IWTP SCADA SOW v2.0.pdf

PDF 92 KB Posted

Attached to
Support for the Industrial Wastewater Treatment Plant
Solicitation number
FA820126R0015
Issued by

About this file

This is a Statement of Work (SOW) for the replacement of a Supervisory Control and Data Acquisition (SCADA) system at the Industrial Wastewater Treatment Plant (IWTP) located at Hill Air Force Base, Utah. The contractor must furnish all labor, materials, tools, equipment, testing, and transportation to deliver a complete, fully integrated, turnkey SCADA system designed, fabricated, programmed, tested, and warranted by a single supplier. The overall Period of Performance shall not exceed 180 calendar days from the Notice to Proceed and includes engineering, material procurement, delivery, physical installation, and final commissioning. Normal working hours are restricted to 0700–1700 hours, Monday through Friday, excluding Federal holidays, with overtime and weekend work requiring pre-coordination and approval from the Contracting Officer and the 75 CES Project Manager.

The system must comply with federal standards including the National Electrical Code, NEMA standards, IEEE standards, and applicable UFC directives. Critical cybersecurity compliance is required through Risk Management Framework (RMF) accreditation per DoDI 8500.01 and DoDI 8510.01, AFI 17-101, and the AFCEC Control Systems Cybersecurity Requirements Guide. The replacement system must integrate seamlessly with existing physical infrastructure while allowing long-term sustainment and troubleshooting by 75 CES personnel without vendor dependence. Hardware specifications include a Dell PowerEdge T340 central SCADA server with Windows Server 2019, a dedicated Operator Workstation running Windows 11, modular Programmable Controller (RTU/MPC) hardware with integrated digital touchscreens, and a Standby UPS providing minimum 20 minutes of backup power. The software platform must be unified, supporting 100,000 active I/O points and native communication over Modbus TCP, BACnet/IP, and OPC UA protocols. The contractor must implement a three-phase quality control inspection system, provide comprehensive Operation and Maintenance manuals with As-Built drawings in AutoCAD format, conduct minimum 3-day factory acceptance testing, provide seven business days of factory-certified on-site training, and supply a one-year comprehensive parts and labor warranty with 24-hour manufacturer telephone support and next-day replacement parts delivery capability.

View the file

Other files

File Type Posted
Solicitation Amendment FA820126R00150004 SF 30.pdf PDF
Solicitation Amendment FA820126R00150001 SF 30.pdf PDF
Solicitation Amendment FA820126R00150002 SF 30.pdf PDF
Solicitation Amendment - FA820126R00150004.pdf PDF
IWTP SCADA Quesitons Vendor Questions and Answers 11Aug2026 V1.0.pdf PDF
Solicitation Amendment FA820126R00150003 SF 30.pdf PDF
IWTP SCADA Instructions and Evaluation Factors_v5.pdf PDF
IWTP SCADA Quesitons Vendor Questions and Answers 11Aug2026.pdf PDF
Solicitation Amendment - FA820126R00150003.pdf PDF
IWTP SCADA SOW v2.2 UPDATED.pdf PDF
Solicitation Amendment FA820126R00150002 SF 30.pdf PDF
IWTP SCADA Instructions and Evaluation Factors_v4.pdf PDF
Solicitation Amendment - FA820126R00150002.pdf PDF
Solicitation Amendment - FA820126R00150001.pdf PDF
IWTP SCADA Quesitons Vendor Questions and Answers 27Jul26.pdf PDF
Solicitation Amendment FA820126R00150001 SF 30.pdf PDF
IWTP SCADA SOW v2.1.pdf PDF
IWTP SCADA Instructions and Evaluation Factors_v3.pdf PDF
IWTP SCADA 90percent Design 12-12-11.pdf PDF
RECORD DRAWINGS.pdf PDF
IWTP Phase II 20IO List(1) (3).pdf PDF
Rev - 0.pdf PDF
IWTP SCADA Instructions and Evaluation Factors_v2.pdf PDF
A003 IWTP CDRL v1.pdf PDF
A002 IWTP CDRL v1.pdf PDF
Solicitation - FA820126R0015.pdf PDF
Wage determinations from Sam.gov.pdf PDF
A005 IWTP CDRL v1.pdf PDF
A001 IWTP CDRL v1.pdf PDF
A006 IWTP CDRL v1.pdf PDF
IWTP SCADA Instructions and Evaluation Factors.pdf PDF
A004 IWTP CDRL v1.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW) FOR IWTP SCADA SYSTEM REPLACEMENT LOCATED AT

HILL AIR FORCE BASE

1.0 PROJECT DESCRIPTION AND SCOPE

1.1 General System Description

1.1.1 The Contractor shall furnish all labor, materials, tools, equipment, testing, and transportation necessary to deliver a complete, fully integrated, and turnkey Supervisory Control and Data Acquisition (SCADA) system.

1.1.2 The system shall be installed at the Industrial Wastewater Treatment Plant (IWTP) compound located at Hill Air Force Base (HAFB), Utah.

1.1.3 The complete system shall be designed, fabricated, programmed, tested, started up, and warranted by a single supplier to ensure a single source of responsibility and long-term support.

1.2 Detailed Scope of Work

1.2.1 The Contractor shall design, build, and install a replacement SCADA system to automate the monitoring and control of industrial waste treatment processes.

1.2.2 The Contractor shall ensure the replacement system integrates seamlessly with the existing physical infrastructure at the IWTP.

1.2.3 The system must comply with all current cybersecurity directives while allowing long-term sustainment and troubleshooting by 75 CES personnel without vendor dependence.

1.3 Period of Performance and Schedule

1.3.1 The overall Period of Performance (PoP) shall not exceed 180 calendar days from the date of the Notice to Proceed (NTP). This period shall include engineering, material procurement, delivery, physical installation, and final commissioning.

1.3.2 The Contractor's normal working hours shall be restricted to 0700 to 1700 hours, Monday through Friday, excluding Federal holidays.

1.3.3 Overtime and weekend work must be pre-coordinated and approved by the Contracting Officer (CO) and the 75 CES Project Manager (PM) to meet schedule constraints or facilitate required utility outages.

2.0 APPLICABLE CODES, STANDARDS, AND CYBERSECURITY

2.1 Federal, Military, and Industrial Standards

2.1.1 The Contractor shall ensure all design, installation, and materials comply with the National Electrical Code (NEC), National Electrical Manufacturers Association (NEMA) standards, and IEEE standards.

2.1.2 The system configuration and installation must comply with UFC 1-200-01 (General Building Requirements), UFC 3-401-01 (Mechanical Engineering), and UFC 3-430-07 (Water Supply and Wastewater).

2.1.3 All electrical and telecommunications systems shall be designed and installed in accordance with UFC 3-560-01 (Electrical Safety), UFC 3-580-01 (Telecommunications Infrastructure), and the 75th CS TAB K directive dated 1 April 2010.

2.2 Cybersecurity and Risk Management Framework (RMF) Compliance

2.2.1 The SCADA system hardware, software, and network components shall be engineered to achieve Risk Management Framework (RMF) accreditation in accordance with DoDI 8500.01 (Cybersecurity) and DoDI 8510.01 (RMF).

2.2.2 The Contractor shall ensure all configurations comply with AFI 17-101 (Risk Management Framework for Air Force Information Technology) and the AFCEC Control Systems Cybersecurity Requirements Guide (CS-CRG).

2.2.3 The system design must integrate security controls consistent with the Department of Defense (DoD) ICS/OT Cybersecurity Reference Architecture and NIST SP 800-82 (Guide to Industrial Control Systems Security).

2.3 Environmental and Safety Regulations

2.3.1 The Contractor shall comply with all Occupational Safety and Health Administration (OSHA) regulations as outlined in 29 CFR Part 1910 and 29 CFR Part 1926.

2.3.2 All environmental mitigation, waste handling, and emissions control shall comply with Environmental Protection Agency (EPA) regulations in 40 CFR and the State of Utah Administrative Codes.

3.0 GENERAL CONTRACTOR REQUIREMENTS

3.1 Project Management and Site Supervision

3.1.1 The Contractor shall provide a qualified, full-time Superintendent on-site to oversee all daily construction, safety, and quality control activities.

3.1.2 The Contractor shall assign a dedicated Project Manager to coordinate scheduling, submittals, and contract modifications with the 75 CES PM, Dennis Laughlin.

3.1.3 The Contractor shall implement a three-phase quality control inspection system covering the design phase, physical construction phase, and final closeout phase.

3.2 Site Logistics

3.2.1 The Government will designate an on-site parking area and a designated layout space for the Contractor's equipment and roll-off containers.

3.3 Protection of Government Property and Safety

3.3.1 The Contractor shall protect all existing government property and physical assets from damage during construction. Any damage caused directly or indirectly by the Contractor shall be repaired or replaced to original condition at no cost to the Government.

3.3.2 The Contractor shall maintain active dust control measures to protect sensitive electronic equipment and active processes operating inside the IWTP.

3.3.3 At the conclusion of each daily shift, the Contractor shall secure all tools, equipment, materials, and facility entry points to prevent unauthorized access.

3.4 Outage Coordination and Mishap Reporting

3.4.1 The Contractor shall submit written requests for utility outages to the 75 CES PM a minimum of 21 calendar days prior to the desired start date. Outages must be carefully coordinated with IWTP operations to minimize process disruptions.

3.4.2 In the event of an occupational accident or physical mishap, the Contractor shall immediately secure the scene, take action to prevent further injury or property damage, and notify the Contracting Officer (CO).

3.4.3 The Contractor shall cooperate fully with any subsequent military accident investigation authorities and preserve all physical evidence until formally released.

4.0 DEMOLITION AND HAZARDOUS MATERIALS

4.1 Hazardous Materials Surveys and Compliance

4.1.1 The Contractor shall post and maintain all government-furnished Asbestos Containing Material (ACM) and Lead-Based Paint (LBP) inspection reports in a prominent, weatherproof location on-site.

4.1.2 The Contractor shall utilize only Utah-licensed and certified asbestos and lead abatement subcontractors. Pre-approved specialty contractors include Environmental Abatement Inc. and Eagle Environmental.

4.2 Legacy SCADA System Demolition

4.2.1 The Contractor shall perform the safe, complete isolation and physical removal of legacy PLC hardware, obsolete wiring, unsecured communication adapters, and redundant field programming ports.

4.2.2 Demolition activities must be carefully sequenced to prevent any unplanned interruptions to the active wastewater treatment processes.

4.2.3 All demolished electronics, cabling, and cabinet components shall be sorted and disposed of in accordance with HAFB environmental waste policies.

4.3 Hazardous Waste Abatement Protocols

4.3.1 All asbestos abatement work shall comply with 29 CFR 1926.1101, 40 CFR Part 763 (Subpart G), 40 CFR Part 61 (Subpart M), and Utah Administrative Code R3017-801.

4.3.2 All lead-based paint disturbance, cutting, and containment shall comply with 29 CFR 1910.1025, 29 CFR 1926.62, 29 CFR 1910.134, and Utah Administrative Code R307-840.

5.0 TECHNICAL HARDWARE SPECIFICATIONS

5.1 Central SCADA Server Configuration

5.1.1 The Contractor shall install a central SCADA server utilizing a Dell PowerEdge T340 platform running the Windows Server 2019 Operating System.

5.1.2 The server hardware shall feature an Intel Xeon 4-Core processor and a minimum of 6 GB of system RAM.

5.1.3 The storage array shall consist of a dedicated hardware RAID controller operating in a Physical RAID 1 configuration with dual 1TB Solid State Drives (SSDs).

5.1.4 The server chassis must include dual hot-plug redundant power supplies, a dual-port 1Gb on-board network interface card (NIC), an optical mouse, and a standard QWERTY keyboard.

5.2 Operator Workstation (OWS) and Power Protection

5.2.1 The Contractor shall install a dedicated Operator Workstation (OWS) running Windows 11 to serve as the primary human-machine interface (HMI).

5.2.2 The OWS shall be equipped with a high-resolution LCD display and a local USB soundbar or external speakers for audible alarm annunciation.

5.2.3 The Contractor shall supply a Standby Uninterruptible Power Supply (UPS) featuring integrated power line filtering and transient surge protection.

5.2.4 The UPS must be engineered to provide a minimum of 20 minutes of continuous backup power to the central server, OWS, network switches, modems, and communication adapters.

5.3 Programmable Controller (RTU/MPC) Hardware

5.3.1 The replacement field controllers shall feature a modular, industrial design suited for wastewater treatment environments.

5.3.2 Each controller shall feature a fully interactive, integrated digital touchscreen on the enclosure face to allow IP configuration, troubleshooting, and diagnostic monitoring without the use of a laptop computer.

5.3.3 The controllers shall feature a minimum of three active communication ports, including two serial RS485 ports and one 10/100 Fast Ethernet port.

5.3.4 All controller I/O modules must be hot-swappable to facilitate field replacement without requiring system wiring removal.

5.4 Controller Input and Output Board Limits

5.4.1 Digital Output Modules: 120VAC cards must feature 16 channels with a 90– 130 VAC rating and 125 mA per channel maximum. 24VAC cards must feature 8 channels with 300 mA per channel maximum. 12VDC cards must feature 8 channels. Relay output cards must feature 5–8 channels supporting Form A and C configurations rated up to 240 VAC/125 VDC.

5.4.2 Analog Output Modules: 0–20mA modules must feature 4–8 channels with 10-bit resolution and a maximum load impedance of 600 Ohms. 0–10VDC modules must feature 8 channels with 10-bit resolution.

5.4.3 Analog Input Modules: 4–20mA modules must feature 2–16 channels supporting self-powered and loop-powered configurations, 16-bit resolution, and ±20 uA accuracy. 0–10VDC modules must feature 16 channels with 16-bit resolution. 0–2k Ohm resistive modules must feature 16 channels with 16-bit resolution.

5.4.4 Digital Input Modules: 120VAC cards must feature 5–16 channels with a 130 VAC maximum input rating. Dry contact relay inputs must feature 4–16 channels with an open-contact voltage rating of 10–24 VDC.

6.0 SOFTWARE, PROGRAMMING, AND DATABASE ARCHITECTURE

6.1 Unified Software Platform

6.1.1 The SCADA system shall operate on a single, unified software platform that consolidates programming, HMI graphics, alarm management, historical data trending, and system diagnostics into one environment.

6.1.2 The software platform must be fully licensed to accommodate a minimum of 100,000 active I/O points, including physical digital/analog channels and calculated control variables.

6.1.3 The platform must natively support simultaneous communication over Modbus TCP, BACnet/IP, and OPC UA protocols to facilitate future system integration.

6.2 Security and Administrative Controls

6.2.1 The software shall enforce role-based access control, offering distinct permissions for Engineering, Supervisory, and Operator levels.

6.2.2 The system shall utilize multi-factor authentication (MFA) via a secure authenticator application to validate user login.

6.2.3 User accounts shall be temporarily locked out after 3 consecutive invalid login attempts, and accounts must be automatically disabled after a pre-defined period of operational inactivity.

6.3 HMI Graphics and Alarm Management

6.3.1 The Contractor shall develop high-performance HMI graphic displays conforming to HAFB P&ID visualization standards.

6.3.2 The HMI graphics shall utilize consistent color-coding to denote system alarm states, restricted to: High Alarm (Red), Low Alarm (Blue), Failed Alarm (Yellow), and Out of Service/Manual Mode (Green).

6.3.3 The alarm subsystem must support configurable alarm routing to the base EMCS via a remote, monitor-only network connection.

6.3.4 The software shall maintain four distinct alarm views, including an Alarm Window for acknowledgment, a Recent Alarms view, an Active Alarms view, and a searchable Alarm History database.

7.0 SUBMITTALS AND DELIVERABLES

7.1 Pre-Installation Submittal Requirements

7.1.1 Product Data: The Contractor shall submit manufacturer data sheets for all instrumentation, controllers, network devices, and physical power supplies prior to purchasing.

7.1.2 Shop Drawings: The Contractor shall submit complete wiring diagrams, panel layout designs, and field connection details for approval.

7.1.3 HMI mockups: The Contractor shall submit representative mockups of the HMI menus, process graphic pages, and historical report logs for 75 CES PM review.

7.2 Project Deliverables and Documentation

7.2.1 The Contractor shall deliver a fully functional, programmed, and field-verified SCADA system that executes all specified automatic control loops.

7.2.2 The Contractor shall supply a complete set of As-Built drawings in AutoCAD format covering all architectural, mechanical, electrical, and control system modifications.

7.2.3 The Contractor shall deliver comprehensive Operation and Maintenance (O&M) manuals, including troubleshooting guides, calibration protocols, and software license keys on secure USB media.

8.0 TESTING, COMMISSIONING, TRAINING, AND WARRANTY

8.1 Factory Acceptance Testing

8.1.1 All central server, OWS, and replacement RTU panel assemblies must undergo a comprehensive, continuous factory test for a minimum period of 3 days prior to shipping to HAFB.

8.1.2 The Contractor shall verify correct I/O routing and firmware performance during the factory acceptance testing phase.

8.2 Commissioning and Start-Up

8.2.1 The Contractor shall utilize factory-certified personnel to perform on-site start-up, loop checks, and control sequence validation.

8.2.2 The Contractor shall submit a detailed, written process switchover plan to the 75 CES PM at least two weeks prior to starting active on-site installation work.

8.3 Training Requirements

8.3.1 The manufacturer shall provide factory-certified instructors to conduct a minimum of seven business days of on-site operator and maintenance training.

8.3.2 The initial training must cover HMI navigation, alarm management, historical trending, basic troubleshooting, controller replacement, and secure administrative practices.

8.3.3 The Contractor shall provide a three-month follow-up training session consisting of two business days on-site to review system performance, graphic modifications, and control sequence editing.

8.4 Warranty and Support Program

8.4.1 The Contractor shall provide a comprehensive one-year parts and labor warranty on all installed hardware, software, and cabling. The warranty period shall commence on the Beneficial Occupancy Date (BOD).

8.4.2 The manufacturer must provide 24-hour telephone support and diagnostic assistance to Hill AFB personnel for the operational life of the installed SCADA system.

8.4.3 The manufacturer shall maintain a local inventory of replacement parts to support next-day delivery of critical controller cards and network components during the warranty period.

File details come from the government source that posted it. Updated .