Amendment_0002_ENG_Epoxy.pdf

PDF 100 KB Posted

Attached to
Epoxy Floor at FCI Food Service - FCI Englewood, CO
Solicitation number
IFBP04031400001
Issued by

About this file

Amendment 0002

View the file

Other files

File Type Posted
Bid_Abstract_ENG_Epoxy.pdf PDF
Clarifications_07172014_ENG_Epoxy.pdf PDF
1_Pre-bid_minutes_ENG_Epoxy.pdf PDF
Amendment_0001_ENG_Epoxy.pdf PDF
IFBP04031400001.pdf PDF
3_Construction_Wage_Rates_CO140007.pdf PDF
1_Specification_ENG_Epoxy.pdf PDF
4_SF24_Bid_Bond.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

07/08/2014

4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

4A6T

BFAOCODE

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

6. ISSUED BY BENGCODE

Federal Bureau of Prisons FCI Englewood

9595 W. QUINCY AVE.

LITTLETON, CO 80123

7. ADMINISTERED BY (If other than Item 6)

9A. AMENDMENT OF SOLICITATION NO.

IFBP04031400001

CODE FACILITY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, country, state and ZIP Code) (X)

X 9B. DATED (SEE ITEM 11)

06/16/2014

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X XThe above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning __1__copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment hereby incorprates the following change(s):

The Construction Wage Rates included as Attachment-3 of the solicitation (Davis-Bacon General Decision CO140007) are hereby replaced with the most recent version dated 07/04/2014 (attached).

*All bidders shall follow the instructions in block 11 of this amendment for acknowledging receipt of this amendment. If choosing option (a), complete the amendment form and enclose with your bid. If choosing option (b) (preferred option), utilize block 19 on page 2 of the solicitation document (Standard Form 1442). The date entered in block 19 for each amendment should match the date reflected in block 3 of each respective amendment.*

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Gregory Formella

(Signature of person authorized to sign)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

By (Signature of Contracting Officer)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

IFBP04031400001/0002 Page 1 of 1

BOP00447

Typewritten Text

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

BOP00447

Highlight

General Decision Number: CO140007 07/04/2014 CO7

Superseded General Decision Number: CO20130007

State: Colorado

Construction Type: Building

Counties: Jefferson and Mesa Counties in Colorado.

BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Modification Number Publication Date 0 01/03/2014 1 01/17/2014 2 03/07/2014 3 04/04/2014 4 05/23/2014 5 06/06/2014 6 06/20/2014 7 07/04/2014

BRCO0007-008 01/01/2014

JEFFERSON COUNTY

Rates Fringes

BRICKLAYER.......................$ 24.03 8.63

CARP9901-005 05/01/2013

Rates Fringes

CARPENTER

All Other Work..............$ 25.00 5.39

ELEC0068-006 06/01/2014

JEFFERSON COUNTY

Rates Fringes

ELECTRICIAN

(Including Low Voltage Wiring and Installation of Fire Alarms, Telephones, Communications Systems and Temperature Controls).......$ 32.65 12.70

ELEC0969-004 07/01/2012

MESA COUNTY

Rates Fringes

ELECTRICIAN

7/8/2014http://www.wdol.gov/wdol/scafiles/DavisBacon/CO7.dvb

(Including Low Voltage Wiring and Installation of Fire Alarms, Telephones, Communications Systems and Temperature Controls)...................$ 20.31 8.56

ELEV0025-002 01/01/2014

Rates Fringes

Elevator Constructor.............$ 40.10 26.785

FOOTNOTE:

a. Employer contributes 8% of basic hourly rate for over 5 years' service and 6% basic hourly rate for 6 months' to 5 years' service as Vacation Pay Credit.

PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans Day; Thanksgiving Day; Friday after Thanksgiving Day; and Christmas Day.

IRON0024-001 11/01/2013

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 24.80 10.14

LABO0720-002 05/01/2014

Rates Fringes

LABORER

Brick Tender/Finisher.......$ 16.42 6.38

PAIN0079-003 01/01/2014

Rates Fringes

PAINTER

(Excluding Drywall Finishing/Taping)...........$ 18.70 6.66

* PAIN0930-001 07/01/2014

Rates Fringes

GLAZIER..........................$ 29.67 7.52

PLAS0577-001 05/01/2013

Rates Fringes

Cement Mason/Concrete Finisher...$ 23.25 10.23

PLUM0003-007 07/01/2013

JEFFERSON COUNTY

Rates Fringes

PLUMBER

(Excluding HVAC work).......$ 33.18 12.44

PLUM0145-003 08/01/2013

MESA COUNTY

Rates Fringes

PLUMBER

(Excluding HVAC work) &

PIPEFITTER (Including

HVAC pipe)..................$ 24.58 10.97

PLUM0208-006 07/01/2013

JEFFERSON COUNTY

Rates Fringes

PIPEFITTER

(Including HVAC pipe).......$ 33.35 12.27

* SHEE0009-001 07/01/2014

Rates Fringes

Sheet metal worker (Includes HVAC duct and installation of HVAC systems)....................$ 32.47 13.98

SUCO2001-017 12/20/2001

Rates Fringes

Carpenters:

Acoustical, Drywall Hanging/ Framing and Metal Studs.................$ 15.95 1.31 Formbuilding/Formsetting....$ 17.55 3.70

Drywall Finisher/Taper...........$ 14.43

Laborer, common..................$ 10.40 2.62

Mechanical Insulator/Asbestos Worker (Includes application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems)....................$ 12.05 .48

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION