ITB 22-021-PW E 40th Ave Storage Tanks - Construction-Volume 2.pdf

PDF 5 MB Posted

Attached to
EWEB ITB 22-021-PW E 40TH AVE STORAGE TANKS - CONSTRUCTION
Solicitation number
S-P00140-00002232
Issued by
Lane County, Oregon

About this file

This document is an Invitation to Bid (ITB) issued by the Eugene Water & Electric Board (EWEB) for the construction of two 7.5-million-gallon (MG) AWWA D110 storage tanks, associated yard piping, and site work at the EWEB owned E. 40th Ave Storage Tank site in Eugene, Oregon. Bidders must meet minimum contractor and specialty subcontractor qualifications as defined in the bid package. The project involves mass excavation, including rock blasting and removal, construction of the two 7.5 MG prestressed concrete tanks, site preparation, tank construction, testing and start-up.

The contract will be awarded on a unit price basis. The Contractor shall be responsible for the cost of all testing as specified, including additional testing if work or materials do not meet the project specifications. EWEB will obtain and pay for certain permits, while the Contractor is responsible for obtaining and paying for other permits. The project is funded by EWEB, and there are no set-asides or incumbent contractors identified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

E. 40TH AVENUE 7.5 MG STORAGE

TANKS

FOR

Eugene Water & Electric Board Volume 2 of 3

FEBRUARY 2022

20-2888 MSA-OR 5-09

TECHNICAL SPECIFICATIONS AND DRAWINGS

E. 40th AVENUE 7.5 MG STORAGE TANKS PROJECT

EUGENE WATER & ELECTRIC BOARD

FEBRUARY 2022

MURRAYSMITH, INC.

888 SW 5th Avenue

Suite #1170 Portland, OR 97204

(503) 225-9010

EUGENE WATER & ELECTRIC BOARD, OREGON

TECHNICAL SPECIFICATIONS

E. 40TH AVENUE 7.5 MG STORAGE TANKS PROJECT

PROFESSIONAL OF RECORD CERTIFICATION(s):

Travis McFeron – Peterson Structural

Engineering, Inc.

I declare the Technical Specification(s) listed below are applicable to the design for the subject project for the Eugene Water & Electric Board (EWEB). Technical Specifications were prepared by me or under my supervision.

Section(s): 031510, 031512, 031520, 032100, 033000, 033010, 033020, 036000, 036410, 036423, 331610

Date Signed: __________________

12/31/22

02/22/2022

EWEB E 40th Ave 7.5 MG Tanks Summary of Work 20-2888 01 10 00 - 1

SECTION 01 10 00 - SUMMARY OF WORK

PART 1 GENERAL

This Summary of Work supplements and amplifies certain sections of the General Conditions and Supplementary General Conditions. The General Conditions and Supplementary General Conditions shall apply except as modified herein. These Special Provisions and additional technical specifications may contain occasional requirements not pertinent to the project. However, these specifications shall apply in all particulars insofar as they are applicable to this project.

1.1 APPLICABLE STANDARD SPECIFICATIONS AND PLANS

Eugene Water & Electric Board, Water Distribution Design and Construction Standards, (including all revisions at date of bid opening), apply except as may be modified herein. In the case of discrepancy, unless noted otherwise herein, the more restrictive provisions shall apply.

1.2 SCOPE OF WORK

The work to be performed under these specifications and drawings consists of mass excavation to include rock blasting and removal in the extents shown on the Drawings and associated work.

The above general outline of principal features of the work does not in any way limit the responsibility of the CONTRACTOR(s) to perform all work and furnish all equipment, labor and materials required by the specifications and drawings. The drawings and specifications shall be considered and used together. Anything appearing as a requirement of either shall be accepted as applicable to both even though not so stated therein or shown.

No attempt has been made in these specifications or drawings to segregate work covered by any trade or subcontract under one specification. Such segregation and establishment of subcontract limits will be solely a matter of specific agreement between the CONTRACTOR and its subcontractors and shall not be based upon any inclusion, segregation, or arrangement in or of these specifications.

1.3 CODE REQUIREMENTS

All work shall be done in strict compliance with the requirements of:

A. International Building Code B. Uniform Mechanical Code C. Uniform Plumbing Code D. National Electric Code E. National Electric Safety Code F. Oregon State Department of Labor and Industries

20-2888 01 10 00 - 2

G. City of Eugene Erosion Control Practices

In case of disagreement between codes or these specifications, the more restrictive shall prevail.

1.4 COORDINATION WITH OTHER CONTRACTORS AND WITH OWNER

Certain work within this contract may require connection to and coordination with the work of other contractors and OWNER. The CONTRACTOR under these specifications shall cooperate fully with all other contractors and OWNER and carefully fit its own ork to such other work as may be directed by the ENGINEER. The CONTRACTOR shall not commit or permit any act to be committed which will interfere with the performance of work by any other contractor or the OWNER.

1.5 ACCESS TO WORK

Access to the work shall be provided as may be required by the OWNER or its representatives, and all authorized representatives of the state and federal governments and any other agencies having jurisdiction over any phase of the work, for inspection of the progress of the work, the methods of construction or any other required purposes.

1.6 PERMITS AND LICENSES

Unless provided for otherwise in these contract documents, all permits, licenses and fees shall be obtained by the CONTRACTOR and all costs shall be borne by the CONTRACTOR.

CONTRACTOR shall pay all plan check fees and other fees necessary to obtain permits and shall accommodate special inspections required thereof. CONTRACTOR shall be responsible for compliance with all permit provisions and shall accommodate all special inspections required thereof, all at no additional expense to the OWNER beyond prices as bid.

The following permits will be obtained and fees paid by the OWNER:

• City of Eugene, 1200-CN Erosion Control Permit.

• City of Eugene, Building/Grading Permit.

1.7 SITE INVESTIGATION AND PHYSICAL DATA

The CONTRACTOR acknowledges that it is satisfied as to the nature and location of the work and the general and local conditions, including but not limited to those bearing upon transportation, disposal, handling and storage of materials, availability of water, roads, groundwater, access to the sites, coordination with other contractors, and conflicts with pipelines, structures and other contractors. Information and data furnished or referred to herein is furnished for information only. Any failure by the CONTRACTOR to become acquainted with the available information and existing conditions will not be a basis for relief from successfully performing the work and will not constitute justification for additional compensation.

20-2888 01 10 00 - 3

The CONTRACTOR shall verify the locations and elevations of existing pipelines, structures, grades and utilities, prior to construction. The OWNER assumes no responsibility for any conclusions or interpretations made by the CONTRACTOR based on the information made available.

1.8 TEMPORARY UTILITIES FOR CONSTRUCTION PURPOSES

The CONTRACTOR shall make all arrangements necessary to provide all temporary utilities for construction purposes and shall pay all costs associated those temporary utilities. Water for construction purposes will be furnished by the OWNER at no cost. The CONTRACTOR shall furnish all valves, hoses, connections and other devices as necessary to obtain enough water for construction and for filling and testing of water lines as required. Fire hydrant use is allowed only by permission of the utility owner. Backflow protection is required on all connections to potable water systems.

1.9 FIELD SERVICE BY MANUFACTURER'S REPRESENTATIVE

The CONTRACTOR shall furnish the services of a manufacturer's or material supplier’s representative for all major equipment and materials furnished by the CONTRACTOR or OWNER under this contract, to check, place in operation and test the installation, and train operating personnel. The manufacturer's representative shall be qualified and authorized to perform repairs and maintenance on the equipment. The above gives a general scope of the services desired from the manufacturer's representative. It will be the responsibility of the CONTRACTOR and the equipment manufacturer to determine detailed requirements. Costs for services of the manufacturer's representative shall be included in the proposal of the CONTRACTOR. The operator training mentioned above shall include enough time during the CONTRACTOR’s operation and testing period to fully explain to the operating personnel the features of the equipment and maintenance thereof.

1.10 CONSTRUCTION WITHIN PUBLIC RIGHTS-OF-WAY

When the work contemplated is wholly or partly within the right-of-way of a public agency such as a city, county or state, the OWNER will obtain from these agencies any right-of-way and street opening permits and all other necessary permit(s) required for the work. The CONTRACTOR shall abide by all regulations and conditions stipulated in the permit(s). Such conditions and requirements are hereby made a part of these specifications, as fully and completely as though the same were fully set forth herein. The CONTRACTOR shall examine the permit(s) granted to the OWNER by any city, county, state and federal agencies. Failure to do so will not relieve the CONTRACTOR from compliance with the requirements stated therein.

The CONTRACTOR shall obtain all construction permits and pay all fees or charges and furnish any bonds and insurance coverages as necessary to insure that all requirements of the city, county, state or federal agencies will be observed and the roadway and ditches are restored to their original condition or one equally satisfactory. A copy of all permits shall be

20-2888 01 10 00 - 4 kept on the work site for use of the ENGINEER.

1.11 CONSTRUCTION WITHIN PRIVATE EASEMENTS

When portions of the work contemplated are within easements held by the OWNER on private property, the CONTRACTOR shall ascertain for itself to what extent the width, status, and special conditions attached to easements may have on its operations and all costs resulting therefrom shall be included and absorbed in the unit prices of the CONTRACTOR’s bid. CONTRACTOR shall coordinate with private property owners and businesses if required.

Landscaping, surface restoration and fence restoration shall be completed within 24 hours following piping and conduit installation and other construction work. Temporary fencing shall be provided continuously until such private fencing is properly restored.

The CONTRACTOR’s attention is directed to Section 00700, General Conditions, part G, regarding safety and the protection of property. Certain portions of this project require working near existing structures and property within private easements. It is the CONTRACTOR’S responsibility to conduct its operations and limit the size of equipment used in such a manner to prevent damage to existing property from excessive vibration or from other direct or indirect CONTRACTOR operations. The cost associated with repairing or replacing property that is damaged by the CONTRACTOR’s operations shall be the responsibility of the CONTRACTOR, in accordance with the General Conditions.

1.12 PRIVATE ROADS AND DRIVEWAYS

Bridges at entrances to business properties where vehicular traffic is necessary shall be provided and maintained. Bridges shall be adequate in width and strength for the service required. No private road or driveway may be closed without approval of the ENGINEER unless written authority has been given by the owner whose property has been affected.

Driveways shall be left open and ready for use at the end of the work shift. All expenses involved in providing for construction, maintenance, and use of private roads or driveways, shall be borne by the CONTRACTOR and the amount thereof absorbed in the unit prices of the CONTRACTOR’s bid.

1.13 TRAFFIC CONTROL AND PROTECTION

The CONTRACTOR shall maintain traffic control and protection in the work areas 24 hours per day. Traffic control shall conform to the standards set forth in the "Oregon Manual on Uniform Traffic Control Devices" issued by the Oregon Department of Transportation.

The CONTRACTOR shall conduct its operations to keep one lane of traffic open for public and private access at all times on City, County and Public streets, roads and highways. If required by the State, the CONTRACTOR shall conduct its operations to keep both directions of traffic open on State Highways. Permits obtained for the project may have more stringent requirements than noted in this section.

20-2888 01 10 00 - 5

Prior to beginning construction, the CONTRACTOR shall submit a detailed street closure and traffic control plan to the ENGINEER and City of Eugene for approval. As construction proceeds, the CONTRACTOR shall notify the ENGINEER as to the status of street closures and detours.

On streets where traffic is heavy, the ENGINEER may require the construction of two-way bridges of adequate design. These bridges shall be provided with guard rails and shall be well lighted at all times. Detours as required by the ENGINEER shall be surfaced with gravel or crushed rock and maintained in good condition. Detours for pedestrians shall not exceed one block in length, and foot bridges over the trenches shall be provided with adequate handrails.

All work shall be carried on with due regard for safety to the public. Open trenches shall be provided with barricades of a type that can be seen at a reasonable distance, and at night they shall be distinctly indicated by adequately placed lights.

1.14 MATERIALS AND COMPACTION TESTING

The OWNER shall provide the services of a licensed, independent agency to perform materials and compaction testing for this project. Materials and compaction tests will be required to show that specified densities of compacted backfill and asphaltic concrete surfacing are being achieved by the CONTRACTOR’s compaction methods. The CONTRACTOR shall provide the OWNER’S REPRESENTATIVE with copies of recent Proctor tests for the backfill and paving material in addition to copies of compaction tests performed in the field.

After the OWNER’S REPRESENTATIVE is satisfied that the CONTRACTOR’s method of compaction consistently meets specified compaction requirements, the testing frequency may be reduced. The OWNER’S REPRESENTATIVE may direct testing at a higher frequency upon failure to obtain specified densities or if the CONTRACTOR changes compaction equipment or methods of compaction. All test locations shall be determined by the

OWNER’S REPRESENTATIVE.

The CONTRACTOR shall be responsible for scheduling and coordinating field services for the materials and compaction testing.

1.15 DECHLORINATION AND DISPOSAL OF CHLORINATED WATER

Any discharge of chlorinated water shall either be through an approved connection to a public sanitary sewer system or shall include de-chlorination to limits acceptable by the Oregon State Department of Environmental Quality (DEQ) for discharge into the existing storm drainage system. No chlorinated water shall be discharged into the storm drainage system prior to approved de-chlorination treatment.

1.16 LIMITS OF THE WORK AND STORAGE OF SPOILS

The limits of the site which may be used for construction, storage, materials handling, 20-2888 01 10 00 - 6 parking of vehicles and other operations related to the project include the project site within the construction fencing as shown on the drawings. The limits of work also include rights of access obtained by the CONTRACTOR, subject to all public laws and regulations and rights of access by utility companies and other holders of easement rights.

1.17 EXISTING WATER SYSTEM SHUTDOWN

If the project involves the need to shut down an existing water system, the CONTRACTOR shall coordinate the work to insure a minimum of shutdown time. The CONTRACTOR shall submit a written shutdown schedule to the ENGINEER for approval. The CONTRACTOR shall provide 72-hour notice preceding each shutdown. See Section 33 12 13, Water Service Connections, for additional requirements.

1.18 FIELD CHANGES, ALIGNMENT, AND GRADE

Changes of alignment and grade shall be made during the course of work in order to avoid interference with unforeseen obstructions. The CONTRACTOR shall locate existing utilities to be crossed, by potholing ahead of the pipe installation, of sufficient distance to avoid conflicts through pipe joint deflection if possible. All costs for minor field changes of alignment and grade shall be borne by the CONTRACTOR. The ENGINEER will endeavor to make prompt decisions on such matters. CONTRACTOR shall anticipate a minimum of 72 hours for any decision requiring significant piping change.

1.19 TESTING AND OPERATION OF FACILITIES

It is the intent of the OWNER to have a complete and operable facility. All the work under this contract will be fully tested and inspected in accordance with the specifications. Upon completion of the work, the CONTRACTOR shall operate the completed facilities as required to test the equipment under the direction of the ENGINEER. During this period of operation by the CONTRACTOR, the new facilities will be tested thoroughly to determine their acceptance.

1.20 PROTECTION OF EXISTING STRUCTURES AND WORK

The CONTRACTOR must take all precautions and measures necessary to protect all existing structures and work. Any damage to existing structures and work shall be repaired by removing the damaged structure or work, replacing the work and restoring to original condition satisfactory to the ENGINEER.

1.21 SALVAGE AND DEBRIS

Unless otherwise indicated on the drawings or in the specifications, all castings, pipe, equipment, demolition debris, spoil or any other discarded material or equipment shall become the property of the CONTRACTOR and shall be disposed of in a manner compliant with applicable Federal, State, and local laws and regulations governing disposal of such waste products. No burning of debris or any other discarded material will be permitted.

20-2888 01 10 00 - 7

1.22 SAFETY STANDARDS AND ACCIDENT PREVENTION

The CONTRACTOR shall be solely and completely responsible for conditions of the job site, including safety of all persons and property during performance of the work. This requirement shall apply continuously and not be limited to normal working hours. The required and/or implied duty of the ENGINEER to conduct construction review of the CONTRACTOR's performance does not, and is not intended to, include review of the adequacy of the CONTRACTOR's safety measures in, on, or near the construction site.

The CONTRACTOR shall comply with the safety standards provisions of applicable laws and building and construction codes. The CONTRACTOR shall exercise every precaution at all times for the prevention of accidents and protection of persons, including employees, and property. During the execution of the work the CONTRACTOR shall provide and maintain all guards, railing, lights, warnings, and other protective devices which are required by law or which are reasonably necessary for the protection of persons and property from injury or damage.

1.23 PUBLIC SAFETY AND CONVENIENCE

General Rule: The CONTRACTOR shall ensure the safety of the public during its performance of the Work and shall minimize any public inconvenience in addition to any other requirement imposed by law. These duties include, but are not limited to, the matters listed below.

Access: The CONTRACTOR shall not unreasonably restrict access to public facilities, commercial property, fire hydrants, residential property, and other areas where the public can be expected to be present, such as sidewalks and streets without first obtaining approval of the OWNER. Driveways shall be closed only with the approval of the OWNER or after obtaining specific permission from the property owner or owners. In addition, the CONTRACTOR shall not obstruct or interfere with travel over any public street or sidewalk without approval of the OWNER.

Public Transit: The CONTRACTOR shall not interfere with the normal operation of any public transit vehicles unless otherwise authorized.

Work Site: The CONTRACTOR shall keep the Project site safe in compliance with applicable law. Safety includes, but is not limited to: 1) providing an approved type of secured and adequate barricades or fences that are easily visible from a reasonable distance around open excavations; 2) closing up or covering with steel plates all open excavations at the end of each Working Day in all street areas and in all other areas when it is reasonably required for public safety; 3) marking all open work and obstructions by lights at night; 4) installing and maintaining all necessary signs, lights, flares, barricades, railings, runways, stairs, bridges, and facilities; 5) observing any and all safety instructions received from the OWNER; and 6) following all laws and regulations concerning worker and public safety. In the event that the law requires greater safety obligations than that imposed by the OWNER, the CONTRACTOR

20-2888 01 10 00 - 8 shall comply with the law.

Emergency: Emergency vehicles, including but not limited to police, fire, and disaster units shall be provided access to the work site at all times.

Cleanliness: The CONTRACTOR shall, on a continuing basis, keep the surfaces of all public and private roadways, sidewalks, and other pathways free of dirt, mud, cold plane grindings, and other matters that the CONTRACTOR may place upon the road. The cost of performing such work shall be included in the CONTRACTOR’s Bid and no additional payment will be made for performing this task.

Parking: The CONTRACTOR shall make any necessary contacts with all applicable governmental bodies to arrange for the removal of parked automobiles, vehicles and other obstructions if they would interfere with the performance of the CONTRACTOR’S work.

Accidents: The CONTRACTOR’S Project Manager or superintendent shall be in charge of accident prevention. CONTRACTOR shall take all actions necessary to prevent damage, injury and loss to persons and property as a result of accidents.

Project Health and Safety Plan: CONTRACTOR shall develop, publish, and implement an overall Project Health and Safety Program for the Project. This Program shall conform to all applicable codes. Contractor shall submit the written Safety Program to the OWNER within 15 days after the receipt of the written Notice to Proceed. The Plan shall be assembled to address project specific health and safety issues to both the public and on-site personnel.

The plan shall include the following items when they apply:

▪ Employee Orientation ▪ Hazardous Materials

▪ Safety Inspections ▪ Hazardous Communications Program

▪ Instruction and Training ▪ Job Hazard Analysis

▪ Accident Reporting ▪ First Aid/Medical Facilities

▪ Signs and Barricades ▪ Personal Protective Equipment

▪ Fire Prevention and Protection ▪ Confined Space Entry Plan

▪ Welding, Cutting, and Burning ▪ Shoring Plan

▪ Painting and Surface Treatment ▪ Fall Protection Plan

▪ Electricity ▪ Emergency Action Plan

▪ Machinery and Mechanized Equipment ▪ Housekeeping

▪ Excavations ▪ Safety Training Requirements and Certification

▪ Sanitation ▪ Pedestrian Access Around Work Site During Construction and After Hours

▪ Chlorine Safety

20-2888 01 10 00 - 9

If the project requires other health and safety issues to be addressed, they too shall be included in the Project Health and Safety Plan. The Program shall subsequently be distributed to and implemented by the CONTRACTOR's personnel as well as its Subcontractors and Suppliers. CONTRACTOR shall fully implement and comply with the Safety Program and shall submit to the OWNER a letter signed by CONTRACTOR'S owner/president affirming such implementation and compliance within 15 days after on-site work has started. CONTRACTOR shall notify the OWNER when safety meeting will be held so that Owner’s personnel may attend. A copy of the approved Health and Safety Plan must be maintained on-site at all times during the life of the Project.

The OWNER has no responsibility for Work site safety. Work site safety is the responsibility of the CONTRACTOR. The CONTRACTOR is required to have a competent person on site at all times during construction activities.

1.24 SANITARY FACILITIES

The CONTRACTOR shall provide and maintain sanitary facilities for its employees and its subcontractors’ employees that will comply with the regulations of the local and State Departments of Health and as directed by the ENGINEER.

1.25 STREET CLEANUP

The CONTRACTOR shall clean daily all dirt, gravel, construction debris, and other foreign material resulting from its operations from all streets and roads.

1.26 VEHICLE PARKING

The vehicles of the CONTRACTOR’s and subcontractors’ employees shall be parked in accordance with local parking ordinances. The project site should be used for parking and material storage. Patterson Street shall not be used for parking or stockpiling.

1.27 PROTECTION OF WATER QUALITY

The work to be performed may involve connections to an existing potable water system. If such work is included in the project, the CONTRACTOR shall take such precautions as are necessary or as may be required to prevent the contamination of the water. Such contamination may include but shall not be limited to deleterious chemicals such as fuel, cleaning agents, paint, demolition and construction debris, sandblasting residue, etc. In the event contamination does occur, the CONTRACTOR shall, at its own expense, perform such work as may be necessary to repair any damage or to clean the affected areas of the water mains to a condition satisfactory to the ENGINEER.

1.28 RECORD DRAWINGS

CONTRACTOR shall maintain at the site one set of specifications, full size drawings, shop

20-2888 01 10 00 - 10 drawings, equipment drawings, and supplemental drawings which shall be corrected as the work progresses to show all changes made. Drawings shall be available for inspection by the ENGINEER. Upon completion of the contract and prior to final payment, specifications and drawings shall be turned over to the ENGINEER.

The CONTRACTOR shall conduct a post-construction survey of all improvements to include valve cover, valve nuts, manhole rim, manhole inverts, etc, and deliver survey information in a CAD (.dwg file) format to the ENGINEER. ENGINEER will prepare final record drawings.

1.29 "OR EQUAL" CLAUSE

To establish a basis of quality, certain processes, types of machinery and equipment or kinds of material may be specified on the drawings or herein by designating a manufacturer's name and referring to its brand or product designation. It is not the intent of these specifications to exclude other processes, equipment or materials of a type and quality equal to those designated. When a manufacturer's name, brand, or item designation is given, it shall be understood that the words "or equal" follow such name or designation, whether in fact they do so or not. If the CONTRACTOR desires to furnish items of equipment by manufacturers other than those specified, they shall secure the approval of the ENGINEER prior to placing a purchase order.

No extras will be allowed the CONTRACTOR for any changes required to adopt the substitute equipment. Therefore, the CONTRACTOR's proposal for an alternate shall include all costs for any modifications to the drawings, such as structural and foundation changes, additional piping or changes in piping, electrical changes or any other modifications which may be necessary or required for approval and adoption of the proposed alternate equipment.

Approval of alternate equipment by the ENGINEER before or after bidding does not guarantee or imply that the alternate equipment will fit the design without modifications.

1.30 SURVEYS

Based upon the information provided by the Contract Documents, the CONTRACTOR shall develop and make all detail surveys necessary for layout and construction, including exact component location, working points, lines, and elevations. Prior to construction, the field layout shall be approved by the OWNER's representative. The CONTRACTOR shall have the responsibility to carefully preserve bench marks, reference points, and stakes, and in the case of destruction thereof by the CONTRACTOR or resulting from its negligence, the CONTRACTOR shall be charged with the expense and damage resulting therefore and shall be responsible for any mistakes that may be caused by the unnecessary loss or disturbance of such bench marks, reference points, and stakes.

1.31 DUST PREVENTION

All unpaved streets, roads, detours, haul roads, or other areas where dust may be generated shall receive an approved dust-preventive treatment or be routinely watered to prevent

20-2888 01 10 00 - 11 dust. Applicable environmental regulations for dust prevention shall be strictly enforced.

1.32 EROSION AND SEDIMENTATION CONTROL

The OWNER has obtained a National Pollutant Discharge Elimination system (NPDES) 1200- CN Permit for this project. The CONTRACTOR shall be responsible for compliance with all 1200-CN permit provisions.

Erosion control measures shall be maintained throughout the project site until approved permanent cover such as a healthy stand of grass, other permanent vegetation, or other ground covering is established. When approved permanent ground cover is established, all temporary erosion control measures shall be removed from the construction site. Erosion control measures shall be installed as approved, per the erosion control drawing(s) in the above referenced document. Erosion control measures including stabilized construction entrances and sediment barriers must be established in conjunction with site clearing and grading.

During construction, and until permanent vegetation or other ground covering is established, the erosion control facilities shall be upgraded as needed for unexpected storm events or site conditions and with the purpose of retaining sediment and sediment-laden water on the construction site.

1.33 INTERFERENCES, OBSTRUCTIONS, AND SEWER CROSSINGS

At certain places, power, light and telephone poles may interfere with excavation and the operation of the CONTRACTOR's equipment. Necessary arrangements shall be made with utility companies for moving or maintaining such poles. The utility company affected by any such interferences shall be notified thereof so that the necessary moving or proper care of poles and appurtenances may have appropriate attention.

All costs resulting from any other interferences and obstructions, or the replacement of such, whether or not herein specifically mentioned, shall be included and absorbed in the unit prices of the CONTRACTOR's bid.

1.34 NOISE LIMITATIONS

The project area is located within a residential zoned area. All applicable City, County ordinances, and State and Federal regulations shall be complied with.

1.35 STORAGE AND PROTECTION OF EQUIPMENT AND MATERIALS

A. Materials and equipment stored overnight shall be placed neatly on the job site.

Unusable materials (i.e. rejected or damaged liner material, old concrete chunks, metal scraps, etc.) shall be expeditiously removed from the job site.

Provide appropriate barricades, signs, and traffic control devices in like-new condition

20-2888 01 10 00 - 12 where necessary to protect the public from any hazards associated with the storage of materials and equipment used for this project.

B. No equipment and/or materials shall be stored outside the immediate work area on public right-of-ways, in the following locations, or in the following manner:

1. In any maintained landscaped or lawn area.

2. In a manner that would totally eliminate an individual residents' street parking.

3. In front of any business.

The “immediate work area” is the area where work is taking place or will be taking place within one calendar day. The CONTRACTOR shall immediately move stored material or equipment which causes a nuisance or creates complaints.

1.36 COMPETENT PERSON DESIGNATION

CONTRACTOR shall designate a qualified and experienced “competent person” at the site whose duties and responsibilities shall include enforcement of applicable OSHA regulations regarding excavations, the prevention of accidents, and the maintenance and supervision of construction site safety precautions and programs.

1.37 EMERGENCY MAINTENANCE SUPERVISOR

The CONTRACTOR shall submit to the ENGINEER the names, addresses, and telephone numbers of at least two employees responsible for performing emergency maintenance and repairs when the CONTRACTOR is not working. These employees shall be designated, in writing by the CONTRACTOR, to act as its representatives and shall have full authority to act on its behalf. At least one of the designated employees shall be available for a telephone call any time an emergency arises.

1.38 PREVAILING WAGE RATES FOR PUBLIC WORKS CONTRACTS IN OREGON

Prevailing wage rates are required for this project, see Division 0 for specific requirements.

1.39 OREGON PRODUCTS

CONTRACTOR's attention is directed to the provisions of Oregon Law, ORS 279A.120 regarding the preference for products that have been manufactured or produced in Oregon.

CONTRACTOR shall use Oregon-produced or manufactured materials with respect to common building materials such as cement, sand, crushed rock, gravel, plaster, etc., and Oregon-manufactured products in all cases where price, fitness, availability and quality are otherwise equal.

20-2888 01 10 00 - 13

1.40 USE OF EXPLOSIVES

The use of explosives shall not be allowed on this project. Alternative methods of excavation shall be utilized.

1.41 CONTAMINATED MATERIAL

A. General

It is possible that the CONTRACTOR may encounter contaminated material (soil and/or water) during excavation activities. This specification identifies requirements for handling and disposing contaminated media.

B. Definitions

1. “Contaminated material” is defined as soil, water, free product, Underground Storage Tanks (UST), buried abandoned utility lines containing residual or free product, solid waste, treated wood waste, chemical containers, or other solid, liquid, or gas substances with contamination levels above background levels.

2. “Hazardous substances” shall mean those substances or materials defined in the Oregon Revised Statutes (ORS) 465.200, as amended.

3. “Release” shall have the meaning as defined in ORS 465.200, as amended.

4. “Environmental laws” shall mean any applicable statute, law, ordinance, order, consent decree, judgment, permit, license, code, covenant, deed, common law, treaty, convention or other requirement pertaining to protection of the environment, health or safety, natural resources, conservation, wildlife, waste management or disposal, hazardous substances or pollution, including but not limited to regulation of releases to air, land, water, and groundwater.

C. Execution

1. Discovery of Contaminated Material

In the event that the CONTRACTOR, during the course of construction or during any other activities authorized under this contract, should encounter suspected contaminated material or any other materials suspected of posing a threat to human health and the environment, the CONTRACTOR shall notify the ENGINEER immediately and manage according to requirements identified below.

2. Discovery of Contaminated Soil

CONTRACTOR shall note evidence of contamination (odor, visual staining of soil, free liquid product seeping from soil, sheen on groundwater, etc.) and note

20-2888 01 10 00 - 14 location of evidence on a sketch of the excavation and provide to the ENGINEER.

CONTRACTOR shall report the discovery to the ENGINEER immediately.

CONTRACTOR shall stop all excavation activities and secure the site to prevent entry by the public. The excavation shall not be backfilled. Protect all open excavations with berms, plates and fencing. CONTRACTOR may continue with work in other non-contaminated areas.

CONTRACTOR shall assist ENGINEER in collecting sample(s) of suspected contaminated media for testing and characterization. CONTRACTOR shall allow 21 days, at no cost to OWNER, for testing, results and instructions as to how to proceed with contaminated materials.

The CONTRACTOR shall obtain a copy of an approved soil disposal/acceptance permit (Disposal/Treatment Facility requires transporter to have a copy of the permit.)

CONTRACTOR will transport and dispose of contaminated material at an approved disposal/treatment facility.

CONTRACTOR shall provide the ENGINEER with a copy of the contaminated soil disposal receipt.

3. Handling of Contaminated Soil

After approval from the ENGINEER, excavate the soil in a manner that prevents commingling of contaminated and non-contaminated soil. ENGINEER will make determination (based on soil saturation) if contaminated soil can be directly transported to a treatment or disposal facility, or if soil needs to be stockpiled to reduce water content. ENGINEER will determine when stockpiled soil can be transported off-site.

CONTRACTOR will be responsible for stockpiling contaminated soil in containers or on impervious surface to prevent the spread of contamination. Any water runoff from the contaminated soil stockpile area(s) must be contained by CONTRACTOR and handled as contaminated water.

Minimize movement of excavation equipment over or through contaminated soil to prevent movement of contaminated soil into areas where no contaminated soil exists.

Stockpiles will be created on an approved site and shall be surrounded by a fence to limit access. The stockpiles must be covered and bermed during periods of rainfall to prevent run-on and run-off. The stockpiles shall be covered with a minimum 10-mil high density polyethylene (HDPE) plastic during periods of strong winds, nightfall, over the weekends, or during extended work stoppages. If dust is

20-2888 01 10 00 - 15 observed coming from the stockpiles, the stockpiles shall be either covered or the dust controlled with water.

Maintain excavation equipment in good working order. Prevent spillage of oil, fuel, or hazardous substances from equipment. In particular, promptly repair oil leaks from equipment and clean up any contaminated soil.

4. Transport of Contaminated Materials

CONTRACTOR shall comply with all applicable Federal, State, or local laws, codes, and ordinances that govern or regulate contaminated substance transportation.

Contaminated soils placed in stockpiles shall be loaded into trucks in a manner that prevents the spilling or tracking of contaminated soil into areas of the site with uncontaminated soil. Loose material falling onto the exterior of the truck during loading shall be removed before the truck leaves the loading area. Any material collected in the loading area shall either be placed back into the truck or back into the stockpile. If loading areas are unpaved, the surface soil shall be sampled at the conclusion of the loading activities to confirm that contaminated soil is not present.

If loading areas are paved, any loose soil shall be cleaned from the pavement at the conclusion of the loading activities.

Specific truck haul routes shall be established before beginning off-site contaminated media transport. On-site truck routes shall be established to minimize or prevent movement of trucks over contaminated soils. Off-site truck routes shall be established to reduce the risk of releases of contaminated soils and impact on local traffic. The CONTRACTOR shall be responsible for ensuring that loaded truck weights are within acceptable limits. All trucks shall be covered before they leave the loading area.

The CONTRACTOR shall ensure that all drivers of vehicles transporting contaminated substances have in their possession during transport all applicable Oregon State and local vehicle insurance requirements, valid driver's license, and vehicle registration and license. The CONTRACTOR shall be responsible for informing all drivers of transport vehicle about:

a. The nature of the material transported.

b. Required routes to and from the off-site thermal treatment or disposal facility.

c. Applicable County street regulations and requirements, and State of Oregon Department of Transportation codes, regulations and requirements.

d. The County's requirement for proper handling and transportation of the substances.

The CONTRACTOR shall not allow contaminated substances to be spilled or tracked

20-2888 01 10 00 - 16 off-site at any time during the project. Trucks used for the transportation of contaminated substances off-site shall be watertight, substance compatible, licensed, insured, and permitted pursuant to federal, state, and local statutes, rules, regulations and ordinances.

If contaminated media is discarded prior to removal of contaminated material, the price per cubic yard of soil materials and price per 100 gallons of contaminated water will be negotiated with OWNER.

1.60 MINIMUM CONTRACTOR QUALIFICATIONS

Minimum contractor qualifications apply to this project for the earthwork, tank contractor and tank prestressor. Refer to front-end Section 00450.

END OF SECTION

EWEB E 40th Ave 7.5 MG Tanks Unit Price Measurement and Payment 20-2888 01 22 20 - 1

SECTION 01 22 20

UNIT PRICE MEASUREMENT AND PAYMENT

PART 1 GENERAL

Measurement and payment will be on a unit price basis in accordance with the prices set forth in the proposal for individual work items. Where work is required but does not appear as a separate item in the proposal, the cost for that work shall be included and absorbed in the unit prices named in the proposal. CONTRACTOR shall make a careful assessment when preparing the bid.

1. Mobilization, bonds, insurance and demobilization: Payment for mobilization, bonds, insurance and demobilization will be on a lump sum basis. The amounts paid for mobilization in the contract progress payment will be based on the percent of the original contract amount that is earned from other contract items, as follows:

A. When 5% is earned, either 100% of the amount for mobilization or 5% of the original contract amount, whichever is the least;

B. When all work is completed, amount of mobilization exceeding 5% of the original contract amount

This schedule of mobilization progress payments will not limit or preclude progress payments otherwise provided by the contract.

2. All work required to construct two 7.5 MG prestressed concrete tanks: Measurement and payment for all project work required to construct two 7.5 million gallon (MG) prestressed concrete tanks, complete, other than as provided for under separate unit prices, will be made on a single lump sum basis. For purposes of evaluating monthly partial payments, this lump sum is broken down as follows:

a. Shop drawings and approvals

b. Construction survey and staking

c. Dewatering

d. Site preparation including minor preliminary site grading, backfill and finish grading

e. Tank construction (2 EA 7.5 MG) including foundation, structure, interior piping, mixing system, interior stairs, hatches and appurtenances.

f. Tank testing, disinfection and start-up

20-2888 01 22 20 - 2

g. Valve vault

h. Water piping including pipe, valves, fittings, restraints and flexible expansion joints.

i. Testing, flushing and disinfection of water mains

j. Site stormwater facilities, complete

k. Tank overflow & drain facilities start-up and testing

l. Tank monitoring manhole

m. Water quality monitoring facilities including enclosures, piping and valves

n. Site access road, parking area and tank access roads with surfacing, drainage ditches and features noted and as shown in the Drawings

o. Electrical, instrumentation & control, and telemetry improvements

p. Maintain owner-provided temporary site fencing

q. Final site grading, surface restoration and site clean-up

r. Site access gate and bollards

s. Traffic control

t. As-built drawing preparation and post-construction survey

Lump sum payment under this item shall cover all particular elements of the project as above generally outlined, whether or not specifically identified, as specified herein and as shown on the Drawings, except for work included separately under other unit price bid items.

3. Tank leak detection system (30-mil PVC liner): Payment for installation of the PVC liners, associated geotextiles, enclosed drain rock and HDPE piping will be made on a lump sum basis.

4. Rock excavation: Payment for rock excavation will be made at the unit price per cubic yard of rock excavated and rock excavation will be paid for in addition to the lineal foot price for pipe, trench excavation and backfill and site excavation for structures. The pay limits for pipe trench shall be 12 inches below the pipe invert and the width shall be the nominal pipe diameter plus 1 foot on each side of the pipe. Pay limits for vaults and other structures shall be to the depth necessary to install the structure and to a maximum of 18 inches beyond the outside walls of the vault or structure. No payment will be made for rock excavation beyond these limits.

20-2888 01 22 20 - 3

Rock excavation is defined in Section 31 23 18, Rock Removal and as determined by the Engineer. Rock excavation will be measured by surveying coordinates and elevations of the solid rock surface prior to and following excavation of the rock; the total quantity of rock excavated will be calculated from these measurements. Rock measurement will be subject to approval by the Engineer. Cost of surveying rock measurement shall be the responsibility of the Contractor. No additional payment will be made for common excavation beyond these limits to remove solid rock and/or boulders nor will payment be made for select backfill beyond these limits placed to fill voids left by removing solid rock and/or boulders.

Contractor’s attention is directed to Section 01 10 00, Summary of Work, which disallows Contractor’s use of explosives in the excavation and removal of rock.

5. Additional cost for overexcavation and select backfill material for unsuitable conditions:

Payment for overexcavation and select structural backfill material for unsuitable tanks structure foundation conditions, unsuitable site stormwater detention facility and unsuitable site piping soil conditions will only be considered as approved by the Engineer in writing.

When such pre-approval is obtained, payment will be made on a per cubic yard basis for the backfill material. Unsuitable material is assumed to be common excavation. Measurement will be agreed upon by CONTRACTOR and ENGINEER prior to overexcavation.

6. Construction Water and Sediment Management Plan. Payment for the construction water and sediment control plan meeting the City of Eugene 1200-CN permit conditions will be made on a lump sump basis. Work includes preparation of a management plan by a licensed engineer, submission of the plan to City of Eugene for review, and installation and operation of temporary measures as needed to meet the permit conditions until permanent site stormwater runoff is accepted. Work includes installation and maintenance of all erosion control measures such as silt fencing, inlet protection and sheeting of exposed cut slopes.

See also Section 01 10 00, Summary of Work.

EWEB E 40th Ave 7.5 MG Tanks Submittal Procedures 20-2888 01 33 00 - 1

SECTION 01 33 00 - SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

A. This Section contains administrative and procedural requirements for submittals for review, information, and for Project closeout.

B. Section includes:

1. Schedule of Submittals.

2. Submittal requirements.

3. Submittal procedures.

4. Engineer review.

5. Resubmittal procedures.

6. Product data.

7. Shop Drawings.

8. Samples.

9. Design data.

10. Test reports.

11. Certificates.

12. Manufacturer's instructions.

13. Manufacturer's field reports.

14. Construction progress schedules.

15. Breakdown of contract price.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action.

B. Informational Submittals: Written and graphic information and physical Samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements.

1.3 SCHEDULE OF SUBMITTALS

A. Within 10 days after the Effective Date of the Contract, Contractor shall submit to Engineer a preliminary Schedule of Submittals, including proposed list of major products proposed for use, with specification section reference, name of manufacturer, supplier, trade name, subcontractor and model number of each product. Provide a schedule of specific target dates for the submission and return of submittals and shop drawings required by the Contract Documents.

20-2888 01 33 00 - 2

B. For products specified only by reference standards, indicate manufacturer, trade name, model or catalog designation, and reference standards.

C. The list and schedule shall be updated and resubmitted when requested by the Engineer.

D. Contractor’s Schedule of Submittals will be deemed acceptable if it provides a workable arrangement for reviewing and processing the required submittals.

1.4 SHOP DRAWING AND SAMPLE SUBMITTAL REQUIREMENTS

A. Before submitting a Shop Drawing or Sample, Contractor shall have:

1. reviewed and coordinated the Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents;

2. determined and verified all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto;

3. determined and verified the suitability of all materials and equipment offered with respect to the indicated application, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work; and

4. determined and verified all information relative to Contractor’s responsibilities for means, methods, techniques, sequences, and procedures of construction, and safety precautions and programs incident thereto.

B. Each submittal shall bear a stamp or specific written certification that Contractor has satisfied Contractor’s obligations under the Contract Documents with respect to Contractor’s review of that submittal, and that Contractor approves the submittal.

C. With each submittal, Contractor shall give Engineer specific written notice of any variations that the Shop Drawing or Sample may have from the requirements of the Contract Documents. This notice shall be set forth in a written communication separate from the Shop Drawings or Sample submittal; and, in addition, in the case of Shop Drawings by a specific notation made on each Shop Drawing submitted to Engineer for review of each such variation.

1.5 SUBMITTAL PROCEDURES

A. Contractor shall submit Shop Drawings and Samples to Engineer for review in accordance with the accepted Schedule of Submittals.

B. Transmit each submittal with Engineer-accepted transmittal form certifying compliance with requirements of Contract Documents.

20-2888 01 33 00 - 3

C. Sequentially number transmittal forms. Mark transmittal forms for resubmittals with original number and sequential alphabetic suffix.

D. Show each Submittal with the following numbering and tracking system:

1. Submittals…

This is the start of the file's text. The full file is on GovTribe.