ITB_03-25_Bid_Tab.pdf
PDF 74 KB Posted
- Attached to
- ITB 03-25 Lift Station 6 Bypass Pump
- Solicitation number
- ITB 03-25
- Issued by
- Volusia County, Florida
About this file
This document is a bid tabulation (ITB 03-25) for the Lift Station 60 Bypass Pump project issued by New Smyrna Beach Utilities in Florida, detailing bid submissions from five contractors: All State Civil, Carr & Collier, Cathcart Construction, Clearwater Solutions, Danus, McMahan, and Razorback. The project involves installing a diesel bypass pumping system at the Master Pump Station #60, with work including site preparation, demolition, concrete pad installation, piping and valve work, pump and fuel system installation, electrical controls, and associated infrastructure improvements.
The bid tabulation shows unit pricing for 12 distinct line items, with total project costs ranging from $526,383.00 (All State Civil) to $1,004,950.00 (Razorback). Each bidder provided itemized pricing for tasks such as mobilization, demolition, sitework, concrete pads, piping, valves, electrical controls, and a standard $50,000 project contingency. The lowest bidder was All State Civil at $526,383.00, while the highest was Razorback at $1,004,950.00. A project contingency of $50,000 is included across all bids, suggesting a standard risk management approach for this municipal infrastructure project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB_03-25_Addendum_1.pdf | ||
| LS60_Bypass_Plans_2024.10.18.pdf | ||
| LS60_Bypass_Specs_2024.10.18.pdf | ||
| ITB_03-25_Lifstation_60_Bypass_Pump.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Description UOM QTY Unit Price Total Unit Price Total Unit Price Total Unit Price Total
Mobilization, Demobilization, Shop Drawings, Insurance, and Bonds
LS 1 $25,000.00 $25,000.00 $38,000.00 $38,000.00 $57,990.00 $57,990.00 $40,505.84 $40,505.84
2 Demolition LS 1 $28,000.00 $28,000.00 $33,000.00 $33,000.00 $14,370.00 $14,370.00 $8,857.08 $8,857.08
Sitework (Clearing, Grubbing, Grading, Erosion Control, Etc.
LS 1 $9,500.00 $9,500.00 $25,000.00 $25,000.00 $39,148.00 $39,148.00 $35,715.56 $35,715.56
4 Reinforced Concrete Pads LS 1 $18,000.00 $18,000.00 $10,300.00 $10,300.00 $14,800.00 $14,800.00 $37,247.74 $37,247.74
Diesel Bypass Pump System, Fuel Tank, Fuel Piping, Etc.
Installation (Owner Supplied)
LS 1 $3,850.00 $3,850.00 $50,000.00 $50,000.00 $9,700.00 $9,700.00 $20,084.32 $20,084.32
Ductile Iron Piping, Supports, Fittings, Valves, and Appurtenances
LS 1 $140,000.00 $140,000.00 $303,000.00 $303,000.00 $177,505.00 $177,505.00 $181,683.15 $181,683.15
7 24-inch Insertion Valve LS 1 $87,000.00 $87,000.00 $70,000.00 $70,000.00 $88,034.00 $88,034.00 $100,907.28 $100,907.28
8 HDPE Piping, Supports, Fittings. And Appurtenances LS 1 $95,000.00 $95,000.00 $39,000.00 $39,000.00 $74,915.00 $74,915.00 $61,333.01 $61,333.01
9 Custom Fabricated Hatch LS 1 $12,500.00 $12,500.00 $30,000.00 $30,000.00 $22,400.00 $22,400.00 $23,972.26 $23,972.26
10 Chain-Link Fence LS 1 $5,200.00 $5,200.00 $5,030.00 $5,030.00 $9,450.00 $9,450.00 $9,882.72 $9,882.72
11 Electrical and Controls LS 1 $52,333.00 $52,333.00 $120,000.00 $120,000.00 $88,550.00 $88,550.00 $56,466.93 $56,466.93
Project Contingency $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00
Item Description UOM QTY Unit Price Total Unit Price Total Unit Price Total Unit Price Total
Mobilization, Demobilization, Shop Drawings, Insurance, and Bonds
LS 1
$82,000.00 $82,000.00 $33,000.00 $33,000.00 $49,000.00 $49,000.00
2 Demolition LS 1 $20,000.00 $20,000.00 $5,000.00 $5,000.00 $32,420.00 $32,420.00
Sitework (Clearing, Grubbing, Grading, Erosion Control, Etc.
LS 1
$50,000.00 $50,000.00 $60,000.00 $60,000.00 $96,041.00 $96,041.00
4 Reinforced Concrete Pads LS 1 $33,000.00 $33,000.00 $60,000.00 $60,000.00 $53,210.00 $53,210.00
Diesel Bypass Pump System, Fuel Tank, Fuel Piping, Etc.
Installation (Owner Supplied)
LS 1
$48,000.00 $48,000.00 $50,000.00 $50,000.00 $57,500.00 $57,500.00
Ductile Iron Piping, Supports, Fittings, Valves, and Appurtenances
LS 1
$284,000.00 $284,000.00 $223,000.00 $223,000.00 $341,662.00 $341,662.00
7 24-inch Insertion Valve LS 1 $105,200.00 $105,200.00 $97,000.00 $97,000.00 $121,000.00 $121,000.00
8 HDPE Piping, Supports, Fittings. And Appurtenances LS 1 $35,000.00 $35,000.00 $50,000.00 $50,000.00 $34,000.00 $34,000.00
9 Custom Fabricated Hatch LS 1 $10,000.00 $10,000.00 $5,000.00 $5,000.00 $11,982.00 $11,982.00
10 Chain-Link Fence LS 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $9,112.00 $9,112.00
11 Electrical and Controls LS 1 $95,000.00 $95,000.00 $100,000.00 $100,000.00 $149,023.00 $149,023.00
Project Contingency $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00
Clearwater Solutions
$626,655.89
ITB 03-25 Liftstation 60 Bypass Pump Danus McMahan Razorback
ITB 03-25 Liftstation 60 Bypass Pump All State Civil Carr & Collier Cathcart Construction
$526,383.00 $773,330.00 $646,862.00Project Total
Project Total $822,200.00 $743,000.00 $1,004,950.00
Sheet1
File details come from the government source that posted it. Updated .