plan
(WSFP)
X Draft plan must be submitted for review and approval thirty
(30) calendar days after task order award. The final plan must be submitted within sixty
(60) calendar days after task order award. Must comply with GSA Order PBS 1000.7A
Updated plan must be provided annually or within thirty
(30) days of any noted change.
• Contracting Officer
• Contracting Officer’s
Representative
• Building Manager
• Safety branch
C.5.4.1 Backup Retention
Contractor shall create two sets of backup data for each BAS at the facility on a biannual basis.
Bi-annually • Contracting Officer
C.5.4.2 Password Retention.
Contractor shall create a listing of the BAS/PMS usernames and passwords that exist within the BAS Operator Workstation and/or Server that are used to access the BAS/PMS.
Review bi-annually
• Contracting Officer
• Contracting Officer’s
C.5.6.1 Condition Monitoring:
Vibration analysis inspection
Contractor shall conduct the vibration analysis inspection on an annual basis to begin ninety
(90) days after task order award and to complete within thirty
(30) days
• Contracting Officer
• Contracting Officer’s
C.5.7.1
CFS Plan for Conveyance Systems
Attachment 20
X A DRAFT plan shall be delivered for review ten (10) calendar days after Task Order Award for approval forty-five (45) calendar days after Task Order Award.
Review 45 days after contract award
Quarterly audits and updates
• Contracting Officer
• Contracting Officer’s
C.5.9 Cleaning & Janitorial Service
X Due thirty (30) days after task order award. Complete cleaning schedule based on the facility. In addition, QC/QA program for spot checking the janitorial program.
• Contracting Officer
• Contracting Officer’s
C.5.10
Spare Parts and Expendables Inventory Report
Forty-five (45) calendar days after Task Order award.
Monthly report • Contracting Officer’s Representative
• Building Manager
C.5.11.6 Fuel Inventory report.
Fuel inventory, including the estimated days or hours the supply will last at current consumption rates.
Weekly Contracting Officer’s Representative
Building Manager
C.5.13
Landscape Management Plan
X Thirty (30) days after contract award
• Contracting Officer
• Contracting Officer’s
C.5.14
Pest Management Plan
X Forty-five (45) calendar days after the Task Order Award
• Contracting Officer
• Contracting Officer’s
C.5.15
Attachment 17
Fire Emergency Plan (FEP)
The initial FEP shall be submitted for review and approval within thirty (30) calendar days after the task order award for review and Contractor shall submit a final plan sixty (60) calendar days after the task order award
Updated plan must be provided annually and within thirty
(30) days of any noted change.
• Contracting Officer’s Representative
• Building Manager
• Safety branch
C.5.16 Snow and Ice Removal Plan
X Detailed snow and ice removal plan due forty-five (45) days after task order award.
• Contracting Officer
• Contracting Officer’s
Representative
• Building Manager
C.5.20.2 As Built drawings.
Semi-annual
Semi-annual • Contracting Officer
Representative
C.5.21.2 Staffing Plan X Initial Staffing Plan shall be submitted for review and approval thirty (30) calendar days after task order award.
The Final Staffing Plan shall be submitted sixty (60) calendar days after task order award
COR must approve change in key personal
• Contracting Officer
• Contracting Officer’s
C.5.21.5 Minimum Staffing
X Contractor personal must be manned at 100% within 90 days from contract award
Review in 90 days from task order award
• Contracting Officer
• Contracting Officer’s
C.6.2 Reporting for Adhesives, Sealants and Primers
Contractor shall report monthly all quantities of adhesives, sealants, adhesive primers, and sealant primers used on a site-by-site basis
Monthly • Contracting Officer’s Representative
• Building Manager
• Safety branch
C.5.21 Health and Safety Training for Employees
X Thirty (30) calendar days after Task Order Start.
Safety Training is reported Monthly
• Contracting Officer’s Representative
• Building Manager
• Safety branch
C.6.9 Workplace Safety and Health Program
Initial safety and health program for review and approval within forty-five (45) calendar days after the task order award for review and shall submit a final plan sixty (60) calendar days after the task order award
Reviewed Annually
• Contracting Officer
• Contracting Officer’s
Representative
C.6.10
Attachment 16
Waste, Recycling and Hazardous Waste Removal Management Plan
X DRAFT due thirty (30) days after task order award. Plan to be finalized in conjunction but Building Manager for site.
Updated plan must be provided annually and within thirty
(30) days of any noted change.
• Contracting Officer
• Contracting Officer’s
Representative
• Building Manager
• Safety branch
C.16.2 Water Sampling Reports.
Contractor shall provide a monthly operations report to the COR by the fifth (5th) business day of the following month
Monthly reports
• Contracting Officer
• Contracting Officer’s
Representative
• Building Manager
• Safety branch
Attachment 16 Site Specific waste reports
Some sites may require solid waste weight reporting.
Monthly reports
• Contracting Officer’s Representative
• Building Manager
• Safety branch
Attachment 16 section 10
Site Specific composting reports
Monthly waste, composting and recycling data will be submitted to the COR and Safety branch.
Monthly reports
• Contracting Officer’s Representative
Environmental reports
The data reporting will include precise measurements of actual weight and the classification of various recycling streams
Attachment 16 section 10 Environmental reports
Site Specific recycling reports
Monthly waste, composting and recycling data will be submitted to the COR and Safety branch.
The data reporting will include precise measurements of actual weight and the classification of various recycling streams
Monthly reports
• Contracting Officer’s Representative
• Building Manager
• Safety branch
C.6.13
Attachment 16
Green Cleaning Plan
Initial plan shall be submitted for review and approval within thirty
(30) calendar days after the task order award for review and Contractor shall submit a final plan sixty (60) calendar days after the task order award
Plan to be reviewed quarterly for the initial 3 quarters after task order award. Then reviewed annually and within thirty
(30) days of any noted change.
• Building Manager
• Safety branch
C.10.1 and C.16.4
Inventory of on-site supplies, materials, tools, and equipment
Within forty-five (45) calendar days after the task order award
Annually • Contracting Officer’s Representative
• Building Manager
C.14.3 Monthly QC Report
Thirty (30) days after the start date of the task order with the first monthly payment request
Monthly • Contracting Officer’s Representative
• Building Manager C.16.2 Monthly
Operations Report
Contractor shall provide a monthly operations report to the COR by the fifth (5th) business day of the following month
• Contracting Officer’s Representative
• Building Manager
C.16.3 Tenant Satisfaction Survey Report
Contractor shall provide a monthly operations report to the COR by the fifth (5th) business day of the following month
Monthly • Contracting Officer’s Representative
• Building Manager
C.16.4 Annual Program Mgmt Meeting Report
Contractor shall provide annual reports on the current status of any contracts and warranties associated with the Contractor’s performance under the task
Annually • Contracting Officer
• Contracting Officer’s
Representative order. To include a list of equipment/system warranties that will expire in the coming year.
Attachment 16 OSHA Form 300 Log of Work-Related Injuries
End of each quarter
• Contracting Officer’s Representative
• Building Manager
• Safety branch
Attachment 16 OSHA Form 300, Log of Work-Related Injuries, and Illnesses
Annually • Contracting Officer’s Representative
• Building Manager
• Safety branch
Attachment 16 Green Purchasing report
Monthly • Contracting Officer’s Representative
• Building Manager
• Safety branch
Attachment 16 Energy Audit Annually • Contracting Officer’s Representative
• Building Manager
• Safety branch
Attachment 16 Energy and Water Quarterly Report
Monthly • Contracting Officer’s Representative
• Safety branch DRAFT