ITB - Construction Checklist 2025.pdf

PDF 134 KB Posted

Attached to
26-032
Solicitation number
336-ITB26-032-3218-2027
Issued by
Polk County, Iowa

About this file

This document is an Iowa Communications Network Construction Site Inspection Checklist used by the Iowa Telecommunications and Technology Commission for the City of Des Moines cable relocation project (ICN OSP Project #77244807) in Polk County. The checklist establishes quality assurance standards for underground cable and fiber optic infrastructure installation, covering excavation and restoration work, cable and conduit installation, handhole installation, grounding and locate facilities, and building entrance and termination components. Sealed bids for this project were due November 23, 2026 at 12:00 p.m. Central, with bid opening scheduled for November 11, 2026 at 4:00 p.m. CST. The project documentation package includes the Invitation to Bid 336-ITB26-032-3218-2027, engineering plans, scope of work, typical drawings, and this construction checklist.

The checklist serves as a mandatory inspection protocol to verify contractor compliance with technical specifications and industry standards throughout project execution. Key inspection items include verification of proper cable depth and routing, correct handhole installation with crushed rock base and wire mesh protection, maintenance of minimum cable bend radius, proper grounding with #6 bare copper bonded connections, tracer wire installation, and secure exterior conduit installations with sealed penetrations. All handhole components must be backfilled and compacted, conduits must be plugged, and pull ropes and tracer wires must be installed per standards. Building entrance elements require proper fiber panel and bulkhead installation with appropriate grounding connections and clear directional labeling. Bidders seeking additional information were directed to contact Sheri Stephens at sheri.stephens@iowa.gov or +1 515-725-4747.

View the file

Other files

File Type Posted
77244807 - Typicals.pdf PDF
77244807 - ENGINEERING PLANS.pdf PDF
77244807 - Scope of Work (SOW).docx DOCX document
1471181-event.pdf PDF
26-032 ITB OSP #77244807 Polk Co - DSM fiber project.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Iowa Communications Network

Construction Site Inspection Checklist

Excavated Areas

• backfilled, restored, & tamped

• lawn restored

• concreted restored

• trash/debris removed

Installation Related Items

• cable/conduit at proper depth

• located within row

• markers installed

Handhole(s) Installation

• set at grade or provide depth

• crushed rock in base

• wire mesh on top of rock

• conduit(s) min. 6-in above rock

• conduit(s) plugged

• pull rope installed

• tracer wire conduit plugged

• backfilled / compacted

Cable Installation

• any visible damage to cable

• bend radius maintained

• cable properly coiled

• snap arounds installed

Locate Facilities

• ground rod installed per standards

• #6 bare copper bonded with ground clamp

• tracer wire routed into closure

• directions labeled

• locate facility tested and verified

Building Entrance/Terminations

• exterior conduit secured

• penetrations sealed

• locate facility installed (if appl)

• #10 ground to ground bar

• #10 grounded properly (lug)

• fiber panel installed correctly

• bulkhead installed correctly

• panel(s) labeled

• cable routed correctly