ITB_03-25_Bid_Tab.pdf
PDF 74 KB Posted
- Attached to
- ITB 03-25 Lift Station 6 Bypass Pump
- Solicitation number
- ITB 03-25
- Issued by
- Volusia County, Florida
About this file
The document is a bid tabulation (ITB 03-25) for New Smyrna Beach Utilities (NSBU), detailing bids received for a Lift Station 60 Bypass Pump project in New Smyrna Beach, Florida. The project involves installing a diesel bypass pumping system, with key deliverables including site preparation, demolition, concrete pad installation, piping systems, electrical and control systems, and a custom fabricated hatch. The procurement targets licensed General Contractors or Certified Underground Utility and Excavation Contractors, with sealed bids due electronically via VendorLink by 2:30 PM on January 16, 2025, and a public bid opening at 3:00 PM the same day. The contract has a 210-day duration, with contractors required to commence work within 14 days of receiving the Notice-to-Proceed.
Five contractors submitted bids, with total project costs ranging from $526,383.00 (All State Civil) to $1,004,950.00 (Razorback). The project includes a $50,000 contingency fund and requires a 10% bid bond. While no explicit set-aside designations for disadvantaged enterprises are specified, subcontractor work is limited to 50% of the total project scope. Contractors must comply with Florida's E-Verify system and maintain a drug-free workplace. NSBU will pre-purchase an 18" skid-mounted solids handling pump, controls, and double-walled fuel tank, with the contractor responsible for equipment installation and site preparation. Mandatory insurance requirements include general liability, workers' compensation, and automobile liability with specific minimum coverage amounts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB_03-25_Bid_Tab.pdf | ||
| ITB_03-25_Addendum_1.pdf | ||
| LS60_Bypass_Plans_2024.10.18.pdf | ||
| LS60_Bypass_Specs_2024.10.18.pdf | ||
| ITB_03-25_Lifstation_60_Bypass_Pump.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Description UOM QTY Unit Price Total Unit Price Total Unit Price Total Unit Price Total
Mobilization, Demobilization, Shop Drawings, Insurance, and Bonds
LS 1 $25,000.00 $25,000.00 $38,000.00 $38,000.00 $57,990.00 $57,990.00 $40,505.84 $40,505.84
2 Demolition LS 1 $28,000.00 $28,000.00 $33,000.00 $33,000.00 $14,370.00 $14,370.00 $8,857.08 $8,857.08
Sitework (Clearing, Grubbing, Grading, Erosion Control, Etc.
LS 1 $9,500.00 $9,500.00 $25,000.00 $25,000.00 $39,148.00 $39,148.00 $35,715.56 $35,715.56
4 Reinforced Concrete Pads LS 1 $18,000.00 $18,000.00 $10,300.00 $10,300.00 $14,800.00 $14,800.00 $37,247.74 $37,247.74
Diesel Bypass Pump System, Fuel Tank, Fuel Piping, Etc.
Installation (Owner Supplied)
LS 1 $3,850.00 $3,850.00 $50,000.00 $50,000.00 $9,700.00 $9,700.00 $20,084.32 $20,084.32
Ductile Iron Piping, Supports, Fittings, Valves, and Appurtenances
LS 1 $140,000.00 $140,000.00 $303,000.00 $303,000.00 $177,505.00 $177,505.00 $181,683.15 $181,683.15
7 24-inch Insertion Valve LS 1 $87,000.00 $87,000.00 $70,000.00 $70,000.00 $88,034.00 $88,034.00 $100,907.28 $100,907.28
8 HDPE Piping, Supports, Fittings. And Appurtenances LS 1 $95,000.00 $95,000.00 $39,000.00 $39,000.00 $74,915.00 $74,915.00 $61,333.01 $61,333.01
9 Custom Fabricated Hatch LS 1 $12,500.00 $12,500.00 $30,000.00 $30,000.00 $22,400.00 $22,400.00 $23,972.26 $23,972.26
10 Chain-Link Fence LS 1 $5,200.00 $5,200.00 $5,030.00 $5,030.00 $9,450.00 $9,450.00 $9,882.72 $9,882.72
11 Electrical and Controls LS 1 $52,333.00 $52,333.00 $120,000.00 $120,000.00 $88,550.00 $88,550.00 $56,466.93 $56,466.93
Project Contingency $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00
Item Description UOM QTY Unit Price Total Unit Price Total Unit Price Total Unit Price Total
Mobilization, Demobilization, Shop Drawings, Insurance, and Bonds
LS 1
$82,000.00 $82,000.00 $33,000.00 $33,000.00 $49,000.00 $49,000.00
2 Demolition LS 1 $20,000.00 $20,000.00 $5,000.00 $5,000.00 $32,420.00 $32,420.00
Sitework (Clearing, Grubbing, Grading, Erosion Control, Etc.
LS 1
$50,000.00 $50,000.00 $60,000.00 $60,000.00 $96,041.00 $96,041.00
4 Reinforced Concrete Pads LS 1 $33,000.00 $33,000.00 $60,000.00 $60,000.00 $53,210.00 $53,210.00
Diesel Bypass Pump System, Fuel Tank, Fuel Piping, Etc.
Installation (Owner Supplied)
LS 1
$48,000.00 $48,000.00 $50,000.00 $50,000.00 $57,500.00 $57,500.00
Ductile Iron Piping, Supports, Fittings, Valves, and Appurtenances
LS 1
$284,000.00 $284,000.00 $223,000.00 $223,000.00 $341,662.00 $341,662.00
7 24-inch Insertion Valve LS 1 $105,200.00 $105,200.00 $97,000.00 $97,000.00 $121,000.00 $121,000.00
8 HDPE Piping, Supports, Fittings. And Appurtenances LS 1 $35,000.00 $35,000.00 $50,000.00 $50,000.00 $34,000.00 $34,000.00
9 Custom Fabricated Hatch LS 1 $10,000.00 $10,000.00 $5,000.00 $5,000.00 $11,982.00 $11,982.00
10 Chain-Link Fence LS 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $9,112.00 $9,112.00
11 Electrical and Controls LS 1 $95,000.00 $95,000.00 $100,000.00 $100,000.00 $149,023.00 $149,023.00
Project Contingency $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00
Clearwater Solutions
$626,655.89
ITB 03-25 Liftstation 60 Bypass Pump Danus McMahan Razorback
ITB 03-25 Liftstation 60 Bypass Pump All State Civil Carr & Collier Cathcart Construction
$526,383.00 $773,330.00 $646,862.00Project Total
Project Total $822,200.00 $743,000.00 $1,004,950.00
Sheet1