This is an Invitation to Bid (ITB) document issued by the City of Waterbury Department of Education for elevator addition projects at two elementary schools. The City of Waterbury seeks qualified contractors to construct new ADA-compliant elevator additions at Driggs Elementary School (77 Woodlawn Terrace, State Project #151-0315 LUE) and Woodrow Wilson Elementary School (235 Birch Street, State Project #151-0316 LUE). The scope of work includes new elevator shafts and cabs, structural modifications and foundations, mechanical and electrical systems integration, architectural finishes, fire alarm and life safety systems, and related site work. Sealed bids are due July 2, 2026 at 11:30 a.m. at the City Hall Building, 235 Grand Street, Waterbury, CT 06702. A mandatory pre-bid conference will be held on June 16, 2026 at 9:00 a.m., commencing at Driggs Elementary School and continuing to Woodrow Wilson Elementary School; attendance and on-time sign-in by a representative of each bidder at both locations is mandatory. The contractor must meet critical milestones including completion of all demolition work with weathertight protection, finish work in designated spaces, fire-rated barriers, and foundation backfill by August 20, 2026 (prior to school year start). Substantial Completion is required by December 15, 2026, and Final Completion by February 10, 2027. The City reserves the right to make one award or separate awards for each school project.
All bids of $50,000 or more must include bid security equal to ten percent of the total bid price, and the selected contractor must furnish a 100 percent performance bond and potentially a 100 percent payment bond. Connecticut state set-aside requirements mandate a minimum of 25 percent of the state-funded contract value be awarded to DAS-certified small businesses and 6.25 percent to minority-, women-, and disabled-owned businesses. Prevailing wage rates per Connecticut Department of Labor standards (dated May 18, 2026) apply to all work. Required insurance includes General Liability ($1,000,000 per occurrence / $2,000,000 aggregate), Automobile Liability ($1,000,000 combined single limit), Workers' Compensation (statutory limits), Excess/Umbrella Liability ($5,000,000), Contractors Pollution Liability ($1,000,000), and Builder's Risk equal to construction value. The contractor must comply with the Davis-Bacon Act, federal American Recovery and Reinvestment Act requirements, HUD Section 3 Clause provisions, and the City of Waterbury Good Jobs Ordinance, and must file an Affirmative Action Plan with the Commission on Human Rights and Opportunities prior to construction commencement. Compensation is limited to the bid amount with five percent retainage at the City's discretion. The architect is Friar Architecture, Inc. Questions regarding the bid must be submitted by June 22, 2026 at 2:00 p.m., with clarifications issued by June 26, 2026 at 2:00 p.m. Contact the Office of the Director of Purchasing at 203-574-6748 for further information.
Text of this file
CITY OF WATERBURY
DRIGGS ELEMENTARY SCHOOL & WOODROW WILSON ELEMENTARY SCHOOL
ELEVATOR ADDITIONS
Driggs Elementary: 77 Woodlawn Terrace
Woodrow Wilson Elementary: 235 Birch Street
WATERBURY, CONNECTICUT
ISSUE FOR RE-BID: June 5, 2026
CONTRACT AND SPECIFICATIONS
City Project ITB.: 8799
State Project No.: Driggs Elementary: 151-0315 LUE; Wilson Elementary: 151-0316
LUE
Mayor: Honorable Paul K. Pernerewski, Jr.
Superintendent of Schools: Dr. Darren Schwartz
Chief Operating Officer: Nicholas J. Albini
Architect: Friar Architecture, Inc.
00 01 10 TABLE OF CONTENTS 1/15/2026
2022-049A
Driggs & Wilson Elementary
- Elevator Additions
Waterbury, CT
00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
Invitation to Bid
00100 Instructions to Bidders
00200 Addendum Acknowledgment Form
00300 Bid Form
00400 Technical Specifications
Attachment A
Annual Statement of Financial Interest
Debarment Certification
City of Waterbury Disclosure of Outstanding Obligations
Attachment B
Sample Contract
General Conditions
Special Conditions
Sample Corporate Resolution
Sample LLC Resolution
Prevailing Wage Rates (place holder)
Good Jobs Ordinance
HBMI Report – Driggs Elementary School
HBMI Report – Woodrow Wilson Elementary School
Geotechnical Engineering Recommendations – Driggs Elementary School
Geotechnical Engineering Recommendations – Woodrow Wilson Elementary School
SPECIFICATIONS
DIVISION 01 -- GENERAL REQUIREMENTS
01 10 00 – Summary
01 14 01 – Preservation and Restoration
01 22 00 – Unit Prices
01 25 00 - Substitution Procedures
01 31 00 - Payment Procedures
01 31 00 - Project Management and Coordination
01 32 00 - Construction Progress Documentation
01 32 33 - Photographic Documentation
01 33 00 - Submittal Procedures
01 40 00 - Quality Requirements
01 42 00 - References
Driggs & Wilson Elementary
- Elevator Additions
Waterbury, CT
00 01 10 - 2
01 50 00 - Temporary Facilities and Controls
Project Sign Template
01 57 13 - Temporary Erosion and Sediment Control
01 57 14 - Temporary Dust Control
01 60 00 - Product Requirements
01 73 00 - Execution
01 74 19 - Construction Waste Management and Disposal
01 77 00 - Closeout Procedures
01 78 23 - Operation and Maintenance Data
DIVISION 02 -- EXISTING CONDITIONS
02 41 00 - Demolition
02 41 23 - Site Demolition
02 82 13.31 – Non-Disturbrance Asbestos Removal and Disposal
02 83 33.13 – Lead Paint (Driggs)
02 83 33.13 – Lead Paint (Wilson)
02 84 11 – Polychlorinated Biphenyl (PCB) Abatement (Driggs)
02 84 11 – Polychlorinated Biphenyl (PCB) Abatement (Wilson)
Abatement Plan – Driggs
Abatement Plan – Wilson
DIVISION 03 -- CONCRETE
03 30 00 - Cast-in-Place Concrete
03 32 00 - Site Cast-in-Place Concrete
DIVISION 04 -- MASONRY
04 20 00 - Unit Masonry
DIVISION 05 -- METALS
05 12 00 - Structural Steel Framing
05 50 00 - Metal Fabrications
DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
06 10 53 - Miscellaneous Rough Carpentry
06 16 00 - Sheathing – USG
DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
07 13 00 - Sheet Waterproofing
07 21 00 - Thermal Insulation
07 27 00 - Air Barriers
Driggs & Wilson Elementary
- Elevator Additions
Waterbury, CT
00 01 10 - 3
07 42 13 - Metal Wall Panels
07 53 23 - Ethylene-Propylene-Diene-Monomer Roofing (EPDM) - Elevate
07 62 00 - Sheet Metal Flashing and Trim
07 71 23 - Manufactured Gutters and Downspouts
07 84 00 - Firestopping
07 92 00 - Joint Sealants
07 95 13 - Expansion Joint Cover Assemblies
DIVISION 08 -- OPENINGS
08 06 71 – Driggs Hardware Schedule
08 06 71 – Wilson Hardware Schedule
08 71 00 – Driggs Door Hardware
08 71 00 – Wilson Door Hardware
08 11 13 - Hollow Metal Doors and Frames
08 14 16 - Flush Wood Doors
08 43 13 - Aluminum-Framed Storefronts
08 80 00 – Glazing
DIVISION 09 -- FINISHES
09 21 16 - Gypsum Board Assemblies
09 22 16 - Non-Structural Metal Framing
09 51 00 - Acoustical Ceilings
09 65 00 - Resilient Flooring
09 91 23 - Interior Painting
DIVISION 10 -- SPECIALTIES
10 14 23 - Panel Signage
10 14 26 - Post and Panel Signage
10 26 00 - Wall and Door Protection
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS (NOT USED)
DIVISION 13 -- SPECIAL CONSTRUCTION (NOT USED)
DIVISION 14 -- CONVEYING EQUIPMENT
14 21 00 - Electric Traction Elevators
DIVISION 21 -- FIRE SUPPRESSION (NOT USED)
DIVISION 22 -- PLUMBING
22 04 00 - General Conditions for Plumbing Trades
Driggs & Wilson Elementary
- Elevator Additions
Waterbury, CT
00 01 10 - 4
22 04 10 - General Conditions for Plumbing Demolition
22 05 17 - Sleeves and Sleeve Seals for Plumbing Piping
22 05 23 - General-Duty Valves for Plumbing Piping
22 05 29 - Hangers and Supports for Plumbing Piping and Equipment
22 05 53 - Identification for Plumbing Piping and Equipment
22 07 00 - Plumbing Insulation
22 10 05 - Plumbing Piping
22 40 00 - Plumbing Fixtures and Specialties
DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 04 00 - General Conditions for Mechanical Trades
23 05 29 - Hangers and Supports for HVAC Piping, Ductwork and Equipment
23 05 53 - Identification for HVAC Piping and Equipment
23 05 93 - Testing, Adjusting, and Balancing for HVAC
23 07 00 - HVAC Insulation
23 31 00 - HVAC Ducts and Casings
23 33 00 - Air Duct Accessories
DIVISION 25 -- INTEGRATED AUTOMATION
DIVISION 26 -- ELECTRICAL
26 04 00 - General Conditions for Electrical Trades
26 05 01 - Electrical Demolition
26 05 03 - Equipment Wiring Connections
26 05 19 - Electrical Power Conductors and Cables
26 05 26 - Grounding and Bonding for Electrical Systems
26 05 29 - Hangers and Supports for Electrical Systems
26 05 33 - Raceway and Boxes for Electrical Systems
26 05 53 - Identification for Electrical Systems
26 09 23 - Lighting Control Devices
26 24 16 - Panelboards
26 27 26 - Wiring Devices
26 28 13 - Fuses
26 28 19 - Enclosed Switches
26 51 00 – Lighting
DIVISION 27 -- COMMUNICATIONS
27 05 29 – Hangers and Supports for Communications Systems
27 05 33 – Raceway and Boxes for Communication Systems
27 51 29 – Emergency 2-Way Communication System
Driggs & Wilson Elementary
- Elevator Additions
Waterbury, CT
00 01 10 - 5
DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY
28 05 29 - Hangers and Supports for Electronic Safety and Security
28 05 33 - Raceway and Boxes for Electronic Safety and Security
28 31 00 - Fire Detection and Alarm
DIVISION 31 -- EARTHWORK
31 23 10 - Earthwork
DIVISION 32 -- EXTERIOR IMPROVEMENTS
32 12 16 - Bituminous Concrete Pavement
32 16 23 - Curbing
32 17 23 - Pavement Markings
32 31 13 – Chain Link Fences and Gates
DIVISION 33 -- UTILITIES
33 40 00 – Storm Drainage System
DIVISION 34 -- TRANSPORTATION
DIVISION 40 -- PROCESS INTEGRATION
DIVISION 46 -- WATER AND WASTEWATER EQUIPMENT
END OF SECTION
THE CITY OF WATERBURY
DEPARTMENT OF EDUCATION
INVITATION TO BID NO. 8799
ELEVATOR PROJECTS
AT
THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS
Pursuant to this Invitation to Bid (“ITB”), sealed bids (the “Bids”) for The Driggs and Woodrow Wilson Elementary Schools Elevator Projects will be received by the City of Waterbury (the “City”) at the office of the Director of Purchasing, Room 103, City Hall Building, 235 Grand Street, Waterbury, CT 06702 until 11:30 a.m. on July 2, 2026, and at that time and place will be publicly opened and read aloud. No bids will be received after 11:30 a.m. on the day the bids are to be opened.
The City invites qualified third parties (each a “Bidder” or “Contractor” and, collectively “Bidders” or “Contractors”) to submit Bids for the construction of new elevator additions at Driggs Elementary School and Woodrow Wilson Elementary School. The projects have been designed by Friar Architecture, Inc. (“Friar”) and are intended to provide ADA-compliant vertical circulation and improved accessibility for students, staff, and visitors. The selected Contractor(s) will be responsible for furnishing all labor, materials, equipment, and supervision necessary to complete the work in accordance with the construction documents prepared by Friar. As also set forth below in Section 00400, the files are posted in the "Documents" section of ProcureWare and the DAS website.
Bids must be enclosed in an opaque sealed envelope and plainly marked with the name of the Project Title (i.e., Driggs and Woodrow Wilson Elementary Schools Elevator Projects) and shall contain the name and address of the Bidder on the envelope.
Each Bid of $50,0000.00 or more shall be submitted in accordance with the Instructions to Bidders and be accompanied by a Bid Security (e.g., a Certified Check or Bid Bond) in the amount of ten (10) percent of the Total Bid Price. The Bidder to whom a contract is offered with a total cost greater than $50,000 must furnish to the City a one hundred
(100) percent performance bond with a surety, and in a form acceptable to the City. In the City's sole discretion, it may also require a one hundred (100) percent payment bond and/or other additional security with a surety, and in a form acceptable to the City.
Complete instructions for filing Bids are included in the Instructions to Bidders.
After reviewing the factors set forth in the Instructions to Bidders, the City reserves the right to reject any and all Bids, to make one award or separate awards of the individual school elevator project, or to decline to make an award.
A mandatory pre-bid conference will be held at 9:00 a.m. on June 16, 2026 with the conference commencing at The Driggs Elementary School (77 Woodlawn Terrace) and continuing on to The Woodrow Wilson Elementary School (235 Birch Street). Attendance and on-time sign-in at the pre-bid conference at each location by a representative of each Bidder is mandatory.
This contract is subject to state set-aside and contract compliance requirements.
Contact the Office of the Director of Purchasing at 203-574-6748 for further information.
https://friarct-my.sharepoint.com/personal/jmy_friar_com/_layouts/15/onedrive.aspx?id=%2Fpersonal%2Fjmy%5Ffriar%5Fcom%2FDocuments%2FWaterbury%20Elevators%20%2D%20Driggs%20%26%20Wilson%2FRe%2DBid%20Documents&ga=1
INVITATION TO BID NO. 8799
ELEVATOR PROJECTS
AT
THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS
TABLE OF CONTENTS
SECTION 00100 - INSTRUCTIONS TO BIDDERS
SECTION 00200 – ADDENDUM ACKNOWLEDGEMENT
SECTION 00300 – BID FORM
SECTION 00400 – TECHNICAL SPECIFICATIONS
INVITATION TO BID NO. 8799
ELEVATOR PROJECTS
AT
THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS
SECTION 00100
INSTRUCTIONS TO BIDDERS
ARTICLE 1. QUALIFICATIONS OF BIDDERS.
1.1 In evaluating Bids, the CITY will consider the qualifications of only those Bidders whose Bids, among other factors, follow the requirements set forth elsewhere in the Bid Documents.
1.2 The CITY reserves the right to reject any Bid based upon Bidder’s prior history with the CITY or with any other party that demonstrates, without limitation, failure to perform or unsatisfactory performance in accordance with the terms of one or more contracts or purchase orders or significant failure(s) to meet contractual obligations.
ARTICLE 2. COPIES OF BID DOCUMENTS.
2.1 Complete sets of Bid Documents shall be used in preparing Bids; neither the CITY nor its representative assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bid Documents.
2.2 The CITY and its representative in making copies of Bid Documents available do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use.
ARTICLE 3. EXAMINATION OF BID DOCUMENTS AND SITE.
3.1 Before submitting a Bid, each Bidder must (a) examine the Bid Documents thoroughly, (b) familiarize itself with all Federal, State and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work; and (c) study and carefully correlate the Bidder's observations and findings with the requirements of the Bid Documents.
3.2 The submission of a Bid will constitute an incontrovertible representation by the Bidder that it has complied with every requirement of this Article 3 and that the Bid Documents are sufficient in scope and detail to indicate and convey all terms and conditions necessary for the Bidder's proposed performance of the Work.
ARTICLE 4. INTERPRETATIONS.
4.1 All questions about the meaning or intent of the Bid Documents must be submitted to the CITY’s ProcureWare website by June 22, 2026, 2:00PM.
4.2 The CITY will issue written clarifications or interpretations by Addenda online at the CITY’s ProcureWare website not later than June 26, 2026, 2:00PM. Only information issued by such CITY written Addenda will be binding. Oral and other clarifications or interpretations will not be binding and will be without legal effect.
4.3 Each Bidder shall be responsible for determining that it has received all Addenda issued and shall acknowledge receipt of all Addenda on the Addendum Acknowledgment Form and the Bidder shall list therein all written Addenda number(s) issued by the CITY.
ARTICLE 5. PRE-BID CONFERENCE.
5.1 A mandatory pre-bid conference will be held at the time and place indicated in the Invitation to Bid to discuss the requirements of the Bid Documents. Attendance at the pre-bid conference is mandatory by a representative of each prospective Bidder.
ARTICLE 6. BID FORM.
6.1 Each Bid shall be submitted on the Bid Form included in Section 00300 of the Bid Documents. The Bid Form shall be removed from the Bid Documents, filled in as required below, and submitted to the CITY. Bidders must fill in all blank spaces on the Bid Form for Bid prices, including without limitation unit prices, extended prices and total price or the Bid will not be considered and shall be void.
6.2 Bid Forms shall be completed in ink. The Bid price of each item on the form shall be stated in figures. If unit prices are required on the Bid Form, discrepancies between unit prices and their respective total amounts will be resolved in favor of the unit prices.
Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
6.3 All names shall be typed or printed below the signature.
6.4 The name and address to which communications regarding the Bid are to be directed shall be shown.
6.5 One (1) original, one (1) paper copy, as well as a copy of the original Bid in pdf format on a CD or flash drive. Each Bid shall be submitted in a sealed opaque envelope bearing on the outside the name of Bidder, its address, and the Project Title for which the Bid is submitted. (If forwarded by mail, Bid and sealed envelope marked as described above shall be enclosed in another envelope with the notation "BID ENCLOSED" on the face and addressed as indicated in the Invitation to Bid.)
ARTICLE 7. RECEIPT OF BIDS.
7.1 Sealed Bids for the Work of this Project will be received at the time and place indicated in the Invitation to Bid.
7.2 The CITY, in its sole discretion, may refuse to consider any Bid not prepared and/or not submitted in accordance with the Bid Documents. Bids will not be received or accepted by the CITY from prospective Bidders who did not attend a mandatory pre-bid conference.
7.3 Bidders are cautioned that it is the responsibility of each individual Bidder to assure that its Bid is in the possession of the Director of Purchasing, or an alternate designated by him, prior to the stated time and at the place of the Bid Opening. The CITY is not responsible for Bids delayed by mail and/or delivery services of any nature.
ARTICLE 8. MODIFICATION AND WITHDRAWAL OF BIDS.
8.1 Bids may be modified only by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to that time scheduled by the CITY for the opening of Bids.
8.2 A Bid may be withdrawn by the Bidder prior to the scheduled time (or authorized postponement thereof by the CITY) for the opening of Bids.
8.3 Any Bid received after the time and date specified as the time for the CITY's opening of Bids shall not be considered. Once bids are opened by the CITY, no Bidder may withdraw its Bid for a period of ninety (90) days, excluding Saturdays, Sundays and legal holidays, after the actual date of the CITY's opening of the Bids.
ARTICLE 9. LOWEST RESPONSIBLE BIDDER.
9.1 A contract may be awarded to the Lowest Responsible Bidder. The term "Lowest Responsible Bidder" as used herein shall mean the Bidder whose Total Bid Price is the lowest of those Bidders possessing, without limitation, the skill, ability, expertise, experience, qualifications and integrity necessary for the faithful performance of the Work, as determined by the CITY.
9.2 After reviewing these and other factors, including without limitation, responsiveness, qualifications and price, the CITY reserves the right to reject any and all Bids, to decline to make an award, to waive any and all informalities if it is in the CITY's best interest to do
so. The CITY reserves the right to disregard all nonconforming, nonresponsive, conditional Bids, and Bids taking exception(s) to the Bid Documents.
9.3 A Bid which includes, for any Item(s), a Bid Price that is abnormally low or high may be rejected in its entirety.
9.4 The CITY reserves the right to reject the Bid of any Bidder that the CITY considers not to possess the qualities set forth in Article 1 herein.
ARTICLE 10. PURCHASE ORDER ISSUANCE/AWARD AND EXECUTION OF CONTRACT.
10.1 If a contract is to be awarded, the CITY will give the Lowest Responsible Bidder a Notice of Award within ninety (90) calendar days, excluding Saturdays, Sundays, and legal holidays, after the actual date of the opening of the Bids.
ARTICLE 11. ACCESS TO SITE.
11.1 Representatives of the State and any local or federal agencies having an interest in the Work shall have access to the Work wherever it is in preparation or progress and the Contractor shall provide proper facilities for such access and inspection.
ARTICLE 12. SALES TAX.
12.1 The goods and services to be provided under any contract or purchase order awarded pursuant to this Invitation to Bid is exempt from the sales taxes of the State of Connecticut.
ARTICLE 13. INSURANCE.
13.1. The Contractor shall not commence work under this Contract until all insurance required under this Section 13 has been obtained by the Contractor and such insurance has been approved by the CITY. The Contractor shall not allow any subcontractor to commence work on any subcontract until all insurance required of any such subcontractor has been so obtained and approved by the CITY. Insurance shall be provided by insurers, satisfactory to the CITY and authorized to do business in the State of Connecticut, an "A-"
Best's Rating and at least a Class V3 or better financial size category as shown in the most current A.M. Best Company ratings.
13.2. At no additional cost to the CITY, the Contractor shall purchase and maintain the insurance coverages set forth below which shall protect the CITY from claims which may arise out of or result from the Contractor’s obligation under this Contract, whether such obligations are the Contractor’s or subcontractor or person or entity directly or indirectly employed by said Contractor or subcontractor, or by any person or entity for whose acts said Contractor or subcontractor may be liable.
13.3. Each insurance policy shall state that the insurance company shall agree to investigate and defend the insured against all claims for damages, even if groundless. If any insurance required herein is to be issued or renewed on a claims made form as opposed to an occurrence form, the retroactive date for coverage shall be no later than the commencement date of this Contract and shall provide that in the event of cancellation or non-renewal, the discovery period for insurance claims (“Tail Coverage”) shall be available for at least 60 months.
13.4. The following policies with stated limits shall be maintained, in full force and effect, at all times during which the services are to be performed by the Contractor:
13.4.1 General Liability Insurance: $1,000,000.00 per occurrence and $2,000,000.00 aggregate and $2,000,000.00 Products and completed operations aggregate; providing coverage to protect the CITY for all damages arising out of bodily injuries, sickness to or death of all persons in any one accident or occurrence and for all damages arising out of destruction of property in any one accident or occurrence.
13.4.2 Automobile Liability Insurance: $1,000,000.00 combined single limit (CSL); providing coverage to protect the CITY with respect to claims for damage for bodily injury and or property damage arising out of ownership, maintenance, operation, use or loading and unloading of any auto including hired & non-owned autos.
13.4.3 Workers’ Compensation: Statutory Limits within the State of Connecticut:
Employers’ Liability:
EL Each Accident: $1,000,000.00 EL Disease Each Employee: $1,000,000.00 EL Disease Policy Limit: $1,000,000.00
Contractor shall comply with all State of Connecticut statutes as it relates to workers’ compensation.
13.4.4 Excess/Umbrella Liability Insurance: Excess or Umbrella insurance coverage that follows form or sits over General Liability, Automobile Liability and Workers Compensation insurances: $5,000,000.00 each occurrence and $5,000,000.00 in the aggregate.
13.4.5 Builder's Risk Insurance: coverage equaling the monetary value of the construction component of the Project. “All Risk” Builders Risk insurance (also know as “course of construction”) coverage with limits equal to or better than the maximum possible loss of all materials of construction used or contemplated under this Contract, including all materials in transit and all materials in storage wherever stored and the value of any and all subsequent Contract changes. This insurance shall include the interests of the CITY, the Contractor and any and all subcontractors. If deemed necessary by the CITY’s Risk Manager, this insurance shall also include coverage for the total value of the Project's constructed property and shall be valid until a certificate of occupancy is issued. Upon the issuance of said certificate, the CITY will assume responsibility for insuring said property.
13.4.6 Contractors Pollution Liability Insurance: $1,000,000.00 each occurrence/claim and $1,000,000.00 aggregate coverage. The foregoing per claim coverage plus appropriate aggregate coverage depending on the size of the job for contractor caused pollution events such as asbestos or lead abatement but not limited to only these pollution causes of loss. Note that there can be no exclusions for hazardous materials, including no exclusions for lead or asbestos.
13.5. Failure to Maintain Insurance: In the event the Contractor fails to maintain the minimum required coverage as set forth herein, the CITY may at its option purchase same and offset the Contractor’s invoices for the cost of said insurance.
13.6. Cancellation: The CITY shall receive written notice of cancellation from the Contractor at least thirty (30) calendar days prior to the date of actual cancellation, regardless of the reason for such cancellation.
13.7. Certificates of Insurance: The Contractor’s General, Automobile, Builder’s Risk and Excess/Umbrella Liability Insurance policies shall be endorsed to add the CITY and State of Connecticut as additional insureds and provide waivers of subrogation on all policies except Builder’s Risk and Pollution Liability. The insurance afforded to the additional insured shall be primary and non-contributory insurance and the coverage and limits provided under the Contractor’s policies shall not be reduced or prorated by the existence of any other insurance applicable to any loss the additional insured may have suffered. Prior to the execution of this Contract by the CITY, the Contractor shall furnish to the CITY, subject to CITY approval, certificate(s) of insurance and Additional Insured Endorsement and Waiver of Subrogation Endorsement verifying the above coverages, including the naming of the CITY, as follows: “The City of Waterbury and State of Connecticut are listed as additional insured on all lines of coverage except Pollution Liability and waiver of subrogation applies to all lines of coverage except Pollution Liability and Builder’s Risk as their interest may appear”. The CITY's Invitation to Bid Number must be shown on the certificate of insurance to ensure correct filing. The Contractor must supply replacement/renewal certificates at least 30 days prior to the expiration of the policy(ies). Said certificates shall contain a provision that coverage afforded under the policies shall not be cancelled or reduced for any reasons unless notice of than thirty
(30) calendar days has been mailed to the CITY's Using Agency and a copy to the CITY's Office of Corporation Counsel, 235 Grand Street, Waterbury, CT 06702.
13.8. No later than thirty (30) calendar days after receipt by the Contractor, the Contractor shall deliver to the CITY a copy of the Contractor's insurance policies and endorsements and riders.
ARTICLE 14. PURCHASE ORDER/CONTRACT TIME.
14.1 BIDDER agrees and covenants that the Contract Time shall commence upon delivery of the CITY’s written notice to proceed, which shall occur after contract execution by both parties. BIDDER guarantees that it shall complete all work in accordance with the following deadlines:
A. On or before August 20, 2026, the following work shall be completed:
(i) All demolition work including openings through the existing building envelope to the new elevator shaft with weathertight protection over openings;
(ii) All work in Storage 103, Corridor 104, Storage 104, Corridor 202, Teacher Work Room 203, Corridor 302 and Storage 303 to be complete including all openings, finishes, MEP fixtures, and life safety systems;
(iii) Provide locking, secure, fire rated barriers separating new corridor/elevator lobby from the existing school corridors, and all finish work within existing corridor area outside of this barrier providing access to Corridors, Teacher Work Room and Storage spaces; and
(iv) The elevator shaft foundation is to be backfilled and complete prior to the start of school in August of 2026.
B. The Project’s Substantial Completion Date is December 15, 2026.
C. The Project’s Final Completion Date is February 10, 2027.
ARTICLE 15. BID DOCUMENTS.
15.1 Bid Documents shall be any and all sections, terms, conditions, forms, drawings, data, etc., listed in the Table of Contents of the Bid Documents.
ARTICLE 16. FEDERAL, STATE AND LOCAL EMPLOYMENT REQUIREMENTS.
16.1 Contractors, if applicable, shall be obligated to fully comply with the attached Hiring of
Waterbury Residents on Certain Publicly Funded Construction Projects, i.e. City of Waterbury Ordinances Chapter 34 (“Good Jobs Ordinance “), Federal Davis-Bacon Act, Federal American Recovery and Reinvestment Act of 2009, and the Housing and Urban Development Section 3 Clause, all as further specified in the attached City of Waterbury Contract form. Also attached hereto, is a full copy of the aforesaid City of Waterbury Ordinance, commonly referred to as the “Good Jobs Ordinance “.
16.2 i. The contractor who is selected to perform this municipal public works project, funded in whole or part by the State, must comply with CONN. GEN. STAT. §§ 4a-60, 4a-60a, 4a- 60g, and 46a-68b through 46a-68f, inclusive, as amended by Public Act 23-204 and Public Act 25-168. An Affirmative Action Plan must be filed with and approved by the Commission on Human Rights and Opportunities prior to the commencement of construction.
ii. State law requires a minimum of twenty-five (25%) percent of the state-funded portion of the contract be set aside for award to subcontractors holding current certification from the Connecticut Department of Administrative Services (“DAS”) under the provisions of CONN. GEN. STAT. § 4a-60g. (25% of the total state-funded value with DAS-certified Small Businesses and 6.25% of the total state-funded value with DAS-certified Minority-, Women-, and/or Disabled-owned Businesses.) The contractor must demonstrate good faith effort to meet the 25% set goals.
iii. For municipal public works contracts, the contractor must file a written or electronic non-discrimination certification with the Commission on Human Rights and Opportunities.
Forms can be found at:
https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports.
16.3 Proposers are advised that prevailing wage rates apply to this Project. The minimum rates to be paid for labor of the various classifications shall be in accordance with the prevailing rate of wages established by the Connecticut Department of Labor. The Contractor should be aware that the Contractor will be obligated to certify payrolls and issue compliance statements in accordance with Connecticut procedural requirements. Proposer’s attention is directed to the attached prevailing wage rate schedule, dated May 18, 2026.
https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports
NOTE: Each Proposal over $50,000.00 submitted shall be accompanied by a Proposal Security (e.g., a Certified Check or Bid Bond) in the amount of ten (10) percent of the Total Proposal Price.
INVITATION TO BID NO. 8799
ELEVATOR PROJECTS
AT
THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS
SECTION 00200
ADDENDUM ACKNOWLEDGEMENT FORM
NOTE: The Bidder is to complete, sign and date this form. The completed form shall be submitted with the BID FORM in accordance with ARTICLE 6 of the INSTRUCTIONS TO
BIDDERS.
The undersigned, as Bidder’s Authorized Representative, acknowledges receipt of the following Addenda and that the modifications to the Bid Documents noted therein have been considered and all costs related thereto are included in the Bid Prices:
Addendum # _______ Dated Issued ____________________
Addendum # _______ Dated Issued ____________________
Addendum # _______ Dated Issued ____________________
Business Name of Bidder: _______________________________________________
(Print or Type)
By Bidder’s Authorized Representative:
Signature: ___________________________________________________________
Name: ___________________________________________________________ (Print or Type) Title: ___________________________________________________________ (Print or Type) Email: ___________________________________________________________ (Print or Type) Date: ___________________________________________________________
(Print or Type)
INVITATION TO BID NO. 8799
ELEVATOR PROJECTS
AT
THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS
ITEM # QTY DESCRIPTION
COST
EACH TOTAL COST
1.0 1 Driggs ES Elevator Addition (per scope) $ $
1.1 1 Driggs ES Elevator Addition – unit prices Rock Removal (per cubic yard) $ $
1.2 1 Driggs ES Elevator Addition – unit prices Structural Fill (per cubic yard) $ $
2.0 1 Wilson ES Elevator Addition (per scope) $ $
2.1 1 Wilson ES Elevator Addition – unit prices Rock Removal (per cubic yard) $ $
2.2 1 Wilson ES Elevator Addition – unit prices Structural Fill (per cubic yard) $ $
GRAND TOTAL ALL CHARGES $
In the event of mathematically incorrect calculations of individual items or totals, the mathematically correct amount as determined by the City shall govern in determining the TOTAL
BID PRICE.
The undersigned also agrees that the quantities indicated are for Bid comparison purposes only and are not represented to be actual quantities for completion of the Work.
The undersigned hereby certifies under the penalties of perjury that this Bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used in this section, the work "person" shall mean any natural person, joint venture, partnership, corporation, or other business or legal entity.
Social Security Number Signature of Individual or or Federal Identification Number Corporate Name
Corporate Officer (if applicable)
Notice of acceptance should be mailed, telegraphed or delivered to the (undersigned Bidder at the following address):
(Company Name)
By:
(Title)
(Business Address)
(City, State, Zip Code)
INVITATION TO BID NO. 8799
ELEVATOR PROJECTS
AT
THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS
SECTION 00400
TECHNICAL SPECIFICATIONS
Each project consists of the construction of a new elevator addition integrated into the existing school building. Work is expected to include, but is not limited to:
• New elevator shaft and cab;
• Elevator equipment and controls;
• Structural modifications and foundations;
• Architectural finishes;
• Mechanical, electrical, fire alarm, and life safety systems;
• Coordination with existing building systems;
• Site work related to the addition.
The construction documents for the Project and prepared by Friar are posted on ProcureWare and the DAS website in the "Documents" section of this bid.
Project Locations
• The Driggs Elementary School - 77 Woodlawn Terrace, Waterbury, CT 06710. State project #151-0315 LUE
• The Woodrow Wilson Elementary School – 235 Birch St, Waterbury, CT 06704, state project #151-0316 LUE
Scope of Work
The Contractor shall:
1. Construct elevator additions in strict accordance with the drawings and specifications prepared by Friar;
2. Coordinate all trades, subcontractors, inspections, and testing;
3. Maintain safe operations in an occupied school environment;
4. Comply with all federal, state, and local codes, including ADA and fire/life safety requirements;
5. Provide all permits, inspections, and approvals required for project completion; and
6. Coordinate construction activities with school administration to minimize disruption.
Bid Requirements
Bids shall include the following:
1. Cover Letter signed by an authorized representative
2. Company Profile & Experience https://friarct-my.sharepoint.com/personal/jmy_friar_com/_layouts/15/onedrive.aspx?id=%2Fpersonal%2Fjmy%5Ffriar%5Fcom%2FDocuments%2FWaterbury%20Elevators%20%2D%20Driggs%20%26%20Wilson%2FRe%2DBid%20Documents&ga=1 o Similar elevator or vertical transportation projects o Experience in occupied school facilities
3. Project Team o Project Manager o Superintendent o Key subcontractors
4. Project Approach and Schedule
5. Cost Proposal o Lump sum price or breakdown as requested o Alternates, if applicable
6. References (minimum of three)
7. Bonding Capacity and Insurance Information
Attachment A
• ANNUAL STATEMENT OF FINANCIAL INTEREST
• DEBARMENT CERTIFICATION
• CITY OF WATERBURY DISCLOSURE OF OUTSTANDING OBLIGATIONS
ANNUAL STATEMENT OF FINANCIAL INTERESTS (Calendar Year 202__) Persons or Entities Conducting Business with the City d:\attach-a-annual statement of financial interests.doc 1
I. Outstanding Purchase Orders of Contracts with the City
A. Contracts
No Contracts with the City
(Service or Commodity Covered by Contract)
(Term of Contract)
(Service or Commodity Covered by Contract)
(Term of Contract)
(Service or Commodity Covered by Contract)
(Term of Contract)
FILL IN AND RETURN WITH YOUR SUBMISSION
Persons or Entities Conducting Business with the City d:\attach-a-annual statement of financial interests.doc 2
B. Purchase Order(s).
No Purchase Order(s) with the City
(Service or Commodity Covered by Purchase Order)
(Date of Purchase Order)
(Service or Commodity Covered by Purchase Order)
(Date of Purchase Order)
(Service or Commodity Covered by Purchase Order)
(Date of Purchase Order)
Persons or Entities Conducting Business with the City d:\attach-a-annual statement of financial interests.doc 3
II. Financial Interest Disclosure (Public Officials, Employees or Board and Commission Members with interest in
Person or Entity Conducting Business with the City)
No Officials, Employees or Board and Commission Members with Financial Interest
(Name of Official)
(Position with City)
(Nature of Business Interest) (e.g. Owner, Director etc…)
Interest Held By:
Self Spouse Joint Child
(Name of Official)
(Position with City)
(Nature of Business Interest) (e.g. Owner, Director etc…)
Interest Held By:
Self Spouse Joint Child d:\attach-a-annual statement of financial interests.doc 4
1. I certify that this Annual Statement of Financial Interests is a complete and accurate statement of those matter required to be disclosed by me pursuant to §39.061 of the Code of Ordinances.
2. I understand that if I fail to file an Annual Statement (or amendment thereto) or an inaccurate Statement I will be in violation with Chapter 39 of the Code of Ordinance and, thereby, subject to the remedies set forth in §§38.71 and
39.101 of said Code.
3. I understand that I must file with the City Clerk, within fifteen (15) days following any reportable occurrence, any amendments to the Annual Statement.
I have read and agree to the above certification.
(Name of Company, if applicable)
Signature of Individual (or Authorized Signatory) Date
Print or Type Name and Title (if applicable)
DELIVERED By Mail Hand-Delivered
DISCLOSURE AND CERTIFICATION AFFIDAVIT REGARDING OUTSTANDING
OBLIGATIONS TO THE CITY OF WATERBURY
For the purposes of this Disclosure of Outstanding Financial Obligations, the following definitions apply:
(a) “Contract” means any Public Contract as defined below.
(b) "Person” means one (1) or more individuals, partnerships, corporations, associations, or joint ventures.
(c) “Public Contract” means any agreement or formal commitment entered into by the city to expend funds in return for work, labor, services, supplies, equipment, materials or any combination of the foregoing, or any lease, lease by way of concession, concession agreement, permit, or per agreement whereby the city leases, grants or demises property belonging to the city, or otherwise grants a right of privilege to occupy or to use said property of the city.
(d) “City” means any official agency, board, authority, department office, or other subdivision of the City of Waterbury.
State of_____________________________
SS.:___________________
County of___________________________
_____________________________________________________, being first duly sworn, deposes and says that:
1. I am the owner, partner, officer, representative, agent or ___________________ of __________________________(Contractor’s Name), the Contractor that has submitted the attached agreement.
2. I am fully informed respecting the preparation and contents of the attached Agreement and of all pertinent circumstances respecting such Agreement;
3. That as a person desiring to contract with the City (check all that apply):
____ The Contractor and each owner, partner, officer, representative, agent or affiliate of the Contractor has filed a list of taxable personal property with the City of Waterbury for the most recent grand list, as required by Conn.
Gen. Stat. §12-42.
____ Neither the Contractor nor any owner, partner, officer, representative, agent or affiliate of the Contractor are required to file a list of taxable personal property with the City of Waterbury for the most recent grand list, as required by Conn. Gen. Stat. §12-42.
____ Neither the Contractor nor any owner, partner, officer, representative, agent or affiliate of the Contractor either directly or through a lease agreement, owes back taxes to the City of Waterbury
OBLIGATIONS TO THE CITY OF WATERBURY
____ Neither the Contractor nor any owner, partner, officer, representative, agent or affiliate of the Contractor either directly or through a lease agreement, has any other outstanding obligations to the City of Waterbury
4. The following list is a list of the names of all persons affiliated with the business of the Contractor, if none state none. Use additional sheet if necessary (Must be on company letterhead and notarized):
Name Title Affiliated Company (if none state NONE)
Service or
Material
DOB
5. That as a person desiring to contract with the City:
(a) The Contractor or an owner, partner, officer, representative, agent or affiliate of the Contractor provides, or has provided, services or materials to the City within one (1) year prior to the date of this disclosure, if none, state none.
Use additional sheet if necessary (Must be on company letterhead and notarized):
Name Title Affiliated Company (if none state NONE)
Service or
Material
DOB
(b) The Contractor possesses an ownership interest in the following business organizations, if none, state none. Use additional sheet if necessary (Must be on company letterhead and notarized) :
Organization Name
Address Type of Ownership
(c) The following persons possess an ownership interest in the Contractor. If the Contractor is a corporation, list all of the officers of the corporation and the names of each stockholder whose shares exceed twenty-five
OBLIGATIONS TO THE CITY OF WATERBURY
(25) percent of the outstanding stock, if none, state none. Use additional sheet if necessary (Must be on company letterhead and notarized):
Name Title DOB Stock %
(d) Of the following of the affiliates, individuals or business entities identified in this affidavit, list each that owns, owned, or within one (1) year prior to the date of this disclosure has owned, taxable property situated in the City of Waterbury, if none state none. Use additional sheet if necessary (Must be on company letterhead and notarized):
Name Title Affiliated Company (if none state NONE)
Address DOB
(e) If the Contractor conducts business under a trade name, the following additional information is required: the place where such entity is incorporated or is registered to conduct such business; and the address of its principal place of business, if none, state none:
TRADE NAME PLACE OF INCORPORATION/REGISTRY PRINCIPAL
PLACE
OF BUSINESS
I hereby certify that the statements set forth above are true and complete, and I understand that any incorrect information or omission of information from this affidavit may result in the immediate termination of the Contractor’s agreement with the City of Waterbury.
For Partnership/Sole Proprietor
In presence of:
Witness Name of Partnership/Business
OBLIGATIONS TO THE CITY OF WATERBURY
By: ______________________________ Name of General Partner/ Sole Proprietor
Address of Business
State of _____________________ )
) SS
County of ____________________ )
______________________________________________ being duly sworn, Deposes and says that he/she is _____________________ of _____________ and that he/she answers to the foregoing questions and all statements therein are true and correct.
Subscribed and sworn to before me this _________ day of _________ 202_.
(Notary Public)
My Commission Expires: ________________________________
For Corporation
Witness Name of Corporate Signatory
Address of Business
Affix Corporate
Seal
By:__________________________________ Name of Authorized Corporate Officer
Its:_____________________________ Title
OBLIGATIONS TO THE CITY OF WATERBURY
State of _____________________ )
) SS
County of ____________________ )
______________________________________________ being duly sworn, deposes and says that he/she is _____________________ of _____________ and that he/she answers to the foregoing questions and all statements therein are true and correct.
Subscribed and sworn to before me this _________ day of _________ 202__.
(Notary Public)
My Commission Expires: ________________________________
This page intentionally left blank
Attachment B Documents
• SAMPLE CONTRACT
• GENERAL CONDITIONS
• SPECIAL CONDITIONS
• SAMPLE CORPORATE RESOLUTION
• SAMPLE LLC RESOLUTION
FINAL FORM CONTRACT for use in ITB 8799 Driggs and Wilson Elevator Projects
JPY 5.19.26
Construction Contract for
ITB No. 8799 Elevator Projects at The Driggs and Woodrow Wilson Elementary Schools between City of Waterbury and
THIS CONTRACT, effective on the date signed by the Mayor, is by and between the CITY OF WATERBURY, City Hall, 235 Grand Street, Waterbury, Connecticut (the "City") and ______________________________, located at ________________________, a ________________ duly registered to do business in Connecticut (the "Contractor").
WHEREAS the Contractor submitted a bid to the City in response to Invitation to Bid (“ITB”) No. 8799 for elevator projects at The Driggs and Woodrow Wilson Elementary Schools (the “Project”); and
WHEREAS the City accepted the Contractor’s bid for ITB No. 8799; and
WHEREAS the City desires to obtain the Contractor's services pursuant to the terms set forth in this Contract.
NOW THEREFORE, THE PARTIES AGREE AND COVENANT AS
FOLLOWS:
1. Scope of Services. The Contractor shall furnish all the labor, services, equipment, materials, supplies, transportation, and incidentals necessary to complete the Project as specified in this agreement (also referred to herein as the "Contract") and such shall be completed in a satisfactory manner, as reasonably determined by the City. All labor, services, equipment, materials, supplies, transportation, and incidentals shall comply with (i) all applicable local, state and federal laws, statutes, ordinances, rules and regulations, including without limitation all notice requirements thereunder, and (ii) generally accepted professional standards.
1.1. The Project consists of passenger elevator replacements, at The Driggs and Woodrow Wilson Elementary Schools located 77 Woodlawn Terrace and 235 Birch Street, respectfully, in Waterbury, Connecticut. The Project is more particularly detailed and described in the Bid Documents in Attachment A. Attachments A and B (see Section 5.1) are hereby made material provisions of this Contract.
Attachment A shall consist of the following, which are attached hereto, are acknowledged by the Contractor as having been received, or otherwise hereby incorporated by reference as noted below, and all are made a part hereof:
1.1.1 City’s ITB No. 8799 (incorporated by reference);
1.1.2 Addendum _ to ITB No. 8799 (incorporated by reference);
1.1.3 Contractor’s Price Proposal, dated _______________, consisting of one page (attached hereto);
1.1.4 Contractor’s Response with associated attachments to ITB No. 8799, dated
______, consisting of ___ pages, (incorporated by reference);
1.1.5 “City of Waterbury, ITB No. 8799, “Scope of Services” (also referred to as
“Technical Specifications”), which were provided through the link in ITB No. 8799;
1.1.6 “Site Map” with List of Drawings prepared by Friar Architecture, Inc., which were provided through the link in ITB No. 8799;
1.1.7 State of Connecticut Prevailing Wage Schedule dated May 18, 2026, and related information, consisting of 9 pages (incorporated by reference);
1.1.8 The General and Special Conditions (attached hereto);
1.1.9 Contractor’s Certificate of Insurance (incorporated by reference);
1.1.10 Contractor’s Performance Bond (incorporated by reference);
1.1.11 Contractor’s Payment Bond (incorporated by reference);
1.1.12 All amendment(s) and Change Orders issued by the City after execution of
Contract (incorporated by reference);
1.1.13 All applicable Federal, State and local statutes, regulations charter and ordinances; and
1.1.14 All applicable permits and licenses (incorporated by reference).
1.2. The entirety of Attachment A plus this executed instrument (including Attachment B) are together deemed the Contract Documents (hereinafter collectively referred to as "Contract Documents"). The City’s record copy of the Contract Documents shall control and shall be effective and binding on the Contractor. If any provision in the Contract Documents conflict with any other provision therein, the provision in the component part of the Contract Document first enumerated below shall govern over any other component part which follows it numerically:
1.2.1 All applicable Federal, State, and local laws, regulations, charter and ordinances;
1.2.2 Contract Amendment(s) and Change Orders;
1.2.3 This Contract;
1.2.4 Addendums to ITB No. 8799;
1.2.5 ITB No. 8799 including the construction documents prepared by Friar
Architecture, Inc. identified through links in Section 1.1.5 and 1.1.6 above;
1.2.6 Contractor’s Price Proposal; and
1.2.7 Contractor’s Response.
2. Representations Regarding Qualification and Accreditation. The Contractor represents that its employees are licensed to perform the scope of work set forth in this Contract. The Contractor further represents that its employees have the requisite skill, expertise and knowledge necessary to perform the scope of work required under the terms of this Contract, including any supplementary work and the City relies upon Contractor’s representations.
2.1. Representations regarding Personnel. The Contractor represents that it has, or will secure at its own expense, all personnel required to perform the services under this Contract. Such personnel shall not be employees of or have any contractual relationship with the City, unless use of City employees or of personnel having a contractual relationship with the City is approved in writing. As set forth above, all the services required hereunder shall be performed by the Contractor or under its supervision and all personnel engaged in the work shall be fully qualified and shall be authorized or permitted under state or local law to perform such services.
2.2. Representations regarding Qualifications. The Consultant hereby represents that, to the extent required by Federal, State and Local statutes, regulations, codes, ordinances, and policies, that the Consultant and/or its employees be licensed, certified, registered, or otherwise qualified, the Consultant and all employees providing services under this Contract, are in full compliance with those statutes, regulations and ordinances. Upon City request, the Consultant shall provide to the City a copy of the Consultant’s licenses, certifications, registrations, etc.
3. Responsibilities of the Contractor. The Contractor agrees to properly implement the services required in the manner herein provided. The Contractor shall, in addition to any other responsibilities set forth in this Contract and the Schedules and Attachments hereto, perform the following coincident with the performance of this Contract:
3.1. Due Diligence Obligation. The Contractor acknowledges its responsibility to examine and to be thoroughly familiar with the City’s bid document, including, but not limited to the plans, specifications, drawings and any addenda thereto.
This is the start of the file's text. The full file is on GovTribe.
Other files
| File | Type | Posted |
|---|---|---|
| ITB 8799 06032026.pdf | ||
| ITB 8799 06092026.pdf | ||
| ITB 8799 Addendum 1.pdf | ||
| Driggs_FULL SET Re-Bid.pdf | ||
| ITB 8799 06032026.pdf.crdownload | CRDOWNLOAD file | |
| ITB 8799- Wtby_Jun_8_26_solicitation_doc.pdf | ||
| Driggs_FULL SET Re-Bid.pdf.crdownload | CRDOWNLOAD file | |
| ITB 8799- Wtby_Jul_13_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .