This document contains the Special Provisions for the S Ivy Street Pedestrian Intersection Improvements project in Clackamas County, Oregon. The project consists of grading, paving, drainage, roadside development, signing, pavement markings, and signals work along S Ivy Street and related side streets in Canby, Oregon. The contract period is scheduled for completion by October 31, 2025, except for seeding establishment.
The contract documents include the Oregon Standard Specifications for Construction and Standard Drawings as well as project-specific plans and exhibits. The contract requires the contractor to perform various tasks such as utility coordination, traffic control, erosion and sediment control, and workplace harassment prevention. Payment terms include progress payments with 5% retainage, an asphalt cement price adjustment clause, and liquidated damages for lane closures. The project is funded by Clackamas County and the City of Canby, with no specific set-asides mentioned.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
FOR HIGHWAY CONSTRUCTION
DEPARTMENT OF TRANSPORTATION
AND DEVELOPMENT
CLACKAMAS COUNTY, OREGON
S IVY STREET PEDESTRIAN
INTERSECTION IMPROVEMENTS
CONSTRUCTION
GRADING, PAVING, DRAINAGE, ROADSIDE DEVELOPMENT,
SIGNING, PAVEMENT MARKINGS, AND SIGNALS
JANUARY 2024
S Ivy Street Pedestrian Intersection Improvements, Canby, Oregon
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 1
Contents
SECTION 00110 – ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND
DEFINITIONS
SECTION 00120 – BIDDING REQUIREMENTS AND PROCEDURES
SECTION 00130 – AWARD AND EXECUTION OF CONTRACT
SECTION 00140 – SCOPE OF WORK
SECTION 00150 – CONTROL OF WORK
SECTION 00160 – SOURCE OF MATERIALS
SECTION 00165 – QUALITY OF MATERIALS
SECTION 00170 – LEGAL RELATIONS AND RESPONSIBILITIES
SECTION 00180 – PROSECUTION AND PROGRESS
SECTION 00190 – MEASUREMENT OF PAY QUANTITIES
SECTION 00195 – PAYMENT
SECTION 00196 – PAYMENT FOR EXTRA WORK
SECTION 00197 – PAYMENT FOR FORCE ACCOUNT WORK
SECTION 00199 – DISAGREEMENTS, PROTESTS AND CLAIMS
SECTION 00210 - MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC
CONTROL
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING
SECTION 00280 - EROSION AND SEDIMENT CONTROL
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00305 - CONSTRUCTION SURVEY WORK
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
SECTION 00320 - CLEARING AND GRUBBING
SECTION 00330 - EARTHWORK
SECTION 00331 - SUBGRADE STABILIZATION
SECTION 00332 - VAULT MODIFICATIONS
SECTION 00350 - GEOSYNTHETIC INSTALLATION
SECTION 00405 - TRENCH EXCAVATION, BEDDING, AND BACKFILL
SECTION 00415 - VIDEO PIPE INSPECTION
SECTION 00440 - COMMERCIAL GRADE CONCRETE
SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION
PIPE
SECTION 00470 - MANHOLES, CATCH BASINS, AND INLETS
SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
SECTION 00640 - AGGREGATE BASE AND SHOULDERS
SECTION 00744 - ASPHALT CONCRETE PAVEMENT
SECTION 00749 - MISCELLANEOUS ASPHALT CONCRETE STRUCTURES
SECTION 00759 - MISCELLANEOUS PORTLAND CEMENT CONCRETE
STRUCTURES
SECTION 00850 - COMMON PROVISIONS FOR PAVEMENT MARKINGS
SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 2
SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND
BARS
SECTION 00869 - CURB AND NON-TRAVERSABLE MEDIAN MARKINGS
SECTION 00902 - CROSSWALK CLOSURE SUPPORTS
SECTION 00905 - REMOVAL AND REINSTALLATION OF EXISTING SIGNS
SECTION 00930 - METAL SIGN SUPPORTS
SECTION 00940 - SIGNS
SECTION 00960 - COMMON PROVISIONS FOR ELECTRICAL SYSTEMS
SECTION 00962 - METAL ILLUMINATION AND TRAFFIC SIGNAL SUPPORTS
SECTION 00963 - SIGNAL SUPPORT DRILLED SHAFTS
SECTION 00990 - TRAFFIC SIGNALS
SECTION 01030 - SEEDING
SECTION 01070 - MAILBOX SUPPORTS
SECTION 02001 - CONCRETE
SECTION 02690 - PCC AGGREGATES
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 3
CLACKAMAS COUNTY DEPARTMENT OF TRANSPORTATION & DEVELOPMENT
SPECIAL PROVISIONS
FOR
Grading, Paving, Drainage, Roadside Development, Signing, Pavement Markings, & Signals
S Ivy Street Pedestrian Intersection Improvements S Ivy Street
Clackamas County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for S Ivy Street Pedestrian Intersection Improvements. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 00110, 00120, 00130, 00140, 00150, 00160, 00165, 00170, 00180, 00190, 00195, 00196, 00197, 00199, 00210, 00220, 00221, 00222, 00223, 00224, 00225, 00228, 00280, 00290, 00305, 00310, 00320, 00330, 00331, 00332, 00350, 00405, 00415, 00440, 00445, 00470, 00490, 00620, 00640, 00744, 00749, 00759, 00850, 00865, 00867, 00869, 00902, 00905, 00930, 00940, 00960, 00962, 00963, 00990, 01030, 01070, 02001, 02690
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
SECTION 00110 – ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND
DEFINITIONS
Comply with Section 00110 of the Standard Specifications supplemented and/or modified as follows:
00110.05(d) References to Laws, Acts, Regulations, Rules, Ordinances, Statutes, Orders, and Permits
Add the following to the first bullet (Statutes and Rules):
• Clackamas County’s Local Contract Review Board (LCRB) Rules are accessible online on the County’s website https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 4
00110.10 Abbreviations
Add the following:
CCDA - Clackamas County Development Agency
DTD - Clackamas County Department of Transportation and Development LCRB - Local Contract Review Board
UNS - Utility Notification System
00110.20 Definitions
Add or modify definitions as follows:
Agreement Form – The written agreement between the Owner and Contractor covering the work to be performed under the contract.
Amendment – A contract modification for Additional Work, Changed Work, Extra Work, Field Directives, or other changes. An Amendment changes the contract value, scope, and/or time. Amendments require formal approval by the Board of County Commissioners, pursuant to LCRB Rule Division C-049-160, prior to approval of such work.
Approved Equal - Materials or services proposed by the contractor and approved by the County as equal substitutes for those materials or services specified.
Award – Same as “Notice to Intent to Award”.
BCC – The Clackamas County Board of County Commissioners
Bid - A written offer by a bidder on forms furnished by the County to do work stated in the bid documents at the prices quoted. "Bid" is synonymous with "proposal" in these bid documents.
Bid Closing - The date and time for Bid Closing is the same as the date and time for Bid Opening.
Bid Documents- The following documents together comprise the Bid Documents:
• Invitation to Bid, Instructions to Bidders, Bid Form, Bid Proposal, Schedule of
Prices, Bid
• Bond, Performance Bond
• Certificate of Insurance, Prevailing Wage Rates
• The "Oregon Standard Specifications for Construction" by ODOT and APWA, 2021 edition.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 5
• Plans and drawings
• Other bid documents included or referenced in the bid documents
• Addenda, if any
• The Agreement Form and Special Provisions
Bonds - The bond or surety bond is a written document given by the surety and principal to the obligee to guarantee a specific obligation.
Change Order - A price agreement for Extra Work, Changed Work, field directives, or other changes. A Change Order does not change the contract value, scope, or time until it is incorporated into an Amendment. Change Orders will be agreed upon, in writing, by the County Project Manager and the Contractor’s designated representative.
Contract - The written contract agreement, including amendments, signed by the Contractor and Clackamas County, which describes the work to be done, the contract amount, and defines the relationships and obligations of the Contractor and the County.
Contract Documents - The Invitation to Bid, the Instructions to Bidders, the accepted Bid Proposal and Schedule of Prices, the Subcontractor List, the Bid Bond, the Performance and Payment Bond, the Certificate of Insurance, the Prevailing Wage Rates, the Standard Specifications and Special Provisions, Amendments, the Plans and Drawings, the Agreement, as well as all documents incorporated by reference therein, and any and all addenda prepared by or at the direction of and adopted by the County and further identified by the signature of the parties and all modifications thereof incorporated in the documents before their execution.
County - The term "County" shall mean Clackamas County, including the Board of County Commissioners, employees and agents of the County authorized to administer the conditions of these contract documents.
Department – A subdivision of the Agency.
Engineer - The County's Project Manager either acting directly or through an authorized representative(s). When referring to approval of extra work or other Contract modifications, “Engineer” also refers to the County’s legal authority according to the LCRB rules.
Invitation to Bid - The public announcement (Notice to Contractors) inviting bids for work to be performed or materials to be furnished.
Legal Holiday - As defined in ORS 279C.540.
Lump Sum - A method of payment providing for one all-inclusive cost for the work or for a particular portion of the work.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 6
Notice of Intent to Award - A written notice from the County notifying bidders that the County intends to award to the responsible bidder submitting lowest responsive bid.
ODOT Procurement Office – Clackamas County Purchasing Department.
Owner – Synonymous with Agency.
Plan Holder’s List – A list of contractor’s names, contact names, phone and fax numbers that the County’s Purchasing Department creates during bidding of the Project.
Project Manager – The Owner’s representative who directly supervises the engineering and administration of the contract.
Shop Drawings – Synonymous with Working Drawings.
Solicitation Document – Synonymous with Bid Documents.
Standard Drawings – The Agency-prepared detailed drawings for Work or methods of construction that normally do not change from project to project. The Standard Drawings include the ODOT Standard Drawings.
Standard Specifications - "Oregon Standard Specifications for Construction", current edition, published by the Oregon Department of Transportation and as amended by the Agency.
State - Where the term “State” or “State of Oregon” or “ODOT” appears in the contract documents it shall mean “Clackamas County”, “State of Oregon”, or “ODOT” as applicable because of context.
Work Day - Any and every calendar day from January 1 to December 31 of every year, excluding Saturdays, Sundays and Legal Holidays.
END OF SECTION
SECTION 00120 – BIDDING REQUIREMENTS AND PROCEDURES
Comply with Section 00120 of the Standard Specifications supplemented and/or modified as follows:
00120.00 Prequalification of Bidders - Delete and replace with the following:
See Instructions to Bidders.
00120.01 General Bidding Requirements – Delete and replace with the following:
See Instructions to Bidders.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 7
00120.05 Request for Plans, Special Provisions, and Bid Booklets: – Delete and replace with the following:
See Notice of Public Improvement Contract and Instructions to Bidders.
Copies of the 2021 Oregon Standard Specifications for Construction and Supplements might be found on the Oregon Department of Transportation website at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
00120.15 Examination of Work Site and Solicitation Documents; Consideration of Conditions to be Encountered – Delete the third paragraph.
00120.25 Subsurface Investigations - Replace the first two sentences of the first paragraph with the following:
The Agency or its consultant has conducted subsurface or geologic investigations of the Project Site, and the results of these investigations are included in the Bid Documents and available at the Engineer’s office.
00120.30 Changes to Plans, Specifications, or Quantities before Opening of Bids - Delete and replace with the following:
See Instructions to Bidders.
00120.40 Preparation of Bids – Delete and replace this section with the following:
See Instructions to Bidders.
00120.45 Submittal of Bids - Delete and replace with:
See Instructions to Bidders.
00120.50 Submitting Bids for More than One Contract – Delete this subsection.
00120.60 Revision or Withdrawal of Bids - Delete and replace with the following:
See Instructions to Bidders.
00120.70 Rejection of Nonresponsive Bids – Delete and replace with the following:
00120.95 Opportunity for Cooperative Arrangement – Delete this section.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 8
SECTION 00130 – AWARD AND EXECUTION OF CONTRACT
Comply with Section 00130 of the Standard Specifications supplemented and/or modified as
00130.00 Consideration of Bids - Delete third paragraph.
00130.10 Award of Contract - Delete and replace with the following:
See Instructions to Bidders.
00130.15 Right to Protest Award – Delete and replace with the following:
00130.30 Contract Booklet – Add the following:
Other documents are part of the contract documents by reference. These include, but are not limited to:
• The "Oregon Standard Specifications for Construction", 2021 Edition, as published by the Oregon Department of Transportation (ODOT).
• “Oregon Standard Drawings” latest edition, as published by ODOT.
• Clackamas County Service District No. 1 "Surface Water Standard
Specifications", latest edition.
00130.40 Contract Submittals - Delete and replace with the following:
00130.70 Release of Bid Guaranties – Delete and replace with the following:
SECTION 00140 – SCOPE OF WORK
Comply with Section 00140 of the Standard Specifications supplemented and/or modified as
00140.30 Agency-Required Changes in the Work – Replace the last paragraph with the following:
Upon receipt of an Engineer’s written order modifying the Work, the Contractor shall perform the Work as modified via Change Order, which may be subject to approval as an Amendment.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 9
If an Amendment incorporating changes to the Work increases the Contract amount, the Contractor shall notify its Surety of the increase and shall provide the Agency with a copy of any resulting modification to bond documents. The Contractor’s performance of Work pursuant to Amendments shall neither invalidate the Contract nor release the Surety.
Payment for changes in the Work shall be made in accordance with 00195.20. Contract Time adjustments shall be made in accordance with 00180.80.
00140.31 "As-Built" Records - Add the following section:
Maintain a current and accurate record of the work completed during the course of this contract. This may be in the form of "as-built" drawings kept by accurately marking a designated set of the contract plans with the specified information as the Work proceeds.
Accurate, complete and current "as-built" drawings are a specified requirement for full partial payment of the work completed. At project completion and as a condition of final payment, the Contractor shall deliver to the Project Manager a complete and legible set of "as-built" drawings.
The "as-built" drawings must show the information listed below. Where the term "locate" or "location" is used, it shall mean record of position with respect to both the construction vertical datum and either construction horizontal datum or a nearby permanent improvement.
1) Record location of underground services and utilities as installed.
2) Record location of existing underground utilities and services that are to remain and that are encountered during the course of the work.
3) Record changes in dimension, location, grade or detail to that shown on the plans.
4) Record changes made by change order.
5) Record details not in the original plans.
6) Provide fully completed shop drawings reflecting all revisions.
SECTION 00150 – CONTROL OF WORK
Comply with Section 00150 of the Standard Specifications modified as follows:
00150.00 Authority of the Engineer – Delete and replace the first sentence with the following:
Except as indicated elsewhere in the Contract (e.g. Amendment approval by the BCC), the Engineer has full authority over the Work and its suspension.
00150.05 Cooperative Arrangements – Delete this section.
00150.10 Coordination of Contract Documents
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 10
(a) Order of Precedence – Delete this section and replace with the following:
The Engineer will resolve any discrepancies between these documents in the following order of precedence:
• Approved Amendments;
• Approved Change Orders
• Bid Schedule with Schedule of Prices;
• Permits from governmental agencies
• Special Provisions;
• Agency-prepared drawings specifically applicable to the Project and bearing the Project title;
• Reviewed and accepted, stamped Working Drawings;
• Agreement Form;
• Standard Drawings;
• Approved Unstamped Working Drawings;
• Standard Specifications;
• All other Contract Documents not listed above.
Notes on a drawing shall take precedence over drawing details.
Dimensions shown on the drawings, or that can be computed, shall take precedence over scaled dimensions.
00150.15(b) Agency Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Engineer will perform the Agency responsibilities described in the ODOT Construction Surveying Manual for Contractors, Chapter 1.5 (see Section 00305) and the following:
00150.15(c) Contractor Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Contractor shall perform the Contactor responsibilities described in the ODOT Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305) and the following:
• Perform earthwork slope staking including intersections and matchlines and set stakes defining limits for clearing which approximate right-of-way and easements.
• Inform the Engineer of any property corners monuments and/or survey markers that are not shown on the plans and are found during construction activities prior to disturbing the monuments. Allow the Agency 2 Work days for referencing all found markers before they are removed. Monuments that are noted on the plans to be protected and are disturbed by the Contractor's activities shall be replaced by the Contractor’s surveyor at the Contractor's expense.
00150.50 Cooperation with Utilities: Add the following to the end of Paragraph (a):
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 11
There may be other utility servers who are not specifically listed in these Special Provisions or on the Plans that may be adjusting or inspecting their facilities within the project limits.
00150.50(c) Contractor Responsibilities – Add the following to the bulleted list:
• Hold a utility scheduling meeting and monthly utility coordination meetings (see also 00180.42);
• Maintain and re-establish utility location marks according to OAR 952-001-0090(3)(a).
Coordinate re-establishment of the location marks with the associated Utility;
• Determine the exact location before excavating within the tolerance zone according to OAR 952-001-0090(3)(c);
• Backfill any exposed utilities as recommended and approved by the Utility representative. Obtain utility locate warning tape from the Utility and replace damaged or removed warning tape. Utility locate warning tape may not be present at all existing utilities;
• Stake, place warning tape, and maintain no work limits around critical Utility facilities as shown or directed by the Engineer and the Utility; and
• In addition to the notification required in OAR 952-001-0090(6), notify the Engineer and the Utility as soon as the Contractor discovers any previously unknown Utility conflicts or issues. Contrary to the OAR, stop excavating until directed by the Engineer and allow the Utility a minimum of two weeks to relocate or resolve the previously unknown utility issues.
The existing underground utilities shown on the Plans have been determined by as-built records and field surveys, but are not guaranteed to be complete or accurate. The Contractor shall be responsible for contacting the individual utility companies to mark locations, and arranging with them for any relocation work that should be required.
The Contractor shall make excavations and borings ahead of the work where necessary to determine the exact location of underground pipes or other features, which might interfere with construction. The Contractor shall support and protect pipes or other services where they cross the trench and shall be responsible for all damages incidental in interruptions of service that may be caused by Contractor operations. Where a new utility line crosses an existing pipeline or other conduit, the trench backfill shall be well compacted in a manner that provides for the required backfill and compaction standards while protecting the utility in question.
Add the following subsection:
00150.50(f) Utility Information (No Anticipated Relocations) - Within the Project limits, there are no anticipated relocations with the Utilities listed in Table 00150-1. Minor grade adjustments by Canby Utility may be required for vaults. The Contractor shall contact those Utilities having buried facilities and request that they locate and mark them for their protection prior to construction.
Table 00150-1
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 12
Utility
Contact Person's Name, Address, Email, and Phone Number
Canby Utility (Utility poles) Jason Berning PO Box 1070 Canby, OR 97013 503-263-4322 jberning@canbyutility.org
Canby Utility (Water Main, and Hydrants)
Joseph Brennan PO Box 1070 Canby, OR 97013 jbrennan@canbyutility.org
Direct Link (Communications) Eric Kehler 190 SE 2nd Ave, Canby, OR 97013 503-266-8223 Eric.kehler@cbsoregon.com
NW Natural (Gas) Blake Johnson 220 NW Second Ave, Portland, OR 97209 503-833-2519 Blake.johnson@nwnatural.com
City of Canby (Sewer) Jerry Nelzen 1470 NE Territorial Rd, PO Box 930, Canby, OR 97013 503-266-0759 nelzenj@canbyoregon.gov
Astound(Broadband) (Formerly Wave)
Robert Lee 669 Glatt Circle, Woodburn, OR 97071 503-707-1076 rlee@wavebroadband.com
The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project.
Canby Utility Board - Power Suppliers -
Energized power lines overhang portions of the Work with a minimum vertical clearance of 18 feet. The Contractor shall maintain at least 10 feet of safety clearance. Exceptions require written approval from the Power Supplier(s) and may require an on-site safety watcher, at no cost to the Contractor. The Contractor shall provide the Engineer a copy of the written approval of exception before beginning Work.
Direct Link - Telecommunication Utilities - The Contractor shall obtain written approval from Telecommunication Utilities that have fiber optic communication cable facilities, for excavating within 10 feet of a buried fiber optic communications cable. Telecommunication Utilities may require an on-site safety representative at no cost to the Contractor for monitoring purposes. The Contractor shall provide the Engineer a copy of the written approval before beginning Work.
Add the following subsection:
00150.50(g) Utility Information (Anticipated Relocations):
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 13
The organizations list in Table 00150-2 may be adjusting Utilities within the limits of the Project during the period of the Contract with relocation Work estimated to be completed by the following dates and times:
Table 00150-2
Utility
Contact Person's Name, Address, Email, and Phone Number
Estimated Completion
Date
Canby Utility (Electrical vault adjustments)
Jason Berning PO Box 1070 Canby, OR 97013 503-263-4322 jberning@canbyutility.org
August 30, 2024
Canby Utility (Water meters)
Joseph Brennan PO Box 1070 Canby, OR 97013 jbrennan@canbyutility.org
Concurrent with roadway construction
Direct Link (Communications pedestals)
Eric Kehler 190 SE 2nd Ave, Canby, OR 97013 503-266-8223 Eric.kehler@cbsoregon.com
August 30, 2024
The Contractor shall contact the Engineer to view the approved utility relocation Plans.
The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project.
00150.55 Cooperation with Other Contractors - Add the following:
The following contractors will be working on or near the project site:
1) K&E Excavating Inc.
Brandon Young, Project Manager Office 971.707.2219 Cell 503.949.0219
00150.70 Detrimental Operations – Add the following:
Portions of this project might be constructed in close proximity to existing private improvements. All private improvements disturbed by the Contractor’s operations shall be repaired or replaced to equal or better condition at the Contractor’s expense. The Engineer may withhold from future payments to the Contractor, an amount equal to the costs reasonably estimated by the Engineer to repair or replace, as the case may be, those private improvements disturbed by the Contractor’s operations. Engineer shall release the retained amount once Engineer has determined that the Contractor has completed the repair consistent with the requirements of this provision. In addition, prior to construction, the Contractor shall provide to the Engineer videotape showing private property, if any, which may be disturbed during construction.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 14
SECTION 00160 – SOURCE OF MATERIALS
Comply with Section 00160 of the Standard Specifications supplemented and/or modified as follows:
00160.20(a) Buy America – Delete this section and replace with the following: Federal highway funds are NOT involved on this Project.
SECTION 00165 – QUALITY OF MATERIALS
Comply with Section 00165 of the Standard Specifications modified as follows:
00165.04 Costs of Testing – Replace this section with the following sentence: All testing required to be performed by the Contractor will be at the Contractor’s expense.
00165.10(a) Field-Tested Materials – Add the following sentence: The County follows the MFTP on its projects:
00165.10(b) Nonfield-Tested Materials - Add the following sentence:
The County follows the NTMAG on its projects.
SECTION 00170 – LEGAL RELATIONS AND RESPONSIBILITIES
Comply with Section 00170 of the Standard Specifications supplemented and/or modified as
00170.00 General - Replace the first sentence of the first paragraph in this section with the following:
The Contractor shall comply with all laws, ordinances, codes, regulations, executive orders, and administrative rules (collectively referred to as "Laws" in this Section) that relate to the Work or to those engaged in the Work.
00170.02 Permits, Licenses, and Taxes – Add the following:
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 15
This project is to be constructed in Clackamas County road right of way and streets. There are no separate road opening permits required from Clackamas County to perform the work required under this contract.
00170.61(a) Workers' Compensation - In the paragraph, replace "00170.70(d)" with "the Agreement".
Add the following subsection:
00170.67 Fees - The fee required by ORS 279C.825(1) will be paid by the Agency to the Commissioner of the Oregon Bureau of Labor and Industries under the administrative rules of the Commissioner.
00170.70(a) Insurance Coverages - Add the following to the end of this subsection:
The following insurance coverages and dollar amounts are required pursuant to this subsection:
Insurance Combined Single Limit Annual Aggregate Coverages per Occurrence Limit
Commercial General Liability $1,000,000 $2,000,000
Commercial Automobile Liability $1,000,000 (aggregate limit not required)
00170.70(d) Additional Insured - Add the following paragraph at the beginning of the section and add the bullets to the end of this subsection:
The liability insurance coverages of 00170.70(a) shall include the Agency, the Agency's governing body, board, or Commission and its members, and their respective officers, agents, and employees as Additional Insureds, but only with respect to the Contractor's activities to be performed under the Contract.
• Clackamas County and its officers, agents, and employees
• Clackamas County Board of Commissioners
• City of Canby and it officers, agents, and employees
00170.70(h) Agency Acceptance – Delete the paragraph in this section and replace with the following:
All insurance and insurance providers are subject to Agency acceptance. In addition, all of the following are subject to Agency acceptance and, if requested by Agency, the Contractor shall provide complete copies of the following to Agency’s representatives responsible for verification of the insurance coverages required by the Contract: insurance policies, endorsements, self-insurance documents and related insurance documents.
00170.70(k) Builder’s Risk Installation Floater – Delete the paragraph in this section and replace with the following:
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 16
If specified by Special Provision, the Contractor shall obtain, at its expense, and keep in effect during the term of the Contract, Builder’s Risk Installation Floater Insurance covering the Contractor's Materials and Equipment to be used for completion of the Work performed under the Contract. The minimum amount of coverage to be carried shall be equal to the full amount of the Contractor´s Equipment, Materials, or fixtures to be installed, in-transit, or stored off-site during the performance of the Contract. This insurance shall include as loss payees the Agency, State of Oregon, the building or structure owner, the Contractor and Subcontractors as their interests may appear.
00170.72 Indemnity/Hold Harmless – Delete and replace with the following:
Clackamas County Public Improvement Contract.
Extend indemnity and hold harmless to the Agency and the following:
• Clackamas County and its officers, agents, and employees
• Clackamas County Board of Commissioners
• City of Canby and it officers, agents, and employees
00170.85(b-1) Contractor Warranty for Specific Items – This subsection does not apply:
SECTION 00180 – PROSECUTION AND PROGRESS
Comply with Section 00180 of the Standard Specifications supplemented and/or modified as
00180.06 Assignment of Funds Due Under the Contract - Delete first bulleted item.
00180.21 Subcontracting - Add the following to subsection (a):
All contracts with subcontractors or suppliers shall have provisions making the contract assignable to the County, at the option of the County, if the Contractor terminates, goes out of business, declares bankruptcy, or otherwise is unable to perform provided that the County gives the subcontractor notice of assignment within fourteen (14) days of learning of the inability of the Contractor to perform.
The Engineer may revoke consent to subcontract. If the Engineer revokes consent to subcontract, the subcontractor shall be immediately removed from the Project Site.
00180.40 Limitation of Operations - Add the following to subsection (a):
The Contractor must provide, at a minimum, a 48-hour notice to the Clackamas County Project Manager in order to perform any work on Saturdays.
Add the following subsection:
00180.40(c) Specific Limitations - Limitations of operations specified in these Special Provisions include, but are not limited to, the following:
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 17
Limitations Subsection
Cooperation with Utilities .......................................... 00150.50 Cooperation with Other Contractors ......................... 00150.55 Contract Completion Time .................................... 00180.50(h) Traffic Lane Restrictions ...................................... 00220.40(e) Noise Control ........................................................... 00290.32 Maintenance Under Traffic ....................................... 00620.43 Opening Sections to Traffic ....................................... 00744.51
Be aware of and subject to schedule limitations in the Standard Specifications that are not listed in this Subsection.
00180.41 Project Work Schedules – Add the following:
A Type “A” schedule as detailed in the Supplemental Specifications is required on this Contract. In addition, a three-week look ahead schedule shall be prepared by the Contractor on a weekly basis and submitted to the Engineer. It shall include all construction activities planned for the following three-week period. The three-week look ahead schedule can be hand-written and shall be in a format agreed upon by the Contractor and the Engineer.
00180.42 Preconstruction Conference - Add the following:
Before beginning On-Site Work and before meeting with the Engineer for the preconstruction conference, hold a group utilities scheduling meeting with representatives from the utility companies involved with this project. Incorporate the utilities time needs into the Contractor's schedule submitted prior to the preconstruction conference.
Submit the following during the preconstruction conference unless otherwise directed:
• The names, addresses, and telephone numbers of two or more persons employed by the Contractor who can be reached day or night to handle emergency matters.
• Subcontractor's list including contact list for each subcontractor with phone numbers and addresses and work to be performed.
• List of personnel authorized to sign change orders and receive progress payment warrants.
• Video recording of private properties affected by construction per 00150.70.
A representative of each subcontractor shall be required to attend the pre-construction conference.
The Contractor shall plan and schedule all Utility adjustment operations well in advance of On-Site Work. When the Contractor becomes aware of Utility conflicts not previously identified, the Contractor shall notify the applicable Utilities in writing the same Calendar Day.
The Contractor shall allow Utilities at least 2 weeks (14 Calendar Days) to relocate (adjust) the Utility conflicts not previously identified.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 18
00180.43 Commencement and Performance of Work - Add the following bullet item:
• Conduct the work at all times in a manner and sequence that will insure minimal interference with traffic. The Contractor shall not begin work that will interfere with work already started. If it is in the County's best interest to do so, the County may require the Contractor to finish a portion or unit of the project on which work is in progress or to finish a construction operation before work is started on an additional portion or unit of the project.
00180.50(h) Contract Time - Complete all Work to be done under the Contract, except for seeding establishment not later than October 31, 2025.
00180.70 Suspension of Work - Add the following to the first bullet item:
If the Inspector has reason to believe that any safety provisions are not being adhered to, the Inspector will immediately notify the Contractor’s site foreman and/or the appropriate person and the County Project Manager. The purpose of this discussion is to determine the validity of the alleged violation. This will also allow the Contractor a reasonable amount of time to correct or improve any of the provisions for the safety on this project. If the County Project Manager finds the problem still unresolved or uncorrected, they will notify the Contractor’s Project Manager and the County’s Risk Management Safety Analyst. If the County’s Risk Management Safety Analyst finds that the job site contains any unresolved safety issues they will take appropriate action up to and including suspension of the Contractor’s operations on all or part of the Work.
00180.85(b) Liquidated Damages - Add the following paragraph:
The liquidated damages for failure to complete the Work on time required by 00180.50(h) will be $1,100 per Calendar Day *.
* Calendar Day amounts are applicable when the Contract time is expressed on the Calendar Day or fixed date basis.
00180.85(c) Lane Closures and Road Closures - Lane closures and road closures beyond the limits specified will inconvenience the traveling public and will be a cost to the Agency.
(1) Lane Closures - It is impractical to determine the actual damages the Agency will sustain in the event traffic lanes are closed beyond the limits listed in 00220.40(e).
Therefore, the Contractor shall pay to the Agency, not as a penalty, but as liquidated damages, $500 per 15 minutes, or for a portion of 15 minutes, per lane, for any lane closure beyond the limits listed in 00220.40(e). In addition to the liquidated damages, all added cost for traffic control measures, including flagging, required to maintain the lane closures beyond the allowed time limits, will be at no additional cost to the Agency. The required traffic control measures will be as determined by the Engineer.
The Engineer will determine when it is safe to reopen lanes to traffic. Assessment of liquidated damages will stop when all lanes have been safely reopened. Any liquidated
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 19 damages assessed under these provisions will be in addition to those listed in 00180.85(b).
00180.88 Workplace Harassment Prevention Plan – Submit a workplace harassment prevention plan for review 10 days before the preconstruction conference. The plan shall ensure all workers are guaranteed a safe and respectful work environment regardless of their identity or status. The plan applies to, but is not limited to, a worker’s race, gender, creed, or any protected characteristic under state or federal law. At a minimum, the plan shall include:
• A Statement that the Contractor shall provide a safe and respectful workplace on the jobsite for all workers, subcontractors, suppliers, and other persons performing work.
• A description of how the plan will be implemented and monitored during the project duration.
• A list of the in-person trainings that will be conducted for workers of all ranks working on the project to support, promote, and grow a positive jobsite culture.
• A list of meaningful policies including procedures for aggrieved workers in need of recourse.
• How incidents involving bullying or harassment will be investigated and resolved in a prompt, thorough, and impartial manner.
Contractor shall post on the jobsite and make available copies of policies about hate, intimidation, or harassment including how to report incidents and how to receive support.
Materials will be provided in all languages necessary to be inclusive of the workforce.
00180.89 Measurement – No measurement of quantities will be made for workplace harassment prevention plan.
00180.95 Payment – Payment for workplace harassment prevention plan will be for developing and implementing the plan during construction of the project, in-person training, developing meaningful policies, and investigating incidents.
SECTION 00190 – MEASUREMENT OF PAY QUANTITIES
Comply with Section 00190 of the Standard Specifications supplemented and/or modified as
00190.20(a) Contractor to Provide Vehicle Weigh Scales: Delete and replace the last paragraph in this section with the following:
Unless otherwise provided in the Contract, Pay Items to be measured by weight shall include all Contractor costs for providing, maintaining, inspecting, and testing scales; for furnishing appropriate weigh tickets; for self-printing scales; for electronic weigh memo system(s); and for transporting Materials to the scales or to check weighing.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 20
00190.20(f)(1) Scale with Automatic Printer: Delete and replace the first sentence in this section with the following:
If the scales have an automatic weigh memo printer or an approved electronic weigh memo system that does not require manual entry of gross weight information, the Agency may periodically have a representative at the scales to observe the weighing procedures.
00190.20(f)(1) Scale with Automatic Printer: Delete and replace the last bullet in this section with the following:
• Furnish a legible, serially numbered weigh memo for each load of Materials to the Agency's Materials receiver at the point of delivery, or as directed by the Engineer.
The memo shall identify the Project, the Materials, the date, net weight (gross and tare as appropriate), and identification of the vehicle and weigh technician. If approved by the Engineer an electronic weigh memo system may be used.
Requests to use an electronic weigh memo system shall be submitted to the Engineer according to 00150.37, providing sufficient detail for the Engineer to perform an evaluation. If approved, the Contractor shall provide training, technical support, reports, and weigh memo information to the Engineer at no additional cost to the Agency. The electronic weigh memo system shall be:
• Capable of recording and securely retaining the same required “weigh memo” information identified above. For retention see 00170.07(c).
• Fully integrated with the provided weigh scale system.
• Designed in such a way that the data electronically read from scales cannot be altered by the Contractor, Subcontractor, Supplier, Engineer, or other system users.
• Designed to allow the Engineer remote access to all the weigh memo data in real-time and allow the Engineer to add comments to the individual weigh memo regarding waste, temperature, stations, yield or other information. The system shall identify the system user or individual that adds comments to the electronic weigh memo or otherwise access the system. The Contractor shall provide the Engineer a means to access the data if the Engineer cannot use an Agency provided hand held device for access.
• Capable of providing all the weigh memo information, including any added comments, in an electronic data file the Engineer can easily access without proprietary software.
00190.20(g) Agency-Provided Weigh Technician: Delete and replace subsection (g) with the following:
The Contractor must provide a weigh technician. The Agency will not provide one for the Contractor.
00190.30 Plant Scales: Add the following sentence after the bulleted list:
If approved by the Engineer an electronic weigh memo system may be used in place of a printer system. See 00190.20(f)(3).
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 21
SECTION 00195 – PAYMENT
Comply with Section 00195 of the Standard Specifications supplemented and/or modified as follows:
00195.10 Payment For Changes in Materials Costs - Replace this subsection with the following subsection:
00195.10 Asphalt Cement Material Price Escalation/De-escalation - An asphalt cement escalation/de-escalation clause will be in effect during the life of the Contract.
The Agency reserves all of its rights under the Contract, including, but not limited to, its rights for suspension of the Work under 00180.70 and its rights for termination of the Contract under 00180.90, and this escalation/de-escalation provision shall not limit those rights.
(a) Monthly Asphalt Cement Material Price (MACMP) - The Monthly Asphalt Cement Material Price (MACMP) is established by the Agency each month. For the actual MACMP, go to the Agency website at:
https://www.oregon.gov/ODOT/Business/Pages/Asphalt-Fuel-Price.aspx
The MACMP is based on selling prices of asphalt cement published by Poten & Partners, Inc. for primarily PG 64-22 paving grades in the Portland, Oregon area and typical non-modified paving grades in the Boise, Idaho area. The MACMP for a given month is the average of the weekly published prices for each area reported each Friday in that month.
If any portion of the Project Site is located within the boundaries of ODOT Maintenance District 13 or 14, the MACMP will be based on the prices for the Boise, Idaho area. If no portion of the Project Site is within the boundaries of ODOT Maintenance District 13 or 14, the Contractor may elect to have the MACMP based on the prices of either the Portland, Oregon area or the Boise, Idaho area. If electing to use Boise, Idaho area prices for determination of the MACMP, the Contractor shall notify the Engineer in writing of the Contractor’s election before or within 7 Calendar Days after the date of the preconstruction conference. This election, once acknowledged by the Engineer, will be binding for the entire duration of the Contract. If no such written notification is made, the Portland, Oregon area prices will be used as the basis of the MACMP. The area selected as the basis of the MACMP, once chosen, will become the sole area to be used as the basis for all asphalt cement used on the Project.
If the weekly prices cease to be available from Poten & Partners, Inc. for any reason, the Agency, in its discretion will select and begin using a substitute price source or index to establish the MACMP each month. The Agency does not guarantee that asphalt cement will be available at the MACMP.
(b) Base Asphalt Cement Material Price (Base) - The base asphalt cement material price for this Project is the MACMP published on the Agency website for the month immediately preceding the Bid Opening date.
(c) Monthly Asphalt Cement Adjustment Factor - The monthly asphalt cement adjustment factor will be determined each month as follows:
• If the MACMP is within ± 5% of the Base, there will be no adjustment.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 22
• If the MACMP is more than 105% of the Base, then:
Adjustment Factor = (MACMP) - (1.05 x Base)
• If the MACMP is less than 95% of the Base, then:
Adjustment Factor = (MACMP) - (0.95 x Base)
(d) Asphalt Cement Price Adjustment - A price adjustment will be made for the items containing asphalt cement listed below. The price adjustment as calculated in (c) above will use the MACMP for the month the asphalt is incorporated into the Project. The price adjustment will be determined by multiplying the asphalt incorporated during the month for subject Pay Items by the Adjustment Factor.
The Pay Items for which price adjustments will be made are:
Pay Item(s)
Level 3, ½” ACP (assuming 5% Binder per Ton of ACP)
00195.20(b) Significant Changed Work – Add the following:
Significant is defined as:
a) An increase or decrease of more than 25 percent of the total cost of the Work calculated from the original proposal quantities and the unit contract prices; or,
b) An increase or decrease of more than 25 percent in the quantity of any one major contract item.
For condition b) above, a major item is defined as any item that amounts to 10 percent or more of the original total contract price.
00195.50(a) Progress Payments - Delete and replace the last sentence in the second paragraph as follows:
All estimated quantities are subject to correction in the final estimate. If the Contractor uses these estimates as a basis for making payments to Subcontractors and Suppliers, the Contractor assumes all risk and bears any losses that result.
00195.50(a)(1) Progress Estimates - Delete the first sentence and replace with the following:
At a regular period each month to be determined at the Preconstruction Conference, the Contractor will make an estimate of the amount and value of pay item work completed and in place. This estimate will be submitted to the Project Manager for review and approval.
(2) Value of Material on Hand - Delete the section and replace with the following:
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 23
(2) Value of Material on Hand - The Contractor will make an estimate of the amount and value of acceptable material to be incorporated in the completed work which has been delivered and stored as given in 00195.60(a) for review and approval.
(4) Limitations on Value of Work Accomplished - In the first sentence, change "Engineer's estimate" to “Contractor’s reviewed estimate”.
00195.50 (b) Retainage - Delete the first paragraph and replace with:
The amount to be retained from progress payments will be 5.0% of the value of payments made, and will be retained in one of the forms specified in Subsection (c) below. The County will withhold Retainage from all force account and change order work.
00195.50(c) Forms of Retainage – Delete first paragraph and replace with:
Forms of acceptable retainage are set forth below in Subsections (1) through (3). “Cash, Alternate A” or “Cash, Alternate B” (Retainage Surety Bond) are the Agency-preferred forms of retainage. Unless the Contractor notifies the County otherwise in writing, the County will automatically hold retainage per paragraph (2) “Cash, Alternate B (No Interest Earned). If the Agency incurs additional costs as a result of the Contractor’s election to use “Bonds and Securities”, the Agency may recover such costs from the Contractor by a reduction of the final payment.
Delete and replace paragraph (2) with the following:
(2) Cash, Alternate B (No Interest Earned) – Retainage will be deducted from progress payments and held by the Agency until final payment is made in accordance with 00195.90, unless otherwise specified in the Contract.
00195.50(d) Release of Retainage – Delete this section and replace with the following:
(d) Release of Retainage - As the Work progresses, release of the amounts to be retained under (b) of this Subsection will only be considered for Pay Items that have been satisfactorily completed. For purposes of this Subsection, a Pay Item will be considered satisfactorily completed only if all of the Work for the Pay Item is complete and all contractual requirements pertaining to the Pay Item and Work have been satisfied. Work not included in a Pay Item, or which constitutes part of an uncompleted Pay Item, will not be regarded as satisfactorily completed Work for the purposes of this Subsection.
When the Work is 50% completed and upon written application of the Contractor and written approval of the Surety, the Engineer or Project Manager may reduce or eliminate retainage on remaining progress payments if the Work is progressing satisfactorily.
A determination of satisfactory completion of Pay Items or Work or release of retainage shall not be construed as acceptance or approval of the Work and shall not relieve the Contractor of responsibility for defective Materials or workmanship or for latent defects and warranty obligations.
CI-300317309: S Ivy Street Pedestrian Intersection Improvements 24