ITB 25-45SS Technical Specifications.pdf

PDF 1 MB Posted

Attached to
Utilities Administration Building Men’s Locker Room Remodeling
Solicitation number
25-45SS
Issued by
Sarasota County, Florida

About this file

This technical specification document is for a City of Sarasota Utilities Department project involving a locker room renovation at 1750 12th Street in Sarasota, Florida. The project, designated as Project No. 23-025, encompasses a comprehensive renovation of an existing locker room, including new plumbing fixtures, interior finishes, toilet partitions, lockers, lighting, and toilet room accessories. The project will be constructed under a single prime contract with a substantial completion timeline of 120 calendar days from the Notice to Proceed, followed by a 30-day final completion period. The contract includes specific requirements for surface preparation, materials, installation, and finish work, with detailed specifications for various components such as ceramic tiling, metal lockers, toilet accessories, and painting.

The project has a structured procurement approach with specific requirements for submittals, including a detailed schedule of painting operations, color samples, and manufacturer certifications. The estimated budget and funding sources are not explicitly stated in the document. The City of Sarasota will require a performance bond, and liquidated damages of $965 per calendar day will be assessed for delays beyond the prescribed completion timeline. The specifications emphasize quality control, with requirements for surface preparation, material compatibility, and adherence to various industry standards including ASTM, OSHA, NFPA, SSPC, and NACE. The project will require precise coordination between different trades and careful attention to environmental conditions during construction.

View the file

Other files

File Type Posted
ITB 25-45SS Electronic Bid Form.xlsx XLSX spreadsheet
ITB 25-45SS Exhibit A - Required Forms.pdf PDF
ITBCON.pdf PDF
ITB 25-45SS Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prepared By:

PA AR97844

2168 Main Street Sarasota, Florida 34237 Phone (941) 917-0883 www.halldarling.com

Project Manual

City of Sarasota Utilities Department Locker Room Renovation

1750 12th Street Sarasota, Florida 34237

Project No. 23-025

City of Sarasota Utilities Department 007300 - 1 Locker Room Renovation Supplementary Conditions

SECTION 007300 - SUPPLEMENTARY CONDITIONS

PART 1 - GENERAL

1.1 PROJECT SUPPLEMENTAL GENERAL CONDITIONS

A. ORDER OF PRECEDENTS

1. If a conflict arises between these Terms and Conditions, the following ORDER

OF PRECEDENTS will apply:

a. Florida State Law as applied to Municipal Purchasing in accordance with

Title XIX, “Public Business”, Chapter 287 “Procurement of Personal Property and Services”

b. City of Sarasota Procurement Code

c. Special Conditions and Supplemental Instructions

d. Detailed Scope of Work

e. Solicitation specific Terms and Conditions (RFP, Bid, Construction, etc.)

f. These Terms and Conditions

B. See City of Sarasota General Terms and Conditions (Most recent version) for requirements.

C. See City of Sarasota Construction Terms and Conditions (Most recent version) for requirements.

D. This “Project Supplemental General Conditions” is intended as a project specific supplement to AIA Document A201-2017 “General Conditions”, “Supplemental General Conditions” and the “General Requirements”. Where conflicting information or instructions exist between any of these documents, the information or instructions in this Project Supplemental General Conditions shall prevail.

E. Liquidated Damages: Liquidated damages will be assessed to the contractor/vendor for each consecutive calendar day completion of the project or work is delayed. Liquidated damage is specified in the scope of work or specification. The Contractor shall pay to the City the sum of Nine Hundred Sixty Five Dollars ($965.00) per calendar day liquidated damages for each and every day’s delay over and above the number of calendar days prescribed for completing the work.

F. Attorney's Fees: Should it become necessary for the City to bring any action against the successful bidder to enforce any of the covenants, provisions or conditions of the agreement, the successful bidder will pay all costs attendant thereto, including reasonable attorney's fees to the attorney.

G. Construction Durations:

1. Substantial Completion: The number of days to substantially complete this project will be 120 calendar days from Notice to Proceed.

2. Final Completion: 30 days after Notice of Substantial Completion.

City of Sarasota Utilities Department 007300 - 2

H. Performance Bond: The Owner will require a performance bond. See City of Sarasota Construction Terms and Conditions (Most recent version) for requirements.

I. AIA A201 GENERAL CONDITIONS OF CONTRACT FOR CONSTRUCTION

1. AIA A201 2017 “General Condition of the Contract for Construction” shall be considered an incorporated portion of the Contract and its provisions, unless specifically indicated to be omitted.

J. SUPPLEMENTARY CONDITIONS

1. Where any Article of AIA A201 2017 “General Condition of the Contract for Construction” is supplemented hereby, either by modification, alteration, removal or addition.

2. Remaining Articles or partial Articles shall remain in effect.

K. § 1.1 BASIC DEFINITIONS

1. Add “§ 1.1.9 The term “product” shall include all material, systems and equipment.”

2. Add “§ 1.1.10 The term “furnish” is considered a contraction of, “supply and deliver to the job site all materials and/or equipment so specified,” unless specifically noted otherwise.”

3. Add “§ 1.1.11 The term “provide” is considered a contraction of, “furnish, install, connect completely, test and place in operation,” unless specifically noted otherwise.”

L. § 1.2 CORRELATION AND INTENT OF THE CONTRACT DOCUMENTS

1. Add “§ 1.2.4 Certain portions of the specifications are written in condensed outline. Naming of an article or operation shall have the effect of stating, ”Contractor shall furnish, install and complete…” said operation or Articles unless it is further clarified in the context which it appears.”

2. Add “§ 1.2.5 When reference is made to specifications or standards of a manufacturer, trade association, governmental agency, reference standard or similar source (ie ASTM, ANSI, ASA, AISC, AVI, etc.) such is made part of this Project Manual, having the force and effect as though included herein, and upon entering into the Contract the Contractor acknowledges his familiarity with those pertaining to the Work.”

3. Add ““§ 1.2.6 Verify coordination occurs across all Contract Documents. Details indicated at various scales shall require components for a complete and functioning component / system, whether or not they are indicated at different scales or within different portions of the Contract Documents.”

M. § 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY

CONTRACTOR

1. Add “§ 3.2.5 If the Contractor, during the progress of the Work, discovers discrepancies between the Drawings and the Specifications, errors and/or omissions, or discrepancies between the physical condition of the Work and the Contract Documents, the Contractor shall immediately notify the Architect in

City of Sarasota Utilities Department 007300 - 3 writing, who shall promptly adjust the same. Whether or not an error is believed to exist, deviations from the Contract Documents shall be made only after direction in writing is obtained from the Architect. Work performed after such discovery without review and direction by the Architect shall be at the Contractor’s risk and expense.”

2. Add “§ 3.2.6 The Contractor shall:

a. Be responsible for existing and proposed measurements;

b. Check the contract documents;

c. Report discrepancies to the Architect;

d. Furnish correct dimensions to all trades; and,

e. Furnish construction lines and dimensions required in the performance of the Work. Scaled dimensions are not acceptable.”

3. Add “§ 3.2.7 Whenever the Drawings indicate existing conditions or other construction not required as part of the Contract, it is understood it is shown as a matter of information, and the Owner assumes no responsibility for its accuracy.

The Contractor shall make themselves familiar with conditions affecting the nature and manner of conducting the work.”

END OF SECTION 007300

City of Sarasota Utilities Department 011000 - 1 Locker Room Renovation Summary

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work by Owner.

4. Access to site.

5. Coordination with occupants.

6. Work restrictions.

7. Specification and Drawing conventions.

8. Miscellaneous provisions.

B. City of Sarasota Requirements:

1. See City of Sarasota General Terms and Conditions (Most recent version) for requirements.

2. See City of Sarasota Construction Terms and Conditions (Most recent version) for requirements.

C. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: Project No. 23-025

City of Sarasota Utilities Department Locker Room Renovation

1750 12th Street Sarasota, Florida 34237

City of Sarasota Utilities Department 011000 - 2

B. Owner: City of Sarasota.

1. Owner's Representative: Georges Nicolas, PE, Engineering Manager 1750 12th Street Sarasota, Florida 34237 941.263.6243 Georges.Nicolas@sarasotafl.gov

Architect: Hall Darling Design Studio, PA 2168 Main Street Sarasota, Florida 34237 941.917.0883

C. Architect's Consultants: Architect has retained the following design professionals who have prepared designated portions of the Contract Documents:

1. MEP Engineer: Genesis Engineering Group, LLC 2601 Cattlemen Rd., Suite 501 Sarasota, Florida 34232

D. Web-Based Project Software: Project software administered by Contractor will be used for purposes of managing communication and documents during the construction stage.

1. See Section 013100 "Project Management and Coordination." for requirements for administering and using web-based Project software.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Renovation to existing locker room. Work to include but not limited to new plumbing fixtures, interior finishes, toilet partitions, lockers, lighting, and toilet room accessories.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.5 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Use of Site: Limit use of Project site to Work in areas as directed by the Architect during the Preconstruction Meeting. Do not disturb portions of Project site beyond areas in which the Work is indicated.

City of Sarasota Utilities Department 011000 - 3

1. Limits: Confine construction operations to area designated by the Owner.

2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances and adjacent properties clear and available to those Owners, those Owners’ employees, students and members, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

3. Schedule deliveries to minimize use of driveways and entrances by construction operations.

4. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.6 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site during entire construction period.

Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. Construction Hours. Work hours will be in accordance with City of Sarasota Ordinance 03-4416 unless otherwise stated in the scope of work or technical specifications. Construction, drilling, repair, alteration, demolition, land clearing or landfilling operations between the hours of 6:00 a.m. and 9:00 p.m. on weekdays or between 9:00 a.m. and 9:00 p.m. on weekends or holidays for which all required permits have been issued, provided that the equipment involved is operated in accord with the manufacturer's specifications and with all manufacturer's sound-reducing equipment in use and in proper operating condition

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

City of Sarasota Utilities Department 011000 - 4

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than two days in advance of proposed disruptive operations.

2. Obtain Owner's written permission before proceeding with disruptive operations.

E. Restricted Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

City of Sarasota Utilities Department 012500 - 1 Locker Room Renovation Substitution Procedures

SECTION 012500012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.

1.4 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.

b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

City of Sarasota Utilities Department 012500 - 2

c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.

h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for

Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

2. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

City of Sarasota Utilities Department 012500 - 3

1.6 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

1.7 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the

Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within ten (10) business days prior to the bid opening date. Requests received after that time may be considered or rejected at discretion of the Owner and Architect.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract Documents.

City of Sarasota Utilities Department 012500 - 4

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the

Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

k. Substitutions will only be approved if determined by the Owner to be an Approved Alternate to the prescribe specifications.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012500012500

City of Sarasota Utilities Department 012600 - 1 Locker Room Renovation Contract Modification Procedures

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

B. See City of Sarasota Construction Terms and Conditions (Most recent version) for additional requirements. If conflicting information is discovered between this specification section and City requirements, City requirements take precedent.

C. Related Requirements:

1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.

1.3 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710 or web based project software.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

City of Sarasota Utilities Department 012600 - 2

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use forms acceptable to Architect.

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Proposal Request Form: Use form acceptable to Architect.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701 or form provided as part of web-based Project management software.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. The City may, by field directive, authorize minor variations from the requirements of the contract documents, which do not involve an adjustment in the contract price or the contract time and are consistent with the overall intent of the contract documents. Supplemental agreements, in the form of "change orders" shall be used to clarify the plans and specifications, to provide for unforeseen work or alterations in plans, to change the limits of construction to meet field conditions, to provide a safe and functional connection to an existing

City of Sarasota Utilities Department 012600 - 3 facility, to make the project functionally operational in accordance with the intent of the original contract, or to adjust the contract price or the contract time requirements. The City of Sarasota will not pay more than a total of 10% on markup and overhead. Any supplemental agreement shall be approved by the City Manager, contractor and the architect/engineer, if applicable, prior to the commencement of the modified work. The City Manager may only approve an adjustment to the contract price that does not exceed 10% of the contract price or $200,000.00, whichever is less in accordance with Ordinance 03-4440.

B. The City reserves the right to make, at any time prior to or during the progress of the work, increases or decreases in the quantities of work as may be found necessary or desirable by the City. Compensation for changes in quantities shall be at the bid unit price for the specific item of work with no additional charges allowed for the change in quantity. All unit prices for items of work in the original contract shall be considered all-inclusive of expenses necessary to accomplish the work regardless of the unit of measure (e.g. LS, LF, CY, SY, TN, etc.)

including but not limited to:

1. Material

2. Delivery

3. Direct Labor

4. Taxes

5. Rental rates

6. Fringe Benefits

7. Overhead

8. Profit

9. Markup

C. A change in quantities whether greater than or lower than the original bid quantity shall be treated as if the new quantity was part of the original quantity of work with respect to unit value. Upon approval of changed quantities the quantities shall be adjusted on the schedule of values to reflect the new total quantity of each item of work. Each proposal for change order shall list both the reduction in quantity of deleted work and increased quantity of added work. The City of Sarasota will not pay more than a total of 10% on markup and overhead when establishing a negotiated fee for items not list by unit price.

Surety and other bonds, when required, are premiums applied to the total contract amount. Adjustments and allowances for increased bond costs will only be considered on the net increase to the total contract amount after consideration of both quantity reductions, quantity increase and other work price adjustments.

D. Changes in contract time will only be considered for documented weather impacts, additional work directed by the City, reductions in work directed by the City, stoppage of work when directed by the City or other causes of delay not attributable to the contractor. Delays by others, such as utility companies, may not necessarily be compensated by the City and the contractor may need to seek compensation from the third party for the delay.

E. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714 or form provided as part of web-based Project management

City of Sarasota Utilities Department 012600 - 4 software. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

F. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

City of Sarasota Utilities Department 012900 - 1 Locker Room Renovation Payment Procedures

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. See City of Sarasota Construction Terms and Conditions (Most recent version) for additional requirements. If conflicting information is discovered between this specification section and City requirements, City requirements take precedent.

C. Related Requirements:

1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

2. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.

1.3 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.

1.4 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.

1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Architect at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

City of Sarasota Utilities Department 012900 - 2

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Name of Architect.

c. Architect's Project number.

d. Contractor's name and address.

e. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703.

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.

4. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site.

5. Overhead Costs: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.

6. Schedule of Values Revisions: Revise the schedule of values when Change Orders or Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.

1.5 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and Construction Manager and paid for by Owner.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

1. Submit draft copy of Application for Payment seven days prior to due date for review by Architect.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.

1. Other Application for Payment forms proposed by the Contractor shall be acceptable to Architect and Owner. Submit forms for approval with initial submittal of schedule of values.

City of Sarasota Utilities Department 012900 - 3

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.

b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.

c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.

F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

City of Sarasota Utilities Department 012900 - 4

4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Submittal schedule (preliminary if not final).

5. List of Contractor's staff assignments.

6. List of Contractor's principal consultants.

7. Copies of building permits.

8. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

9. Initial progress report.

10. Report of preconstruction conference.

11. Certificates of insurance and insurance policies.

12. Performance and payment bonds.

13. Data needed to acquire Owner's insurance.

I. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

J. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706.

5. AIA Document G706A.

6. AIA Document G707.

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

9. Final liquidated damages settlement statement.

PART 2 - PRODUCTS (Not Used)

City of Sarasota Utilities Department 012900 - 5

END OF SECTION 012900

City of Sarasota Utilities Department 012900 - 6

City of Sarasota Utilities Department 013100 - 1 Locker Room Renovation Project Management and Coordination

SECTION 013100013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Project meetings.

B. See City of Sarasota Construction Terms and Conditions (Most recent version) for additional requirements. If conflicting information is discovered between this specification section and City requirements, City requirements take precedent.

C. Related Requirements:

1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.

2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.

1.3 DEFINITIONS

A. RFI: Request for Information. Request from Owner, Construction Manager, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

City of Sarasota Utilities Department 013100 - 2

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1. Post copies of list in project meeting room, in temporary field office, in web-based Project software directory, and in prominent location. Keep list current at all times.

1.5 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

City of Sarasota Utilities Department 013100 - 3

1.6 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Architect and Construction Manager.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product

Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Architect. Identify each page of any attachments with the RFI number and sequential page number.

1. Attachments shall be electronic files in PDF format.

D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven working days for Architect's response for each RFI. RFIs received by Architect or Construction Manager after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

City of Sarasota Utilities Department 013100 - 4

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect or Construction Manager of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect and Construction Manager in writing within 10 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Use software log that is part of web-based Project software. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's and Construction Manager's response was received.

8. Identification of related Minor Change in the Work, Construction Change

Directive, and Proposal Request, as appropriate.

F. On receipt of Architect's and Construction Manager's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect and Construction Manager within seven days if Contractor disagrees with response.

1.7 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Web-Based Project Software: Provide, administer, and use web-based Project software site for purposes of hosting and managing Project communication and documentation until Final Completion.

1. Web-based Project software site includes, at a minimum, the following features:

a. Compilation of Project data, including Contractor, subcontractors, Architect, architect's consultants, Owner, and other entities involved in Project.

Include names of individuals and contact information.

b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.

City of Sarasota Utilities Department 013100 - 5

c. Document workflow planning, allowing customization of workflow between project entities.

d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor Changes in the Work, Construction Change Directives, and Change Orders.

e. Track status of each Project communication in real time, and log time and date when responses are provided.

f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.

g. Processing and tracking of payment applications.

h. Processing and tracking of contract modifications.

i. Creating and distributing meeting minutes.

j. Document management for Drawings, Specifications, and coordination drawings, including revision control.

k. Management of construction progress photographs.

l. Mobile device compatibility, including smartphones and tablets.

2. Provide up to seven web-based Project software user licenses for use of Owner, Architect, and Architect's consultants.

3. At completion of Project, provide digital archive in format that is readable by common desktop…