IFB439_Beaver Creek PS_Appendix 2 - Virginia Waterworks Protection Permit No. 22-2318.pdf
PDF 9 MB Posted
- Solicitation number
- IFB-131135
- Issued by
- Albemarle County, Virginia
About this file
This file is a Virginia Water Protection (VWP) Individual Permit No. 22-2318 issued by the Virginia Department of Environmental Quality for the Rivanna Water and Sewer Authority (RWSA) to construct and operate a surface water intake and associated infrastructure at Beaver Creek Reservoir in Albemarle County, Virginia. The permit authorizes RWSA to withdraw surface water for public water supply purposes serving the Crozet community and surrounding areas. The project includes construction of a new steel-frame intake tower with wedgewire screens in the reservoir, a new pumping station on the shoreline, a raw water transmission main approximately 3,800 feet long from the pumping station to the Crozet Water Treatment Plant, dam rehabilitation including a new reinforced-concrete spillway, modifications to principal spillway equipment, and a permanent access road with a bridge crossing an intermittent stream. The permit authorizes total impacts of 0.36 acres of surface waters, consisting of 0.15 acres of permanent impacts and 0.21 acres of temporary impacts. The permit term is fifteen (15) years from the date of issuance, with reissuance applications required 270 calendar days prior to expiration.
The permit establishes maximum water withdrawal limits of 2.2 million gallons per day (Mgal/d), 66 million gallons monthly, and 420 million gallons annually, based on projected water demands through 2039 and population growth projections for the Crozet service area. RWSA must implement a minimum instream flow (MIF) protocol requiring release of 90 percent of inflow or a tiered maximum release, whichever is lower, with releases calculated annually on March 1st based on Mechums River flow measurements. The permit requires RWSA to install intake screens with 1-millimeter openings and maintain screen face approach velocities not exceeding 0.25 feet per second to protect aquatic species. Comprehensive monitoring and reporting requirements include daily recording of withdrawal amounts and stream flows, semi-annual monitoring reports to the Department, monthly construction inspections during active work, and submission of a Monitoring and Operations Plan within 120 days of permit issuance. The permit imposes no compensation requirements for unavoidable impacts as permanent wetland impacts are less than 0.1 acre and permanent stream impacts are less than 300 linear feet. No public comments were received during the public comment period from November 20 through December 19, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VWP Individual Permit No. 22-2318 Part I – Special Conditions
Part I – Special Conditions
A. Authorized Activities
1. This permit authorizes the construction and operation of a surface water intake and associated infrastructure to withdraw surface water from the Beaver Creek Reservoir for the purposes of a public water supply. This permit authorizes the total impact to 0.36 acres of surface waters, consisting of 0.15 acres of permanent impacts and 0.21 acres of temporary impacts.
a. Permanent impacts consist of no more than 0.07 acre (2900 ft2) of open water and 0.08 acre (275 linear feet) of stream channel.
b. Temporary impacts consist of no more than 0.18 acre (7,850 ft2) of open water and 0.03 acre (35 linear feet) of stream channel.
c. Authorized surface water impacts described under this condition shall be as depicted on the impacts map entitled “Impact Map” submitted with the Joint Permit Application October 5, 2023.
2. The permittee shall conduct authorized activities as described in the Joint Permit Application and supplemental materials, revisions, and clarifications. Any changes to the authorized activities or impacts map that affect permitted areas shall be submitted to the Department immediately upon determination that changes are necessary, and Department approval shall be required prior to implementing the changes.
3. The permit authorizes the temporary use of mechanical equipment in surface waters in accordance with all applicable permit conditions.
4. The permittee shall notify the Department of any changes in authorized impacts to surface waters, of any modifications of the intake structure, or any changes to the design or type of construction activities in surface waters authorized by this permit. Department approval shall be required prior to implementing the changes. Any additional impacts, modifications, or changes shall be subject to individual permit review or modification of this permit.
B. Permit Term
1. This permit is valid for fifteen (15) years from the date of issuance. A new permit may be necessary for the continuance of the authorized activities, including water withdrawals, or any permit requirement that has not been completed, including compensation provisions.
2. The permittee shall submit a new permit application at least 270 calendar days prior to the expiration of this permit if reissuance will be requested. A complete permit application is due by March 31, 2039 in accordance with 9VAC25-210-65.
C. Standard Project Conditions
1. This permit does not constitute, convey, or imply authority to any permittee to unlawfully or incidentally take any threatened or endangered species that is protected by Virginia laws or regulations, pursuant to § 3.2-1000 through -1011; § 29.1-563 through -570; and 4VAC15-20 et seq. In accordance with recommendations from the Virginia Department of Wildlife Resources (DWR) and Conservation and Recreation (DCR), the permittee shall comply with the most recent Time-of-Year-Restrictions (TOYR) recommended by the agency(ies) for this project.
2. The activities authorized by this permit shall be executed in such a manner that any impacts to beneficial uses are minimized. As defined in § 62.1-44.3 of the Code of Virginia, "beneficial use" means both instream and offstream uses. Instream beneficial uses include, but are not limited to, the protection of fish and wildlife habitat, maintenance of waste assimilation, recreation, navigation, and cultural and aesthetic values. The preservation of instream flows for purposes of the protection of navigation, maintenance of waste assimilation capacity, the protection of fish and wildlife resources and habitat, recreation, cultural and aesthetic values is an instream beneficial use of Virginia's waters. Offstream beneficial uses include, but are not limited to, domestic (including public water supply), agricultural uses, electric power generation, commercial, and industrial uses.
3. No activity shall substantially disrupt the movement of aquatic life indigenous to the water body, including those species which normally migrate through the area, unless the primary purpose of the activity is to impound water.
4. Flows downstream of the project area shall be maintained to protect all uses.
5. No activity shall cause more than minimal adverse effect on navigation, and no activity shall block more than half of the width of the stream at any given time.
6. The activity shall not impede the passage of normal or expected high flows, and any associated structure shall withstand expected high flows.
7. All required notifications and submittals shall include project name and permit number and be submitted electronically to Withdrawal.permitting@deq.virginia.gov or mailed to the office stated below, unless otherwise directed in writing by the Department subsequent to the issuance of this permit: Department of Environmental Quality, Attn: Water Withdrawal Permitting Program Manager, Office of Water Withdrawal Permitting, P.O. Box 1105, Richmond VA 23218.
8. All reports required by this permit and other information requested by the Department shall be signed by the permittee or a person acting in the permittee’s behalf, with the authority to bind the permittee. A person is a duly authorized representative only if both criteria below are met. If a representative authorization is no longer valid because of a change in responsibility for the overall operation of the facility, a new authorization shall be immediately submitted to the Department.
a. The authorization is made in writing by the permittee.
b. The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity, such as the position of plant manager, superintendent, or position of equivalent responsibility. A duly authorized representative may thus be either a named individual or any individual occupying a named position.
9. All submittals shall contain the following signed certification statement:
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
10. Any fish kills or spills of fuels or oils shall be reported to the Department immediately upon discovery at 540-574-7800. If the Department cannot be reached, the spill or fish kill shall be reported to the Virginia Department of Emergency Management (VDEM) at 1-800-468-8892 or the National Response Center (NRC) at 1-800-424-8802. Any spill of oil as defined in § 62.1- 44.34:14 of the Code of Virginia that is less than 25 gallons and that reaches, or that is expected to reach, land only is not reportable, if recorded per § 62.1-44.34:19.2 of the Code of Virginia and if properly cleaned up.
11. The Department shall be notified in writing within 24 hours or as soon as possible on the next business day when potential environmentally threatening conditions are encountered which require debris removal or involve potentially toxic substances. Measures to remove the obstruction, material, or toxic substance or to change the location of any structure are prohibited until approved by the Department.
12. Virginia Water Quality Standards shall not be violated in any surface waters as a result of the project activities.
13. All excavation, dredging, or filling in surface waters shall be accomplished in a manner that minimizes bottom disturbance and turbidity.
14. All in-stream activities shall be conducted during low-flow conditions whenever practicable.
15. Erosion and sedimentation controls shall be designed in accordance with the Virginia Erosion and Sediment Control Handbook, Third Edition, 1992. These controls shall be placed prior to clearing and grading and maintained in good working order to minimize impacts to state waters. These controls shall remain in place until the area is stabilized and shall then be removed.
16. All construction, construction access, and demolition activities associated with this project shall be accomplished in a manner that minimizes construction materials or waste materials from entering surface waters, unless authorized by this permit. Wet, excess, or waste concrete shall be prohibited from entering surface waters.
tel:(800)%20468-8892 tel:(800)%20424-8802
17. All fill material placed in surface waters shall be clean and free of contaminants in toxic concentrations or amounts in accordance with all applicable laws and regulations.
18. Measures shall be employed at all times to prevent and contain spills of fuels, lubricants, or other pollutants into surface waters.
19. Machinery or heavy equipment in temporarily impacted wetlands shall be placed on mats or geotextile fabric, or other suitable means shall be implemented, to minimize soil disturbance to the maximum extent practical. Mats, fabrics, or other measures shall be removed as soon as the work is complete in the temporarily impacted wetland.
20. Stream channel restoration activities shall be conducted in the dry or during low flow conditions.
When site conditions prohibit access from the streambank or upon prior authorization from the Department of Environmental Quality, heavy equipment may be authorized for use within the stream channel. The equipment shall be stationed on cobble bars.
21. Temporary disturbances to wetlands, stream channels, and/or stream banks during project construction activities shall be avoided and minimized to the maximum extent practicable.
22. All temporarily disturbed wetland areas shall be restored to preconstruction conditions within 30 calendar days of completing work in the areas, which shall include re-establishing pre-construction contours, and planting or seeding with appropriate wetland vegetation according to cover type (emergent, scrub/shrub, or forested), except for invasive species identified on the Department of Conservation and Recreation’s (DCR’s) Virginia Invasive Plant Species List. The permittee shall take all appropriate measures to promote and maintain the revegetation of temporarily disturbed surface waters through the second-year post-disturbance.
23. All temporarily impacted streams and stream banks shall be restored to their original elevations and contours within 30 calendar days following the construction at that stream segment, and the banks shall be seeded or planted with the same vegetative cover type originally present along the banks, including supplemental erosion control grasses if necessary but not including invasive species identified on DCR’s Virginia Invasive Plant Species List. The permittee shall take all appropriate measures to promote and maintain the revegetation of temporarily disturbed surface waters through the second-year post-disturbance.
24. All materials (including fill, construction debris, excavated materials, and woody materials, that are temporarily placed in wetlands, in stream channels, or on stream banks) shall be placed on mats or geotextile fabric, shall be immediately stabilized to prevent the material or leachate from entering surface waters, and shall be entirely removed within 30 calendar days following completion of that construction activity. After removal, disturbed areas shall be returned to original contours, shall be stabilized, and shall be restored to the original vegetated state within 30 calendar days. The permittee shall take all appropriate measures to promote and maintain the revegetation of temporarily disturbed surface waters through the second-year post-disturbance.
25. Temporary in-stream construction features such as cofferdams shall be made of non-erodible materials.
26. All non-impacted surface waters that are within the project or right-of-way limits, and that are within fifty feet of any project activities, shall be clearly flagged or demarcated for the life of the construction activity within that area. The permittee shall notify all contractors and subcontractors that no activities are to occur in these marked areas.
27. All required Federal, State, and Local permits for impacts to state waters that are related to the construction of this project must be obtained prior to commencement of any construction activities. A summary of all necessary permits required for construction shall be submitted to the Department prior to commencement of any construction activities.
D. Surface Water Withdrawals
1. Surface water withdrawn from Beaver Creek Reservoir and authorized under this permit is to be used for a public water supply.
2. The withdrawal of water from Beaver Creek Reservoir shall not exceed the following:
a. A maximum daily withdrawal of 2.2 million gallons per day (Mgal/d);
b. A maximum monthly withdrawal of 66 million gallons (Mgal); and
c. A maximum annual withdrawal of 420 million gallons (Mgal).
3. The permittee shall install intake screens with openings no larger than 1 millimeter in width and height for mesh screens or a slot size of 1 millimeter in width for wedgewire screens. The permittee shall ensure that the maximum screen face approach velocity does not exceed 0.25 feet per second.
4. The permittee shall estimate the previous days inflow in units of million gallons per day (Mgal/d) on a daily basis by monitoring the stream flow gages detailed herein and by applying the equation:
“Inflow = QM x 0.1 x 0.646”, where:
a. Inflow= estimated streamflow into Beaver Creek Reservoir;
b. QM = the previous day’s provisional mean daily flow at USGS Gage No. 02031000 (Mechums River near Whitehall, VA);
c. 0.1 = is the adjustment factor for drainage area (Intake drainage area of 9.51 square miles / Stream Gaging Station No. 02031000 drainage area of 95.3 square miles); and
d. 0.646 is the conversion factor for CFS to Mgal/d.
5. During construction requiring drawdown of the Reservoir, release must be a minimum of 0.3 cfs on a daily basis.
6. Following construction and commissioning of infrastructure, the required release from the Reservoir must be a minimum of 90% of inflow, or the maximum release, whichever is lower, on a daily basis.
7. The permittee shall provide the following maximum release from the Reservoir to maintain in-stream flows in Beaver Creek:
Mechum’s River Mean Flow (cfs) November 1st
– March 1st
Maximum Required Release from Beaver Creek Reservoir (cfs)
0-19 1.5 20-29 1.9 30-59 2.3 60 + 3.1
The maximum required release shall be calculated each year on March 1st and applies until March 1st of the following year.
8. Within one (1) year (December 27, 2025) of the issuance of this permit, the permittee shall submit a plan, for Department review and approval, detailing how the permittee will estimate stream inflow (Mgal/d) into the Beaver Creek Reservoir through the establishment of an upstream inflow gage or robust procedure for estimating inflows from withdrawals, releases, and recorded Reservoir elevation levels.
9. The permittee shall prepare and submit, for Department review and approval, a plan for conducting and completing an evaluation of existing and future water demands and all potential water sources available to the permittee. The plan shall be submitted no later than the end of year 14 of the permit term (December 31, 2038).
10. The permittee shall submit a Drought Management Plan to the Department for review within 180 days (June 25, 2025) of permit issuance. Any revisions to the plan shall be submitted to the Department for review prior to implementing the change. The plan shall include, at a minimum, the following:
a. Development of drought stages including when and how each stage will be implemented.
b. Description of the conservation measures to be implemented during each drought stage.
11. When a drought emergency is declared by the Commonwealth of Virginia in the Middle James Drought Evaluation Region from the Drought Response Plan or by Albemarle County in accordance with the County’s (or Locality’s) Drought Management Ordinance, the permittee shall implement either the provisions directed by the Commonwealth, the Drought Management Ordinance, or the mandatory conservation measures as detailed in Attachment B of this permit, whichever is the most restrictive. The permittee shall be responsible for determining when drought emergencies are declared. The permittee shall retain records documenting that mandatory conservation measures were implemented during declared drought emergencies.
E. Water Withdrawal Monitoring, Recordation and Reporting Conditions
1. Within 120 days (April 26, 2025) of the issuance of this permit, the Permittee shall submit a Monitoring and Operations Plan for Department review and approval. The Plan should specifically address the following:
a. Procedures for operating the intake to ensure compliance with all water withdrawal conditions of this permit;
b. Procedures for estimating inflow in accordance with Part I D 4 including the time of day that the estimate will be made;
c. Procedures for estimating outflow.
d. A procedure for estimating the previous day’s inflow at the intake location in the event that Gage No. 02031000 (Mechums River near Whitehall, VA) is damaged, disabled, or discontinued;
e. Procedures for recording withdrawals as well as all other monitoring and reporting requirements in Part I E 2 and E 6, including a sample of the reporting form or table that will be used.
2. On each day that pumping occurs, the permittee must monitor and record the following:
a. Date and time;
b. Total amount of water withdrawn each day; and
c. The provisional stream flow in cubic feet per second (cfs) as measured at the Stream Gage No.
02031000 (Mechums River near Whitehall, VA) and the required release as measured in cfs and Mgal/d.
3. The permittee shall monitor withdrawals from the Beaver Creek Reservoir on a daily basis using flow totalizer technology to confirm that the withdrawals are in compliance with this permit. Such meters shall produce volume determinations within plus or minus 10% of actual flows. A defective meter or other device must be repaired or replaced within 60 days. A defective meter is not grounds for not reporting the withdrawals. During any period when a meter is defective, generally accepted engineering practice shall be used to estimate withdrawals and the period during which the meter was defective must be clearly identified in the report.
4. The permittee shall record daily the following information regarding the outflow released from the Reservoir:
a. Date and time;
b. Actual outflow released in cfs; and
c. Required outflow to be released in cfs.
5. The permittee shall report any withdrawal not in compliance with Parts I D 2 or I D 5 or release not in compliance with Parts I D 5 or I D 6 by the fifth (5th) day of the month following the month in which the withdrawal or release occurred. Failure to report may result in compliance or enforcement activities. Reports shall include project name and permit number and be submitted electronically to Withdrawal.permitting@deq.virginia.gov or mailed to the office stated below, unless otherwise directed in writing by the Department subsequent to the issuance of this permit:
Department of Environmental Quality, Attn: Water Withdrawal Compliance Coordinator, Office of Water Compliance, P.O. Box 1105, Richmond VA 23218.
6. The permittee shall submit a water withdrawal monitoring report to the Department semi-annually.
The semi-annual monitoring period shall be as follows: January through June and July through December. The daily records shall be tabulated by month. The report shall be submitted to the Department by February 10th and August 10th of every year within the permit term. Submittal of the report may take the form of electronic reporting, or another form determined to be acceptable by the Department. In the event the electronic reporting system is not available, the permittee may submit the report electronically to withdrawal.permitting@deq.virginia.gov. The report shall include the following information:
a. The permittee’s name and address;
b. The permit number;
c. The source (s) from which water is withdrawn;
d. The location (latitude and longitude) of each point of water withdrawal;
e. Information listed in Part I E 2;
f. The cumulative volume (million gallons) of water withdrawn each month and for the calendar year;
g. The average daily volume (million gallons per day) of water withdrawn as calculated on the last day of the monitoring period.
h. In the last report for the calendar year, the largest single day withdrawal volume (million gallons) that occurred in the year and the month in which it occurred;
i. The method of measuring each withdrawal;
j. A summary of the dates on which the releases from the Reservoir did not meet the required volumes as determined in accordance with Part I D 5 and reason/justification for not meeting requirement outlined in Part I D 5; and
k. If during a semi-annual reporting period a drought emergency is declared, the report shall include a summary of mandatory conservation measures implemented during the drought event.
7. Water withdrawal monitoring and reporting activities shall comply with this section, Part I C, and Part II. All records and information that result from the monitoring and reporting activities required by this permit, including any records of maintenance activities to the withdrawal system, shall be retained for the life of the permit. This period of retention shall be extended automatically during the course of any unresolved litigation regarding the regulated activity or as requested by the Department.
F. Stream Modifications, Including Intake/Outfall Structures
1. Redistribution of existing stream substrate for erosion control purposes is prohibited.
2. Material removed from the stream bottom shall not be deposited into surface waters unless otherwise authorized in this permit.
3. Riprap apron for all outfalls shall be designed in accordance with the Virginia Erosion and Stormwater Management Regulation, 9VAC25-875.
4. For streambank protection activities, structures and backfill shall be placed as close to the streambank as practical, while still avoiding and minimizing impacts to surface waters to the maximum extent practical. No material shall be placed in excess of the minimum necessary for erosion protection.
5. Asphalt and materials containing asphalt or other toxic substances shall not be used in the construction of submerged sills, breakwaters, dams, or weirs.
6. Authorized stream relocation at Impact Site 8 shall be conducted done in the dry, unless specifically authorized by this permit, and all flows shall be diverted around the channelization or relocation area until the new channel is stabilized. The diversion shall be accomplished by leaving a plug at the inlet and outlet ends of the new channel during excavation. Once the new channel has been stabilized, flow shall be routed into the new channel by first removing the downstream plug and then the upstream plug. The new stream channel shall be constructed following the typical sections submitted with the application and should incorporate natural stream channel design principles to the greatest extent practicable. A low flow channel shall be constructed within the channelized or relocated area. The centerline of the channel shall meander, to the extent possible, to mimic natural stream morphology. The rerouted stream flow shall be fully established before construction activities in the old streambed can begin.
7. At least 30 calendar days prior to the initiation of land disturbance or construction activities at Impact Site 8, the permittee shall submit a stream relocation design plan to the Department for review.
G. Installation of Utilities
1. All utility line work in surface waters shall be performed in a manner that minimizes disturbance in each area. Temporarily disturbed surface waters shall be restored in accordance with Part I C 22, C 23, and C 24, unless otherwise authorized by this permit.
2. Material resulting from trench excavation may be temporarily side cast into wetlands not to exceed a total of 90 calendar days, provided the material is not placed in a manner such that it is dispersed by currents or other forces.
3. The trench for a utility line cannot be constructed in a manner that drains wetlands (e.g., backfilling with extensive gravel layers creating a French drain effect).
H. Road Crossings
1. Access roads authorized by this permit shall be constructed to minimize the adverse effects on surface waters to the maximum extent practicable and to follow as near as possible pre-construction contours and elevations.
2. Installation of pipes and road crossings shall occur in the dry via the implementation of cofferdams, sheet piling, stream diversions or other similar structures.
3. All surface waters temporarily affected by a road crossing shall be restored to their original elevations immediately following the removal of that particular temporary crossing. Temporary access roads shall be removed entirely following activity completion.
4. At crossings of streams, pipes and culverts must be installed to maintain low flow conditions and shall be countersunk at both inlet and outlet ends of the pipe or culvert, unless otherwise specifically approved by the Department of Environmental Quality on a case-by-case basis, and as follows: The requirement to countersink does not apply to extensions or maintenance of existing pipes and culverts that are not countersunk, floodplain pipes and culverts being placed above ordinary high water, pipes and culverts being placed on bedrock, or pipes and culverts required to be placed on slopes 5.0% or greater. Bedrock encountered during construction must be identified and approved in advance of a design change where the countersunk condition cannot be met. Pipes and culverts 24 inches or less in diameter shall be countersunk three inches below the natural stream bed elevations, and pipes and culverts greater than 24 inches shall be countersunk at least six inches below the natural stream bed elevations. Hydraulic capacity shall be determined based on the reduced capacity due to the countersunk position. In all stream crossings appropriate measures shall be implemented to minimize any disruption of aquatic life movement.
5. When countersinking culverts in streams, the permittee shall install the structure and any riprap or ancillary features in a manner to ensure reestablishment of the stream channel within 15 days post construction. When installing culverts in any surface water, the permittee shall install the culvert and ancillary features in a manner that will maintain the pre-construction hydrologic regime.
Surface water depth within the impact area shall be consistent with depths upstream and downstream of the impact area.
6. Stream bottom elevations at road crossings shall be measured at the inlet and outlet of the proposed structure and recorded prior to construction and within one week after the completion of construction to ensure that the design elevations were met. This information shall be recorded on the Monthly VWP Permit Inspection Checklist (Attachment D) completed after the crossing is installed.
I. Stormwater Management Structures
1. The outfall and overflow structure shall be constructed and maintained to prevent downstream sediment deposition, erosion, or scour that may be associated with normal flow and any expected storm flows. Construction shall include the use of an appropriately sized riprap outlet protection apron at the outfall site.
2. Maintenance excavation shall follow the stormwater management plan approved by the Virginia Stormwater Management Program Authority and shall not exceed the original contours or designated maintenance areas of the facility.
3. Draining of a stormwater management facility shall be performed by a method that prevents downstream sediment deposition, erosion, or scour.
J. Project Construction Monitoring and Submittals (Impact Sites)
1. The permittee shall submit written notification at least ten (10) calendar days prior to the initiation of land disturbance or construction activities in permitted areas. The notification shall include preconstruction photographs, projected schedule for initiating and completing work at each permitted impact area.
a. Preconstruction photographs shall be taken at each impact area prior to initiation of activities within impact areas.
b. Photographs shall depict the impact area and the nonimpacted surface waters immediately adjacent to and downgradient of each impact area.
c. Each photograph shall be labeled to include the following information: permit number, impact area number, date and time of the photograph, name of the person taking the photograph, photograph orientation, and photograph subject description.
2. Site inspections shall be conducted once every calendar month and recorded on the Monthly VWP Permit Inspection Checklist (Attachment D) by the permittee or the permittee’s qualified designee during active construction within authorized surface water impact areas. Monthly inspections shall be conducted in the following areas: all authorized permanent and temporary impact areas; all avoided surface waters, including wetlands, stream channels, and open water;
surface water areas within 50 feet of any land disturbing activity; and all on-site areas designated for permanent preservation. The Monthly VWP Permit Inspection Checklist (Attachment D) shall be completed in its entirety for each monthly inspection and shall be kept on-site and made available for review by Department staff upon request during normal business hours.
3. The VWP Permit Construction Status Update Form (Attachment C) enclosed with this permit shall be completed in June and December of every year for the duration of this permit. The VWP Permit
Construction Status Update Form (Attachment C) shall include reference to the VWP permit authorization number and one of the following statements for each authorized surface water impact location:
a. Construction activities not yet started;
b. Construction activities started;
c. Construction activities started but are currently inactive, or;
d. Construction activities complete.
4. The VWP Permit Construction Status Update Form (Attachment C) shall be submitted and must be received by the Department no later than January 10 and July 10 of every year.
5. The permittee shall notify the Department within 24 hours of discovering impacts to surface waters including wetlands, stream channels, and open water that are not authorized by this permit.
The notification shall include photographs, estimated acreage and/or linear footage of impacts, and a description of the impacts.
6. The permittee shall submit written notification of completion within 30 calendar days after the completion of all activities in all permitted impact areas authorized under this permit.
Part II – General Conditions
A. Duty to Comply
The permittee shall comply with all conditions and limitations of the VWP permit. Nothing in this chapter shall be construed to relieve the permittee of the duty to comply with all applicable federal and state statutes, regulations, toxic standards, and prohibitions. Any VWP permit violation or noncompliance is a violation of the Clean Water Act and State Water Control Law and is grounds for enforcement action, VWP permit termination, VWP permit revocation, VWP permit modification, or denial of an application for a VWP permit extension or reissuance.
Nothing in this VWP permit shall be construed to relieve the permittee from civil and criminal penalties for noncompliance.
B. Duty to Cease or Confine Activity
It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the activity for which a VWP permit has been granted in order to maintain compliance with the conditions of the VWP permit.
C. Duty to Mitigate
The permittee shall take all reasonable steps to minimize or prevent any impacts in violation of the VWP permit that may have a reasonable likelihood of adversely affecting human health or the environment.
D. VWP Permit Actions
A VWP permit may be modified in whole or in part, revoked and reissued, extended, transferred, or terminated in accordance with 9VAC25-210-180 of the Virginia Administrative Code.
1. During the drafting and authorization of a permit modification, only those conditions to be modified shall be addressed with preparing a draft modified permit. VWP permit terms and conditions of the existing permit shall remain in full force and effect during the modification of the permit.
2. This VWP permit may be modified upon the request of the permittee or upon Department initiative when any of the following developments occur:
a. When new information becomes available about the project or activity covered by the VWP permit, including project additions or alterations, that was not available at VWP permit issuance and would have justified the application of different VWP permit conditions at the time of VWP permit issuance;
b. When a change is made in the promulgated standards or regulations on which the VWP permit was based;
c. When changes occur that are subject to "reopener clauses" in the VWP permit; or
d. When developments applicable to surface water withdrawals occur as specified in 9VAC25-
210-380 of the Virginia Administrative Code.
3. When this VWP permit authorizes surface water withdrawals, it may be modified when any of the following developments occur:
a. When the Department determines that minimum instream flow levels resulting directly from the permittee's withdrawal of surface water are detrimental to the instream beneficial use, existing at the time of permit issuance, and the withdrawal of surface water should be subject to further net limitations or when an area is declared a surface water management area pursuant to §§ 62.1-242 through 62.1-253 of the Code of Virginia, during the term of the VWP permit.
b. Significant changes to the location of the surface water withdrawal system are proposed such that the Department of Environmental Quality determines a new review is warranted due to the potential effect of the surface water withdrawal to existing beneficial uses of the new location.
c. Changes to the permitted project or the surface water withdrawal, including increasing the storage capacity for the surface water withdrawal, that propose an increase in the maximum permitted withdrawal volumes or rate of withdrawal or that cause more than a minimal change to the instream flow requirements with potential to result in a detrimental effect to existing beneficial uses.
d. A revision to the purpose of the surface water withdrawal that proposes to include a new use or uses that were not identified in the permit application or a modification of the existing authorized use or uses such that the use description in the permit application and permit is no longer applicable. Examples of uses include, but are not limited to agricultural irrigation, golf course irrigation, public water supply, manufacturing, and electricity generation.
4. When the permittee has submitted a timely and complete application for reissuance of an existing
VWP individual permit, but through no fault of the permittee, the Department does not reissue or reissue with conditions a VWP individual permit or the Department does not provide notice of its tentative decision to deny the application before an existing VWP individual permit expires, the conditions of the expiring VWP individual permit shall be administratively continued in full force and effect until the effective date of a reissued permit or the date on which the Department denies the application. Timely application shall be a minimum of 180 days for an individual permit or a minimum of 270 days for an individual permit for a surface water withdrawal, unless otherwise specified in the existing permit.
5. Any permittee desiring to continue a previously permitted activity after the expiration date of this
VWP permit shall apply for and obtain a new permit or, if applicable, shall request an extension in accordance with 9VAC25-210-180 of the Virginia Administrative Code. Any permittee with an effective VWP permit for an activity that is expected to continue after the expiration date of the VWP permit, without any change in the activity authorized by the VWP permit other than as may be allowed under 9VAC25-210-180, shall submit written notification requesting an extension. The permittee must file the request 90 days prior to the expiration date of the VWP permit. VWP permit modifications shall not be used to extend the term of a VWP permit beyond 15 years from the date of original issuance. When a permit term, other than that of an Emergency Virginia Water Protection Permit, is less than 15 years, an extension of the permit terms and conditions may be granted in accordance with 9VAC25-210-180. Emergency Virginia Water Protection Permits shall not exceed a duration of one year or shall expire upon the issuance of a regular Virginia Water Protection Permit, whichever comes first.
6. This VWP permit may be transferred to a new permittee only by modification to reflect the transfer, by revoking and reissuing the permit, or by automatic transfer. Automatic transfer to a new permittee shall occur if the current permittee: a) Notifies the Department of the proposed transfer of the permit and provides a written agreement between the current and proposed permittees containing the date of transfer of VWP permit responsibility, authorization, and liability to the new permittee; and b) the Department does not within 15 days notify the existing permittee of its intent to modify the VWP permit.
7. After notice and opportunity for a formal hearing pursuant to § 62.1-44.15:02 of the Code of
Virginia, a VWP permit can be terminated for cause. Reasons for termination for cause are as follows:
a. Noncompliance by the permittee with any condition of the VWP permit;
b. The permittee's failure in the application or during the VWP permit process to disclose fully all relevant facts or the permittee's misrepresentation of any relevant facts at any time;
c. The permittee's violation of a special or judicial order;
d. A determination by the Department that the permitted activity endangers human health or the environment and can be regulated to acceptable levels by VWP permit modification or termination;
e. A change in any condition that requires either a temporary or permanent reduction or elimination of any activity controlled by the VWP permit; and
f. A determination that the permitted activity has ceased and that the compensation for unavoidable adverse impacts has been successfully completed.
8. The Department may terminate this permit without cause when the permittee is no longer a legal entity due to death, dissolution, or when a company is no longer authorized to conduct business in the Commonwealth. The termination shall be effective 30 days after notice of the proposed termination is sent to the last known address of the permittee or registered agent unless the permittee objects within that time. If the permittee does object during that period, the Department shall follow the applicable procedures for termination under § 62.1-44.15:25 of the Code of Virginia and 9VAC25-230 of the Virginia Administrative Code.
9. This VWP permit may be terminated by consent, as initiated by the permittee. The permittee shall submit a request for termination by consent within 30 days of completing or canceling all permitted activities and all required compensatory mitigation requirements. When submitted for project completion, the request for termination by consent shall constitute a notice of project completion. The director may accept this termination on behalf of the Department. The permittee shall submit the following information:
a. Name, mailing address, and telephone number;
b. Name and location of the activity;
c. The VWP permit number; and
d. One of the following certifications:
i. For project completion: "I certify under penalty of law that all activities and any required compensatory mitigation authorized by a VWP permit have been completed. I understand that by submitting this notice of termination that I am no longer authorized to perform activities in surface waters in accordance with the VWP permit, and that performing activities in surface waters is unlawful where the activity is not authorized by a VWP permit, unless otherwise excluded from obtaining a permit. I also understand that the submittal of this notice does not release me from liability for any violations of this VWP permit."
ii. For project cancellation: "I certify under penalty of law that the activities and any required compensatory mitigation authorized by this VWP permit will not occur. I understand that by submitting this notice of termination that I am no longer authorized to perform activities in surface waters in accordance with the VWP permit, and that performing activities in surface waters is unlawful where the activity is not authorized by a VWP permit, unless otherwise excluded from obtaining a permit. I also understand that the submittal of this notice does not release me from liability for any violations of this VWP permit, nor does it allow me to resume the permitted activities without reapplication and issuance of another permit."
iii. For events beyond permittee control, the permittee shall provide a detailed explanation of the events, to be approved by the Department, and the following certification statement:
"I certify under penalty of law that the activities or the required compensatory mitigation authorized by this VWP permit have changed as the result of events beyond my control (see attached). I understand that by submitting this notice of termination that I am no longer authorized to perform activities in surface waters in accordance with the VWP permit, and that performing activities in surface waters is unlawful where the activity is not authorized by a VWP permit, unless otherwise excluded from obtaining a permit. I also understand that the submittal of this notice does not release me from liability for any violations of this VWP permit, nor does it allow me to resume the permitted activities without reapplication and issuance of another permit.
E. Inspection and Entry
Upon presentation of credentials, the permittee shall allow the Department or any duly authorized agent of the Department, at reasonable times and under reasonable circumstances, to conduct the actions listed in this section. For the purpose of this section, the time for inspection shall be deemed reasonable during regular business hours. Nothing contained herein shall make an inspection time unreasonable during an emergency.
1. Enter upon any permittee's property, public or private, and have access to, inspect and copy any records that must be kept as part of the VWP permit conditions;
2. Inspect any facilities, operations, or practices (including monitoring and control equipment) regulated or required under the VWP permit; and
3. Sample or monitor any substance, parameter, or activity for the purpose of ensuring compliance with the conditions of the VWP permit or as otherwise authorized by law.
F. Duty to Provide Information
The Department may request (i) such plans, specifications, and other pertinent information as may be necessary to determine the effect of an applicant's discharge on the quality of state waters or (ii) such other information as may be necessary to accomplish the purposes of this chapter. Any owner, permittee, or person applying for a VWP permit or general permit coverage shall provide the information requested by the Department.
G. Monitoring and Records Requirements
1. Monitoring of parameters, other than pollutants, shall be conducted according to approved analytical methods as specified in the VWP permit. Analysis of pollutants will be conducted according to 40 CFR Part 136 (2017), Guidelines Establishing Test Procedures for the Analysis of Pollutants.
2. Samples and measurements taken for the purpose of monitoring shall be representative of the monitored activity.
3. The permittee shall retain records of all monitoring information, including all calibration and maintenance records and all original strip chart or electronic recordings for continuous monitoring instrumentation, copies of all reports required by the VWP permit, and records of all data used to complete the application for the VWP permit, for a period of at least three years from the date of permit expiration. This period may be extended by request of the Department at any time.
4. Records of monitoring information shall include:
a. The date, exact place and time of sampling or measurements;
b. The name of the individuals who performed the sampling or measurements;
c. The date and time the analyses were performed;
d. The name of the individuals who performed the analyses;
e. The analytical techniques or methods supporting the information such as observations, readings, calculations and bench data used;
f. The results of such analyses; and
g. Chain of custody documentation.
H. Property rights
The issuance of a VWP permit does not convey any property rights in either real or personal property, or any exclusive privileges, nor does it authorize injury to private property or any invasion of personal rights or any infringement of federal, state or local laws or regulations.
I. Reopener
This VWP permit may be reopened for the purpose of modifying the conditions of the VWP permit to meet new regulatory standards duly adopted by the board. Cause for reopening VWP permits includes, but is not limited to when the circumstances on which the previous VWP permit was based have materially and substantially changed, or special studies conducted by the board or the permittee show material and substantial change, since the time the VWP permit was issued and thereby constitute cause for VWP permit modification or revocation and reissuance.
J. Compliance with State and Federal Law
As to the permitted activity(ies), compliance with a VWP permit constitutes compliance with the VWP permit requirements of the Law and regulations.
K. Severability
The provisions of this VWP permit are severable.
L. Oil and Hazardous Substance Liability
Nothing in this VWP permit shall be construed to preclude the institution of legal action or relieve the permittee from any responsibilities, liabilities, or penalties to which the permittee is or may be subject under § 311 of the Clean Water Act or §§ 62.1-44.34:14 through 62.1-44.34:23 of the State Water Control Law.
M. Unauthorized Discharge of Pollutants
Except in compliance with a VWP permit, unless the activity is otherwise exempted or excluded, no person shall dredge, fill, or discharge any pollutant into, or adjacent to surface waters; withdraw surface water; otherwise alter the physical, chemical, or biological properties of state waters regulated under this chapter and make them detrimental to the public health, to animal or aquatic life, or to the uses of such waters for domestic or industrial consumption, for recreation, or for other uses; excavate in wetlands; or on or after October 1, 2001, conduct the following activities in a wetland:
1. New activities to cause draining that significantly alters or degrades existing wetland acreage or functions;
2. Filling or dumping; or
3. Permanent flooding or impounding.
Permit Decision Rationale
3. Project Location:
The Crozet Water Supply System includes the Beaver Creek Reservoir and the Beaver Creek Dam located at 1525 Browns Gap Turnpike in Crozet, Virginia. The Crozet Water Treatment Plant (WTP) is located approximately a mile away at 4673 Three Notch’d Road in Crozet, Virginia.
City/County: Albemarle County Waterbody: Beaver Creek Reservoir, Beaver Creek Basin: James Subbasin: Middle James Section: 10g Class: III Special Standards: PWS
HUC: 020802040102
U.S.G.S. Quadrangle: Crozet
4. Project Description:
Rivanna Water and Sewer Authority (RWSA) proposes the continuation of an existing surface water withdrawal system for the purposes of a public water supply. The Crozet Water Supply System was previously excluded from VWP permitting in accordance with 9VAC25-210-310 A 1, as it was in operation prior to July 1, 1989. This exclusion will become invalid with the issuance of this VWP permit due to RWSA requesting an increased volume of withdrawal and associated upgrades and expansion of the water supply system. Construction work to expand the capacity of the Crozet WTP from 1 million gallons per day (Mgal/d) to 2.1 Mgal/d commenced in 2018 and was completed in 2021. The remaining project components include:
Raw Water Intake and Tunnel. The project consists of the construction of a new steel-frame intake tower in Beaver Creek Reservoir. The new intake will improve reservoir withdrawal capability with the installation of airburst equipped wedgewire screens and five intakes set at various depths to optimize access to the lower-level strata of the reservoir. The reservoir volume will not change as a result of the project. A hypolimnetic oxygenation system will introduce oxygen-saturated water at the new intake location, improving the quality of water withdrawn. The raw water intake tower will be supported by drilled piles and will be constructed in the wet by divers. A connecting tunnel between the pumping station and the intake will be installed by a microtunnel boring machine that will be launched from a wet well shaft beneath the pump station on shore and wet-retrieved in the reservoir at the intake location.
This is the start of the file's text. The full file is on GovTribe.