About this file

This is a specification document for Item 964.6, an Epoxy Healer-Sealer Treatment on Bridge Decks project involving a state or local transportation department. The work consists of providing all labor, materials, and equipment required to prepare, clean, and apply an epoxy sealer system with sand aggregate to the entire surface of exposed concrete bridge decks. The epoxy sealer system must be one of three approved products: Bridge Seal 75% by Unitex, Dural 335 by Euclid Chemical, or Sikadur 55 SLV by Sika Corporation, selected with consideration for cure time and the project requirement that all lanes be reopened to traffic during daily high-volume hours. The sand aggregate must meet specific specifications, including being poorly graded with grain size between U.S. sieve size 20 and 40, angular, with less than 0.2 percent moisture, and free of contaminants. The contractor must submit a detailed Bridge Deck Epoxy Healer/Sealer Installation Plan for engineer approval prior to commencing work, including material and equipment lists, application procedures, joint protection methods, and work schedules accounting for curing time.

Payment is calculated by actual square yards of epoxy sealer system installed on the bridge deck at the contract unit price per square yard, with full compensation for all material, labor, equipment, cleaning, preparation, application, pavement marking removal, manufacturer's field support, and miscellaneous cleanup included in the bid price. The work must be performed when ambient temperature is between 65 and 95 degrees Fahrenheit, and the contractor is fully responsible for all expenses associated with the required manufacturer's field representative, who must be on-site prior to and during installation and must remain until the installation crew has demonstrated competency. The contractor must maintain comprehensive records for each batch, including batch numbers, placement locations, times, temperatures, and traffic opening times, and must repair any areas damaged during the contractor's operations at no additional cost to the department.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM 964.6

EPOXY HEALER-SEALER TREATMENT ON BRIDGE DECKS SQUARE YARD

Description

The work to be done under this Item shall consist of providing all labor, materials, and equipment required to prepare, clean, and apply a epoxy sealer system with sand aggregate to entire surface of exposed concrete bridge decks.

Materials

The epoxy sealer system shall be one of the followings or approved equivalent:

· Bridge Seal 75% by Unitex

· Dural 335 by Euclid Chemical

· Sikadur 55 SLV by Sika Corporation

The sealer system shall be selected with cure time in mind and in consideration to the overall deck sealing operation schedule. Sealer system that requires long cure time and impacts the project’s requirement that all lanes are re-opened to traffic during daily high volume hours will be rejected by the Engineer.

The sand aggregate used in conjunction with the epoxy system shall meet the requirements of Sand Borrow, M1.04.0 and be poorly graded with grain size between U.S. sieve size 20 and 40. The aggregate must be angular, with less than 0.2 percent moisture, and free of dirt, clay, asphalt, and other foreign or organic materials.

Equipment

For the epoxy sealer, the mixing and application systems must be capable of accurately blending the epoxy resin and hardening agent, and must uniformly and accurately apply the epoxy materials at the specified rate to the bridge deck in such a manner as to cover 100 percent of the work area including 1 inch of the vertical face of the curb/barrier.

ITEM 964.6 (Continued)

The fine aggregate spreader must be propelled in such a manner as to uniformly and accurately apply dry aggregate to excess onto the applied epoxy material. Self-propelled vacuum truck shall be used to remove excess debris and aggregate. For hand applications, equipment must consist of calibrated containers, a paddle type mixer, squeegees, and stiff bristle brooms suitable for mixing and applying the epoxy and aggregate.

Submittal

The Contractor shall submit for review and approval by the Engineer the Bridge Deck Epoxy Healer/Sealer Installation Plan, which shall include but no be limited to the following:

1. Material list and corresponding cut sheets

1. Equipment list and corresponding cut sheets (for surface preparation, epoxy mixing, and aggregate boarding)

1. A copy of International Concrete Repair Institute Guideline No. 03732

1. Application procedure

1. Method to protect bridge joint, and areas not to be sealed

1. Work schedule (Including curing time for epoxy)

The Contractor shall not begin the work until written approval of the above submittals has been received from the Engineer.

Construction.

Surface Preparation

Inspect the deck and identify deteriorated concrete areas for full and/or partial depth concrete deck repair. All concrete deck patches shall be cured for at least 28 days of age prior to the shotblast cleaning operation.

The Contractor shall remove all existing pavement marking on the bridge deck area for the sealer application. This work shall be considered incidental to the Item.

The Contractor shall remove all sand deposit, and other debris from the bridge. Immediately prior to application of the healer sealer, clean the entire deck surface by shot blasting to remove asphaltic material, oils, dirt, rubber curing compounds, paint carbonation, laitance, weak surface mortar, and other materials that may interfere with the bonding or curing of the healer sealer. The prepared deck surface must conform to requirements described in the International Concrete Repair Institute Guideline No. 03732, Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays, concrete surface profile 3 (CSP 3). The Pavement markings on the bridge deck must be removed and replaced at the completion of the work. A vacuum cleaner or oil-free moisture-free air blast should be used to remove all dust and other loose material.

Patching and cleaning operations must be inspected and approved prior to placing the sealer.

ITEM 964.6 (Continued)

Any contamination of the deck, or to intermediate courses, after initial cleaning, must be removed.

There must be no visible moisture present on the surface of the concrete at the time the epoxy sealer is applied. Conduct moisture testing in accordance with ASTM D 4263. A transparent polyethylene sheet (4 mil) must be taped to the deck. Seal all edges with tape that will stick to the concrete substrate, and leave the plastic sheet in place for a minimum of 16 hours to detect the presence of moisture in the deck concrete. There must be no moisture visible on the polyethylene sheet. Alternate methods to detect moisture must be approved by the Engineer. Compressed air may be used to dry the deck surface, providing it is moisture and oil free.

The bridge joints, drainage structures, and any other areas not to be sealed, shall be protected from damage during preparation of the surface. The protection shall be removed once the epoxy and aggregate has been applied, but prior to initial set of the epoxy. The protection must meet the approval of the Engineer.

Application

The epoxy manufacturer’s representative must be on site prior to and during the installation to ensure all preparation and application is performed according to their requirements. The epoxy sealer shall be applied and spread according to the manufacturer’s recommendations. The fine aggregate shall be applied in such a manner as to cover the epoxy mixture completely within 5 minutes. The epoxy sealer system shall be applied to the entire bridge deck surface and the areas within 1 inch of the vertical face of the curb/barrier.

The fine aggregate (sand) must be applied to excess and provide a dry appearance to the deck after placement. No bleed through, or wet spots should be visible in the overlay. If the surface appears wet additional sand will need to be placed immediately. The sand should be spread at a rate of at least 1.5 pounds per square foot. The Contractor should use an air compressor connected to a venturi system to effectively broadcast the aggregate.

All foot traffic on the uncured epoxy shall be minimized and shall only be done with steel spiked shoes approved by the Engineer.

The minimum curing periods must be according to the manufacturer’s recommendations, or as directed by the Engineer. The epoxy sealer shall also be cured until loose aggregate can be removed by vacuuming or brooming without tearing or damaging the surface. No traffic or equipment is allowed on the deck surface during the curing period.

The Contractor shall plan and prosecute the work to provide the minimum curing periods for both courses as specified herein, or other longer minimum curing periods as recommended by the manufacturer, prior to opening the bridge to traffic, unless otherwise permitted. Remove and replace any areas damaged or marred by the Contractor’s operations in accordance with this special provision at no additional cost to the Department.

ITEM 964.6 (Continued)

Provide the Engineer with all records including, but not limited to, the following for each batch provided:

· batch numbers and sizes

· location of batches as placed on deck, referenced by stations

· batch time

· temperature of air, deck surface, epoxy components, including aggregates

· loose aggregate removal time

· time open to traffic

The work shall be scheduled to be perfomed when the ambient tempreture is expected to be not less than 65 and not greater than 95 degrees fahrenheit.

Manufacturer's Field Representative

1.The Contractor shall arrange with the epoxy system’s manufacturer or distributor to have the services of a competent field representative at the work site prior to any installation to instruct the work crews in the proper installation procedures. The field representative shall remain at the job site after work commences and continue to instruct until the representative and the Contractor, Inspector and/or Engineer are satisfied that the crew has mastered the technique of installing the system successfully. The representative shall make periodic visits to the project as the work progresses and shall confer on each visit with the Contractor, Inspector and/or Engineer.
2.The manufacturer's field representative must be fully qualified to perform the work and shall be subject to the approval of the Engineer.

3. The Contractor shall be completely responsible for the expense of the service of the required field representative and the bid contract price shall be full compensation for all costs in connection therewith.

METHOD OF MEASUREMENT AND BASIS OF PAYMENT

Item 964.60 will be measured for payment by actual Square Yard of epoxy sealer system installed on the bridge deck.

Item 964.60 will be paid for at the Contract unit price per Square Yard, which shall include full compensation for all material, labor, equipment, and incidental work required for cleaning, preparing and applying a epoxy sealer system. The removal of the pavement markings from the bridge deck, the manufacturer's field support, and miscellaneous clean-up shall be considered incidental to this item.

The full and/or partial depth concrete deck repair shall be performed and paid for under corresponding items.