About this file

Page 2 of Amendment 0001

View the file

Other files

File Type Posted
BidResultsUndergroundUtLEWjune24.pdf PDF
RFI4LEWjune19.pdf PDF
RFI3LEWjune17.pdf PDF
RFI2utilitiesLEWJUNE16.pdf PDF
BOP30A3.pdf PDF
RFI1.pdf PDF
Minutes.pdf PDF
WageRates.txt TXT text file
BOP30A2.pdf PDF
BOP30A.pdf PDF
CoverLetterLEWutilities.pdf PDF
BOP1442.pdf PDF
TOC.pdf PDF
Specifications.pdf PDF
WageRates.txt TXT text file
SolicitationDocumentApril13LEW.pdf PDF
Drawings.pdf PDF
New Compressed —
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0001

IFB LEW-0015

52.211-12 Liquidated Damages - Construction (SEPT 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $950.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of Clause)