IFB439_Beaver Creek PS_Appendix 4 - VDH Certificate to Construct.pdf
PDF 415 KB Posted
- Solicitation number
- IFB-131135
- Issued by
- Albemarle County, Virginia
About this file
This document is a Waterworks Construction Permit issued by the Virginia Department of Health to the Rivanna Water and Sewer Authority (RWSA) for the Beaver Creek Raw Water Pump Station, Intake and Transmission Main project in Albemarle County. The permit authorizes construction of infrastructure designed to increase raw water supply capacity from 1.1 million gallons per day (MGD) to 2.2 MGD to meet future population-driven demands and the current treatment capacity of the Crozet Water Treatment Plant. The project scope includes installation of a diffused air/destratification system to address seasonal stratification in Beaver Creek Reservoir; construction of a new intake tower with four wedge-wire drum screens; a pump station and wet well equipped with two 1,900 gpm vertical turbine pumps rated at 4.8 MGD total capacity; a sodium permanganate chemical feed system for water quality improvement; and approximately 3,800 linear feet of 12-inch diameter ductile iron transmission main to connect to existing infrastructure. The permit, effective August 12, 2026, and expiring August 12, 2031, is based on approved plans dated July 13-14, 2026, and authorizes work designed to withdraw and pump 4.8 MGD, with 2.8 MGD allocated for plant buildout and 2.0 MGD for minimum in-stream flow requirements for Beaver Creek.
Upon completion of construction, RWSA must submit a statement signed by a licensed Virginia professional engineer certifying that work was completed in accordance with approved documents and include bacteriological analysis results where applicable. The owner must contact the regional Virginia Department of Health Office of Drinking Water field office to determine whether a final inspection is required and schedule such inspection accordingly. Any deviations from approved plans affecting capacity, hydraulic conditions, operating units, treatment processes, or water quality must receive prior approval from the Virginia Department of Health. The permit does not suspend RWSA's obligations to comply with applicable federal, state, and local laws and regulations. Upon the field office's acceptance of the completion statement and satisfactory final inspection notification, the Virginia Department of Health will authorize the project to be placed into service and issue or amend the waterworks operation permit as required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH of VIRGINIA B. Cameron Webb, MD, JD
State Health Commissioner
Department of Health
P O BOX 2448
RICHMOND, VA 23218
TTY 7-1-1 OR
1-800-828-1120
WATERWORKS CONSTRUCTION PERMIT
Permit No.: 93890 Subject: Albemarle County
Effective Date: August 12, 2026 Water: Crozet WTP
Expiration Date: August 12, 2031 PWSID: 2003250
Issued to:
Rivanna Water and Sewer Authority (RWSA)
695 Moores Creek Lane
Charlottesville, VA 22902
ATTN: Mr. Campbell, Director of Operations, dcampbell@rivanna.org
This Waterworks Construction Permit is issued in accordance with Title 32.1 of the Code of Virginia, and
12VAC5-590 et seq. of the Waterworks Regulations. This is your authorization from the State Health
Commissioner to construct the project in accordance with the approved documents. The plans titled “Beaver
Creek Raw Water Pump Station, Intake and Transmission Main” are dated July 13, 2026. The specifications titled “Beaver Creek Raw Water Pump Station, Intake and Transmission Main” are dated July 14, 2026.
A Description Sheet of the proposed construction is enclosed.
This permit does not suspend, minimize, or otherwise alter the waterworks’ obligation to comply with federal, state, or local laws and regulations or permits.
Any deviations from the approved documents affecting capacity, hydraulic conditions, operating units, the functioning of the treatment processes, or the water quality delivered, must be approved by this Office before any such changes are made. Pursuant to 12VAC5-590-240 B, revised plans and specifications shall be submitted in time to ODWConstructionPermits@vdh.virginia.gov to allow the evaluation and approval of these plans or specifications before any construction work that will be affected by these changes may begin.
Upon completion of construction:
• In accordance with 12VAC5-590-250, the owner must submit a statement signed by a professional engineer licensed in Virginia certifying that the work was completed in accordance with the approved documents to ODWFieldOffice2@vdh.virginia.gov. If applicable, this certification must include copies of bacteriological analysis results.
• The owner must contact the regional ODW field office to determine if a final inspection is required in accordance with 12VAC5-590-260 A, and to schedule a final inspection if required.
You can find contact information for ODW field offices at: vdh.virginia.gov/drinking-water/contact-us/.
dcampbell@rivanna.org mailto:ODWConstructionPermits@vdh.virginia.gov mailto:ODWFieldOffice2@vdh.virginia.gov
Upon the ODW Field Office’s acceptance of the statement of completion of construction and, if applicable, notification of a satisfactory completion of a final inspection by field staff, ODW will notify you that the project may be placed into service. If required, ODW will then issue or amend your waterworks operation permit in accordance with the Waterworks Regulations.
If we can be of additional assistance, please contact ODWConstructionPermits@vdh.virginia.gov.
Sincerely, Kamber A. Lee
Plan Review Supervisor
Office of Drinking Water
Enclosure:
Description Sheet of Proposed Construction
Statement of Completion of Construction
Ec: Consulting Engineer: Christopher I Ramo, PE, cramo@hazenandsawyer.com Blue Ridge Health District, John McClelland, john.mcclelland@vdh.virginia.gov
Albemarle County Executive, Jeff Richardson, jeff.richardson@albermarle.org
Albemarle County Building Official, Michael Dellinger, Michael.dellinger@albermarle.org
ODW, Lexington Field Office, steve.kvech@vdh.virginia.gov, thomas.thompson@vdh.virginia.gov file:///C:/Users/lps36084/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/X1TOJN03/PlanReview/Plan%20Review%20-%20Templates/lps36084/Desktop/temp/ODWConstructionPermits@vdh.virginia.gov cramo@hazenandsawyer.com%20 mailto:john.mcclelland@vdh.virginia.gov mailto:jeff.richardson@albermarle.org mailto:Michael.dellinger@albermarle.org steve.kvech@vdh.virginia.gov mailto:thomas.thompson@vdh.virginia.gov
VIRGINIA DEPARTMENT OF HEALTH
DESCRIPTION SHEET
of Proposed Construction
PROJECT DESCRIPTION
The purpose of the project is to increase the raw water supply to Rivanna Water and Sewer Authority’s
(RWSA) Crozet WTP and meet future population driven demands within RWSA service Area. The intent of the project is to increase the permitted water supply from 1.1 MGD to 2.2 MGD which will allow supply to meet the current 2.2 MGD treatment capacity of Crozet WTP in Albemarle County.
This project consists of the installation of a diffused air/destratification (DA/D) system to address seasonal stratification and improve water quality within Beaver Creek reservoir. The project also includes the construction of a new intake tower, pump station and wet well, along with piping controls and associated appurtenances. Additionally, the project includes the installation of approximately 3,800 linear feet of 12-in diameter ductile iron transmission water main, justified by hydraulic analysis to connect to the existing
12-inch diameter water main and convey raw water from the new raw water intake to Crozet WTP. The new intake, pump station and raw water transmission main will be designed to withdraw and pump 4.8
MGD, with 2.8 MGD to meet the plant’s final buildout capacity and the remaining 2.0 MGD to meet the minimum in-stream flow requirements for Beaver Creek.
Diffused air/destratification (DA/D) system: The system includes an air compressor, a 1060-gallon receiving tank that transfers atmospheric air from the shoreline to the bottom of the reservoir; a bottom-lying pipeline diffuser that distributes forced air to the reservoir water column via bubble plumes and will be equipped with all necessary piping and controls. The DA/D system will be operated on a seasonal basis when the reservoir thermally stratifies. The system is not directly associated with the provision of raw water to Crozet WTP.
Intake Tower: Four wedge-wire drum intake screens will be installed on a reservoir-supported intake structure at multiple elevations to provide selective-level withdrawal. Each screen will have a 1-mm slot opening and will be designed for a maximum screen face approach velocity of 0.25 ft/s at the maximum reservoir withdrawal capacity of 4.80 MGD. Each intake screen will be equipped with a mechanically driven brush cleaning system that rotates four times per day to remove debris from the screen surface. Each intake screen will be hard-piped to a common shaft wet well via a 16-inch diameter Sch 40S 316L stainless steel pipeline. Intake piping within the open reservoir will be constructed of stainless steel and will transition to restrained-joint ductile iron pipe (DIP) within a minimum 66-inch diameter micro tunnel boring machine (MTBM)- bored tunnel. To facilitate selection of the desired withdrawal elevation, each intake pipeline will be equipped with an open/close-duty, metal-seated, bonneted knife gate valve installed upstream of its discharge into the shaft wet well. The valves will be remotely operated through SCADA with local manual operation provided within the pump station as a backup.
Pump Station and Wet Well: A new raw water pump station with an approximately building footprint of
3,273 sf will be constructed with a finished floor elevation of 568.5 ft. A 66-inch micro tunnel will convey four 16-inch diameter raw water transmission lines to the wet well, which will have an operating elevation of 509 ft. Two equally sized pumps (one stand-by) will be installed for both systems. The pump station will be equipped with two identical vertical turbine pumps, each driven by a variable frequency drive
(VFD). Each pump will be rated for a capacity of 1900 gpm@200 ft TDH, with a NPSH-req of 23 ft and powered by a 150-hp motor. The new Beaver Creek raw water pump station will be designed with total raw water pumping capacity of 4.8 MGD, with 2.8 MGD pumped to the Crozet WTP to deliver water for public water supply and 2.0 MGD pumped to the rehabilitated dam spillway to deliver water to meet iminium in-stream flow requirements for Beaver Creek. The proposed raw water pump station will include a pump room, compressor room, chemical room, chemical storage area, and electrical room. The chemical room will be equipped with a sodium permanganate injection system, and an emergency shower and eyewash station in accordance with applicable safety requirements. The proposed pump station will be equipped with all necessary accessories and appurtenances including a raw water surge tank, air release valves, check valves, blowoff assemblies, and gate valves. An HVAC system will also be installed alongside the outdoor equipment. A 350 kVA/438 kVA, 0.8 pf diesel generator will be installed on a concrete pad adjacent to the proposed pump station to provide emergency backup power.
Chemical Feed System: A diaphragm-type chemical feed system consisting of a metering pump with a capacity range of 0.0022 gpm to 0.0168 gpm and a 160-gallon solution tank will be provided for the injection of sodium permanganate 20% (liquid form). The system will be designed to deliver a maximum sodium permanganate dose of 2 mg/l at the maximum raw water flow rate of 2.8 MGD. The chemical will be injected into the raw water within the proposed raw water pump station to oxidize dissolved iron and manganese, thereby improving raw water quality and minimizing iron and manganese deposition within the raw water transmission main to Crozet WTP. The chemical feed system will be controlled through
SCADA. It will automatically start when the raw water vertical turbine pump is on, and it will stop when the pump is shut down.
• The required chemical adjustments and dosing will be controlled through the water treatment process at Crozet WTP.
PROJECT CAPACITY EVALUATION
The waterworks has available capacity. The proposed raw water intake from Beaver Creek reservoir is permitted by DEQ and water withdrawal shall not exceed the following limits:
420 million gallons per year; 66 million gallons per month; 2.2 million gallons per day.
Conclusion: After the proposed project is constructed and placed in operation, the permitted capacity of the entire waterworks will be evaluated.
STATEMENT OF COMPLETION OF CONSTRUCTION
Date: ___________________________
Waterworks Owner: ___________________________
Licensed PE: ___________________________
For your use in complying with 12VAC5-590-250 of the Virginia Waterworks Regulations, I submit the following statement:
The construction work described as Beaver Creek Raw Water Pump Station, Intake and Water Main and permitted by the State Health Commissioner under Construction Permit No. 93890 issued on August 12, 2026, was completed in accordance with the approved plans and specifications, revised only in accordance with the provisions of 12VAC5-590-240, as described below, and including successful completion of all specified pressure testing, disinfection, and satisfactory bacteriological analysis results. Copies of bacteriological analysis results are attached to this statement as applicable.
In accordance with 12VAC5-590-250 B, all project specific requirements, including performance validation, process testing and validation, water quality testing, and operator training, are completed and reports and certificates of testing and training are attached to this statement as applicable.
In accordance with 12VAC5-590-240, all deviations from the approved plans and specifications affecting capacity, hydraulic conditions, operating units, the functioning of water treatment processes, or the quality of water to be delivered, were approved by the Virginia Department of Health under the following documents:
Revised Plans and Specifications/Addenda/Change Orders/Field Orders/Engineers Supplemental
Instructions
Number or Title Execution Date VDH Approval Date
This statement is based upon inspections of the waterworks during and after the construction.
Waterworks Owner Signature: _____________________________________ Date: _____________
(Required if the waterworks owner is not the permit applicant)
Consulting Engineer Signature:_____________________________________Date:______________
Engineer Seal:
| Waterworks Construction Permit |
| Issued to: |
| Upon completion of construction: |
| • In accordance with 12VAC5-590-250, the owner must submit a statement signed by a professional engineer licensed in Virginia certifying that the work was completed in accordance with the approved documents to ODWFieldOffice2@vdh.virginia.gov. If app... |
| • The owner must contact the regional ODW field office to determine if a final inspection is required in accordance with 12VAC5-590-260 A, and to schedule a final inspection if required. |
| Sincerely, |
| VIRGINIA DEPARTMENT OF HEALTH |
| DESCRIPTION SHEET |
| of Proposed Construction |
| Date: ___________________________ |
| Waterworks Owner: ___________________________ |
| Licensed PE: ___________________________ |
| For your use in complying with 12VAC5-590-250 of the Virginia Waterworks Regulations, I submit the following statement: |
| This statement is based upon inspections of the waterworks during and after the construction. |
| Consulting Engineer Signature:_____________________________________Date:______________ |
| Engineer Seal: |
| kamber.lee@vdh.virginia.gov | |
| 2026-08-12T14:47:24+0000 | |
| Signed with Box Sign by Kamber Lee (kamber.lee@vdh.virginia.gov) |
File details come from the government source that posted it. Updated .