IFB Solicitation - NP NER PMS BMS FY24(1).pdf

PDF 4 MB Posted

Attached to
Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY24(1)
Solicitation number
693C73-27-B-000003
Issued by

About this file

This is an Invitation for Bids (IFB) solicitation for construction services issued by the Federal Highway Administration Eastern Federal Lands Highway Division. The Northeast Region Pavement and Bridge Preservation Construction project (NP NER PMS BMS FY24(1), Solicitation Number 693C73-27-B-000003) is a Small Business set-aside restricted to certified Small Business Concerns only under NAICS code 237310 (Highway, Street, and Bridge Construction). The project encompasses bridge maintenance and pavement preservation work across eight National Historic Sites and Seashores in New York, New Hampshire, and Massachusetts, including Home of FDR National Historic Site, Eleanor Roosevelt National Historic Site, Vanderbilt Mansion National Historic Site, Fire Island National Seashore, Saint-Gaudens National Historical Park, Sagamore Hill National Historic Park, Saratoga National Historical Park, and Springfield Armory National Historical Park. Work includes thin lift asphalt overlay, chip seal, crack cleaning and sealing, asphalt concrete pavement patching, concrete repairs, bridge rail replacement, and pavement markings.

The project is structured with a base contract (Schedule A) plus five government options (Schedules B through F), with an estimated total project cost of $2,000,000 to $3,000,000. The maximum performance period for all schedules combined is 78 calendar days from the Notice to Proceed, with individual schedule durations ranging from 11 to 22 calendar days. Construction cannot begin earlier than March 22, 2027. Sealed bids are due by December 1, 2026, at 1400 hours local time, submitted electronically to EFLHD.Contracts@dot.gov. A bid guarantee of 20 percent of the bid price or $3,000,000, whichever is less, is required in the form of a bid bond. Bidders must be registered in the System for Award Management (SAM) at time of bid submission and award, must complete the VETS-4212 annual reporting requirement, and must submit performance and payment bonds as required by FAR Clause 52.228-15 within 10 days of award. Award will be made to the responsive, responsible bidder with the lowest Evaluation Total Price, calculated as the sum of all six schedules' bid totals. Progress payments will be made via Electronic Funds Transfer only, with payment information required in SAM. The contract incorporates FAR and Transportation Acquisition Regulation provisions and clauses by reference.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB No. 693C73- 27-B-000003

This Contract Cites

STANDARD SPECIFICATIONS (FP-14)

Contract No.

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

NP NER PMS BMS FY24(1)

Home of FDR National Historic Site (HOFR), Eleanor Roosevelt National Historic Site

(ELRO), Vanderbilt Mansion National Historic Site (VAMA), Fire Island National Seashore (FIIS), Saint-Gaudens National Historical Park (SAGA), Sagamore Hill

National Historic Park (SAHI), Saratoga National Historical Park (SARA), Northeast Region Pavement and Bridge Preservation Construction

PMIS# 340695A, 340691A, 340726A, 340727A, 341534A, 341187A, 341540A, 341189A,

341190A, and 341192A

ADDRESS:

CONTRACTOR:

SOLICITATION

Springfield Armory National Historical Park (SPAR)

STATES

COUNTIES

PARKS

New York, New Hampshire, and Massachusetts

NY/Dutchess, Nassau, Suffolk and Saratoga, NH/Sullivan, MA/Hampden

ELRO, HOFR, FIIS, SAGA, SAHI, SARA, SPAR, VAMA

TYPE OF IMPROVEMENT

Bridge maintenance and pavement preservation of roadways and parking areas for various Northeast region parks.

Work includes thin lift asphalt overlay, chip seal, crack cleaning and sealing, asphalt concrete pavement patching, concrete repairs, bridge rail replacement, pavement markings, and other miscellaneous work.

Project Length Totals For Parking Areas, Lane Miles is calculated as SQFT/11ft (nominal) lane

2.88 7.98

Schedule Parking Area Roadway / Parking Area / Other Mileposts / SQFT Linear

Feet Route Miles

Lane Miles

A 1793-001P: Fall Kill Bridge To 40 0.01 0.02

A HOFR-0011: Wallace Center Entrance/ Exit Road

0 To 0.30 1,584 0.30 0.60

A HOFR-0407: Bellefield Mansion Loop 0 To 0.23 1,214 0.23 0.46

A ■ HOFR-0900: FDR Library Parking 11,186 0 0.00 0.19

A ■ HOFR-0903A: Bellefield Parking A 2,716 0 0.00 0.05

A ■ HOFR-0903B: Bellefield Parking B 1,096 0 0.00 0.02

A ■ HOFR-0906: Farm Lane West Parking 35,258 0 0.00 0.61

A 1797-003P: Rustic Bridge To 182 0.03 0.06

A VAMA-0011: Bard Road 0 To 0.45 2,376 0.45 0.90

A VAMA-0401: Mansion Loop 0 To 0.17 898 0.17 0.34

A ■ VAMA-0901: Overlook Parking 1,928 0 0.00 0.03

A ■ VAMA-0906AZ: Coach House Parking A

2,300 0 0.00 0.04

A ■ VAMA-0906BZ: Coach House Parking B

1,358 0 0.00 0.02

B FIIS-0010ZZ: West Entrance Paved Road

0 To 0.11 581 0.11 0.22

B FIIS-0101: Main Entrance 0 To 0.25 1,320 0.25 0.25

B FIIS-0103: Main Exit 0 To 0.22 1,162 0.22 0.22

B ■ FIIS-0902: William Floyd Estate Parking 31,532 0 0.00 0.54

C ■ SAGA-0900: Visitor Parking 4,318 0 0.00 0.07

C ■ SAGA-0901 Visitor Center Drive Parking

5,134 0 0.00 0.09

D SAHI-0010AZ: Entry Circle Road A 0 To 0.10 528 0.10 0.10

D SAHI-0100: Theodore Roosevelt House Road

0 To 0.12 634 0.12 0.12

D SAHI-0102:Old Historic Road 0 To 0.10 528 0.10 0.10

D SAHI-0103: Access Road to Old Orchard Museum

0 To 0.23 1,214 0.23 0.23

D SAHI-0105: Spur to Theodore Roosevelt House Road

0 To 0.07 370 0.07 0.07

D SAHI-0106: House Entrance Road 0 To 0.07 370 0.07 0.14

D SAHI-0404: Gray Cottage Access Road 0 To 0.10 528 0.10 0.10

D ■ SAHI-0900: Main Parking Area 51,215 0 0.00 0.88

D ■ SAHI-0901AZ: Barn Parking A 1,894 0 0.00 0.03

D ■ SAHI-0901BZ: Barn Parking B 992 0 0.00 0.02

D ■ SAHI-0902: Theodore Roosevelt Museum Parking

3,700 0 0.00 0.06

D ■ SAHI-0903: Administrative and Handicap Parking

4,890 0 0.00 0.08

D ■ SAHI-Route 0904: Maintenance Area Parking

4,731 0 0.00 0.08

D ■ SAHI-0905: Equipment Storage Parking 3,135 0 0.00 0.05

D ■ SAHI-0906 THR Rear Entrance Parking 2,209 0 0.00 0.04

E 1910-002P: Kroma Kill Bridge #2 To 37 0.01 0.02

E 1910-003P: Kroma Kill Bridge #3 To 46 0.01 0.02

E SARA-0100: Roosevelt Road 0 To 0.11 581 0.11 0.11

E SARA-0401: Headquarter Loop Road 0 To 0.08 422 0.08 0.16

E ■ SARA-0916: Monument Parking 13,259 0 0.00 0.23

E ■ SARA-0918Z: Support Facility Parking C

1,913 0 0.00 0.03

E SARA-0500: TOUR ROAD 0 To 0 30 0.01 0.01

F SPAR-0011: Entrance Road (Ceremonial)

0 To 0.10 528 0.10 0.20

F ■ SPAR-0900: Main Parking Area (Museum)

21,503 0 0.00 0.37

TABLE OF CONTENTS

Page

Notice to Bidders 1 through 3

Checklist for Bid Submission 1 through 2

*SF-1442 Solicitation, Offer, and Award 1 through 6

Statement of Work 1 page

Bid Schedule Instructions 1 through 4

*Bid Schedule B-1 through B-9

*SF-24 Bid Bond C-1 through C-4

FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION REGULATION

SOLICITATION PROVISIONS & CONTRACT CLAUSES

1 through 6

D-1 through D-4

E-1

F-1 through F-4

F-5 through F-114

G-1 through G-11

H-1 through H-7

J-1 through J-63

K-1 through K-3

Index to Federal and Transportation Acquisition Regulations

Representations and Certifications (SAMs online)

Instructions to Bidders

*Socioeconomic Program Requirements

Minimum Wage Schedules

*General Contract Requirements

Construction Contract Requirements

Special Contract Requirements

Section K

Permits

SPECIFICATIONS ON SAM.GOV

Categorical Exclusion Form (NEPA)

NP NER PMS BMS FY24(1) Bridge_Insp_Rpts_adv

NP NER PMS BMS FY24(1) details_adv

NP NER PMS BMS FY24(1) RIP_Rpts_prelim

*Bidder’s Qualification Form

*Federal Contractor Veterans’ Employment Report VETS-4212

1 page

1 through 8

1 through 83

1 through 25

1 through 56

1 through 7

1 through 5

*BOLD-FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE*

NOTICE TO BIDDERS

CONTRACT FORMAT:

Bidders should note that the format of this contract is in accordance with Federal Acquisition

Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-pages in this booklet. FAR provisions and clauses incorporated by reference can be accessed on the Internet website at https://www.acquisition.gov/. Bidders are encouraged to review the documents thoroughly before submitting a bid.

INVITATION FOR BIDS BOOKLET AND BID SUBMITTAL:

It is the responsibility of the Bidder to verify that this bid is complete as listed in the Table of Contents.

The Bidder is responsible for submitting all required forms and documents with the bid. Bidders should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.

CONSTRUCTION CONTRACTS:

Additional guidance is given in FAR Subpart 35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e.

proprietary Cintec arch strengthening.) There are exceptions and they will be reviewed on a case-by-case basis.

HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:

As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Bidder must submit prior to award a Material Safety Data Sheet (MSDSs) for all hazardous materials that the Bidder identifies in paragraph (b) of this clause in Section G of this booklet. Failure to submit MSDSs may render the Bidder ineligible for award of contract. The apparent low Bidder should submit their MSDSs within two weeks after bid opening.

INTERNET BASED DATABASES - REQUIRED INPUT:

Per FAR Provision 52.204-7, bidders are required to be registered in the System for Award

Management (SAM) at the time a bid is submitted and at the time of award.

Access the following web site to register: https://www.sam.gov/.

Per FAR Clause 52.204-13, contractors shall maintain an active SAM registration during contract performance through final payment under a contract. This includes reviewing at least annually its registration in SAM and validating that the information is current, accurate, and complete.

NOTICE:

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-

3, Offeror Representations and Certifications—Commercial Products and Commercial Services.

Contracting Officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to update their entity registration to remove these representations in SAM.

https://www.acquisition.gov/ https://www.sam.gov/

According to FAR 22.1302-1(b) federal contractors and sub-contractors MUST complete the required annual Vets-4212 Form in order to be eligible for a contract award. It can be completed online at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year’s filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

PAYMENT:

Bidders are advised to review the Standard Specifications for Construction of Roads and Bridges on

Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.

PROGRESS PAYMENTS:

ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in

SAM must be accurate in order for contractors’ invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the SAM database. Bidders are advised that under FAR Clause

52.232 5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION”, payments for performance and payment bond premiums shall be included in mobilization.

WELFARE-TO-WORK INITIATIVE:

The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.

INCREASING SEAT BELT USE IN THE UNITED STATES:

The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.

OBTAINING SOLICITATION DOCUMENTS:

Invitation For Bid (IFB) documents will not be mailed. All solicitation documents are available for direct download from the Contract Opportunities website: https://sam.gov/. Contractors are encouraged to register on the website (for this specific project) in order to receive automatic notifications when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address: eflhd.contracts@dot.gov.

http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm https://sam.gov/ mailto:eflhd.contracts@dot.gov

THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES

NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON THOSE

CHANGES.

PLEASE NOTE: For security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to a scheduled bid opening. All visitors must sign in at the main entrance of the Quantum Park facility and wait to be escorted by a Government employee to Eastern Federal Lands Highway Division (EFLHD) in Suite 200. Visitors must then register with the EFLHD Receptionist. A Government employee will collect all bids. Prior to the bid opening, a

Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry, and no exceptions will be made.

PLEASE NOTE ELECTRONIC BIDS WILL BE ACCEPTED VIA EMAIL ONLY

AT EFLHD.CONTRACTS@DOT.GOV. Bids sent to any other email address besides

EFLHD.Contracts@dot.gov will not be accepted. Bids will not be accepted via facsimile. Bids submitted via external, cloud-based, file storage services such as OneDrive, etc. shall not be accepted. The government will not click on links sent via email to access bid documents. Hand-delivered bids are not recommended unless the contractor is also attending the bid opening.

mailto:EFLHD.CONTRACTS@DOT.GOV mailto:EFLHD.Contracts@DOT.GOV

CHECKLIST FOR BID SUBMISSION

The following is a checklist of items included in the bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.

PLEASE NOTE ELECTRONIC BIDS WILL BE ACCEPTED VIA EMAIL ONLY AT

EFLHD.CONTRACTS@DOT.GOV. Bids sent to any other email address besides

EFLHD.Contracts@dot.gov will not be accepted. Bids will not be accepted via facsimile. Bids submitted via external, cloud-based, file storage services such as OneDrive, etc. shall not be accepted. The government will not click on links sent via email to access bid documents. Hand-delivered bids are not recommended.

1. Bid Envelope (If the Bidder elects not to send the bid electronically via email to

EFLHD.Contracts@dot.gov):

a. Addressed as shown in Block 7 of SF-1442

b. In the lower left corner, indicate the following: Solicitation No., Project Name & Number, and mail to Suite E2-3-300, ATTENTION: ACQUISITIONS. If bids are hand-delivered, bring them to the main entrance of Quantum Park, and ask for the Federal Highway Administration

(EFLHD) Receptionist to be contacted and an EFLHD representative will come to collect the bid. Hand-delivered bids are not recommended.

2. Standard Form 1442: Solicitation, Offer and Award

a. Block 14: Name and Address of Bidder.

b. Block 15: Telephone Number of Bidder

c. Block 16: Remittance Address if different from Block 14.

d. Block 19: All Amendments Acknowledged, with dates of Amendments.

e. Block 20: Bid is signed and dated.

3. Bid Schedule - (Pages B-1 through B-9)

a. Unit bid price and bid amount provided for each pay item in numbers.

b. Corrections initialed.

4. Standard Form 24, Bid Bond (Pages C-1 through C-4) (Required if bid guarantee is bid bond)

a. Date executed

b. Legal name and address of bidder.

c. Type of organization.

d. State of incorporation (if applicable).

e. Name and business address of Treasury approved surety.

f. Penal sum of bond (not less than 20% of bid total).

g. Bid identification.

h. Signature of Bidder

i. Seal, if corporation

j. Signature of Surety

k. Seal, if corporation

BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.

mailto:EFLHD.CONTRACTS@DOT.GOV mailto:EFLHD.Contracts@dot.gov

CHECKLIST FOR BID SUBMISSION

5. Power of Attorney

a. Dated on or before execution date of bond

b. Power has original signature of surety, or is embossed with surety’s seal in the certification section

BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.

6. Bidder’s Qualifications form (provided separately as part of the Bid Documents

Package). Form completed, signed and submitted with bid

7. System for Award Management (SAM): The contractor is currently registered in the

System for Award Management (SAM) database at https://www.sam.gov/ at the time the bid is submitted. If the contractor elects to not have its active SAM registration viewable by the public, then the contractor must submit a copy with the bid.

8. Online Representations and Certifications Application: The contractor’s

Representations and Certifications have been input online via the electronic database at https://www.sam.gov/.

9. VETS - 4212 Reporting: The contractor has completed the annual reporting requirement online at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is

August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year’s filing cycle. Federal contractors and subcontractors who are required to file a form VETS-

4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process

10. INVOICING FOR PAYMENTS: The Contractor affirms that it does not operate any diversity, equity, and inclusion (DEI) initiatives that are inconsistent with the Equal Protection principles of the Constitution and the non-discrimination requirements of Federal law, as interpreted by the Supreme Court in Students for Fair Admissions v. Harvard, 600 U.S. 181 (2023).

NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL

DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE

IS SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA

PRIOR TO BID SUBMISSION MAY CAUSE THE BID TO BE REJECTED.

https://www.sam.gov/ https://www.sam.gov/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

SUITE E2-3-300

693C73

Attn: Acquisition and Contracts

ASHBURN VA 20147

See Block 7

Monique Lynch

See Block 10 x

10/29/2026

693C7327B000003

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This Invitation for Bids is for the Northeast Region Pavement and Bridge Preservation Construction, Project NP NER PMS BMS FY24(1), located in Dutchess, Nassau, Suffolk and Saratoga Counties, New York; Sullivan County, New Hampshire;

and Hampden County, Massachusetts, in strict accordance with the Solicitation/ Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.

FP - Standard Specification for Construction of Roads & Bridges on Federal Highway Projects.

Bid Schedule, Section B - pages B-1 through B-9.

Special Contract Requirements, Section J - pages J-1 through J-63.

Categorical Exclusion Form (NEPA), pages 1 through 8.

NP NER PMS BMS FY24(1)_Bridge_Insp_Rpts_adv, pages 1 through 83.

NP NER PMS BMS FY24(1)_details_adv, pages 1 through 25.

NP NER PMS BMS FY24(1)_RIP_Rpts_prelim, pages 1 through 56.

Permit Tracking Form, 1 page.

Issuance of this solicitation does not guarantee that an award will be made. Any resulting awards are subject to the availability of funding and the discretion of the awarding entity, including cancellation or amendment based on a determination of change in agency needs.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 78 calendar days and complete it within ________________ ________________ calendar days after receiving

Continuation Sheet, Block 11

12/01/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

EFLHD.Contracts@dot.gov

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

EFLHD-CO

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

SUITE E2-2-200

ATTN: CONSTRUCTION

ASHBURN VA 20147

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

FFEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

A/P Branch, AMZ-150 PO Box 25710 OR E-MAIL

9-AMC-AMZ-EFLINVOICES@FAA.GOV

Oklahoma City OK 73125

Block 26

CONTINUATION OF SF 1442

Block 2:

This project is RESTRICTED - Bids will be accepted from all eligible Small Business concerns.

This procurement falls under North American Industry Classification System (NAICS) code 237310 - Highway, Street, and Bridge Construction (see FAR 19.103).

Electronic bids will be accepted via email sent to EFLHD.Contracts@dot.gov. Please be sure to indicate the solicitation number, project number, and ATTN: Monique Lynch on the subject line of your email. Bids submitted via external, cloud-based, file storage services such as OneDrive, etc. shall not be accepted. The government will not click on links sent via email to access bid documents. Please note you must include a scanned copy of your official bid bond along with your bid documents if you submit your bid electronically.

Block 9:

PHYSICAL DATA AVAILABLE FOR REVIEW

1. Manual on Uniform Traffic Control Devices for Streets and Highways, most current edition, published by the Federal Highway Administration. https://mutcd.fhwa.dot.gov/.

2. National Park Service Sign Manual, revised - January 1988, United States Department of the Interior. https://highways.dot.gov/federal-lands/design/highway-design-library.

3. NP NER PMS BMS FY24(1)_Bridge_Insp_Rpts_adv

4. NP NER PMS BMS FY24(1)_RIP_Rpts_prelim

5. NP NER PMS BMS FY24(1)_details_adv

6. Categorical Exclusion Form (NEPA)

7. Permits

Data and information furnished or referred to above is for the Contractor's information.

The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

A Government representative can be available to show the project to prospective bidders.

All requests for site visits see Section E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.

mailto:EFLHD.Contracts@dot.gov https://mutcd.fhwa.dot.gov/ https://highways.dot.gov/federal-lands/design/highway-design-library mailto:eflhd.contracts@dot.gov

Block 11:

Maximum time allowed for the contract if Schedules A, B, C, D, E and F are awarded at the same time:

If the Government awards the contract as Schedules A + B + C + D + E + F, the performance period to complete all contract work will be 78 calendar days.

Maximum time allowed for each schedule of work if awarded separately:

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 17 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 13 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 22 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.

If Schedule D (Government Option 3) is exercised after the award of the original contract, the performance period to complete all Schedule D work will be 16 calendar days and will start on the effective date of Schedule D’s Notice to Proceed.

If Schedule E (Government Option 4) is exercised after the award of the original contract, the performance period to complete all Schedule E work will be 11 calendar days and will start on the effective date of Schedule E’s Notice to Proceed.

If Schedule F (Government Option 5) is exercised after the award of the original contract, the performance period to complete all Schedule F work will be 15 calendar days and will start on the effective date of Schedule F’s Notice to Proceed.

See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above. Work restrictions can be found in SCR Sections 108 and 156.

Construction activities at the project site cannot begin any earlier than March 22, 2027.

Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)

Bidders are to assume that the award of the contract and approval of the Contractor’s

Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause

52.228-15) may result in the start of construction activities to be no earlier than

March 22, 2026. See Subsection 108.01 of the SCRs for additional details.

Block 12A:

Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.

Block 13:

A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision

52.228-1, Bid Guarantee. Please note you must include a scanned copy of your official bid bond along with your bid documents if you submit your bid electronically.

Block 17:

Amounts should be completed as follows:

Schedule A - $

Schedule B (Option 1) - $

Schedule C (Option 2) - $

Schedule D (Option 3) - $

Schedule E (Option 4) - $

Schedule F (Option 5) - $

Other:

The estimated price is expected to fall within the price range of $2,000,000 to

$3,000,000.

Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from the Contract

Opportunities website located at http://SAM.gov. FP-14 versions can be downloaded at the FHWA web site located at http://flh.fhwa.dot.gov/resources/specs/.

Electronic bids must contain the required signatures (electronic or by hand). Bids submitted via external, cloud-based, file storage services such as OneDrive, etc. shall not be accepted. The government will not click on links sent via email to access bid documents.

If you elect not to submit your bid electronically to EFLHD.Contracts@dot.gov, then please mail your bid to:

Federal Highway Administration - Eastern Federal Lands Highway Division

ATTN: ACQUISITIONS

Quantum Park

22001 Loudoun County Parkway

Suite E2-3-300

Ashburn, VA 20147 http://sam.gov/ http://flh.fhwa.dot.gov/resources/specs/

STATEMENT OF WORK

Sealed bids from certified Small Business Concerns only will be accepted for the Northeast

Region Pavement and Bridge Preservation Construction, Project NP NER PMS BMS FY24(1), Solicitation Number 693C73-27-B-000003, located in Dutchess, Nassau, Suffolk and Saratoga

Counties, New York; Sullivan County, New Hampshire; and Hampden County, Massachusetts.

The project consists of bridge maintenance and pavement preservation of roadways and parking areas across several parks including Home of FDR National Historic Site (HOFR), Eleanor

Roosevelt National Historic Site (ELRO), Vanderbilt Mansion National Historic Site (VAMA), Fire Island National Seashore (FIIS), Saint Gaudens National Historic Park (SAGA), Sagamore

Hill National Historic Park (SAHI), Saratoga National Historical Park (SARA) and Springfield

Armory National Historical Park (SPAR). The work includes thin lift asphalt overlay, chip seal, crack cleaning and sealing, asphalt concrete pavement patching, pavement markings, and other miscellaneous work.

The project will be split into multiple work schedules/contract options, with the cost of the entire project expected to fall within the price range of $2,000,000 to $3,000,000.

The performance period to complete all contract work will be 78 calendar days after the issuance of the Notice to Proceed.

Construction activities at the project site cannot begin any earlier than March 22, 2027.

BID SCHEDULE INSTRUCTIONS

PROJECT: NP NER PMS BMS FY24(1)

BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to

Bidders. When preparing the bid, comply with the following:

COMPLETING THE BID SCHEDULE

Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit

Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual

Schedule of Work by adding the amounts of the listed items and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.

To be eligible for award, bidders must submit prices for each pay item.

Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.

Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.

The amount in Block 17 of the SF 1442 should be completed as follows:

Schedule A - $ .

Schedule B - $ .

Schedule C - $ .

Schedule D - $ .

Schedule E - $ .

Schedule F - $ .

SCHEDULES OF WORK

The Bid Schedule is comprised of the following separate schedules and options:

Schedule A (Base Contract) - Pages B-1 through B-2

Schedule B (Government Option 1) - Page B-3

Schedule C (Government Option 2) - Page B-4

Schedule D (Government Option 3) - Page B-5 through B-6

Schedule E (Government Option 4) - Page B-7

Schedule F (Government Option 5) - Page B-8

The Government will award the project as a Base Contract (Schedule A) with the option to award Schedules B, C, D, E, and F (Government Options 1, 2, 3, 4, and 5); see FAR

Provisions 52.217-4 and 52.217-5.

The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedules B, C, D, E, and F (Government Options 1, 2, 3, 4 and 5) at that time. If additional funding is required for the award of Schedules B, C, D, E, and F (Government Options 1, 2, 3, 4 and 5), and is received after the award of Schedule A

(Base Contract), the Government has the right to exercise Schedules B, C, D, E, and F

(Government Options 1, 2, 3, 4 and 5) at the unit prices bid according to the following schedule:

Schedule B (Government Option 1): No later than the contract completion date for Schedule A

(Base Contract).

Schedule C (Government Option 2): No later than the contract completion date for Schedule A

(Base Contract).

Schedule D (Government Option 3): No later than the contract completion date for Schedule A

(Base Contract).

Schedule E (Government Option 4): No later than the contract completion date for Schedule A

(Base Contract).

Schedule F (Government Option 5): No later than the contract completion date for Schedule A

(Base Contract).

COMPLETION OF WORK

The Government has estimated the number of calendar days necessary to complete all work from the effective date of the Notice to Proceed to contract completion for the various award scenarios. The maximum number of calendar days allowed (i.e., the contract performance period) is shown in Block 11 of the SF-1442 and described below.

If the Government awards the contract as Schedules A + B + C + D + E + F, the performance period to complete this work will be 78 calendar days.

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 17 calendar days and will start on the effective date of

Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 13 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 22 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.

If Schedule D (Government Option 3) is exercised after the award of the original contract, the performance period to complete all Schedule D work will be 16 calendar days and will start on the effective date of Schedule D’s Notice to Proceed.

If Schedule E (Government Option 4) is exercised after the award of the original contract, the performance period to complete all Schedule E work will be 11 calendar days and will start on the effective date of Schedule E’s Notice to Proceed.

If Schedule F (Government Option 5) is exercised after the award of the original contract, the performance period to complete all Schedule F work will be 15 calendar days and will start on the effective date of Schedule F’s Notice to Proceed.

In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and

Special Contract Requirements (SCRs). Specific work limitations may be (but are not limited to):

National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc.); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc.); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc.). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCRs).

Bidders are to assume that the award of the contract and approval of the Contractor’s

Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-

15) may result in the start of construction activities to be no earlier than March 22, 2027.

See Subsection 108.01 of the SCRs for additional details.

BASIS FOR AWARD

The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation

Total Price of Project, which is defined as:

Schedule A (Base Contract) Bid Total +

Schedule B (Government Option 1) Bid Total +

Schedule C (Government Option 2) Bid Total +

Schedule D (Government Option 3) Bid Total +

Schedule E (Government Option 4) Bid Total +

Schedule F (Government Option 5) Bid Total.

BID SCHEDULE

Project No : NP NER PMS BMS FY24(1) Schedule : A

Project Name : Northeast Region Pavement and Bridge Preservation Construction

(ELRO, HOFR, FIIS, SAGA, SAHI,

SARA, SPAR, VAMA)

Schedule Type : Base

AMD# Line Item Number

Pay Item Number

Description Supplemental Description

Quantity Unit Unit Price Amount

A0200 15101-0000 MOBILIZATION ALL LPSM

A0220 15201-0000

CONSTRUCTION

SURVEY AND

STAKING

ALL LPSM

A0240 15401-0000 CONTRACTOR

TESTING ALL LPSM

A0260 15701-0000 SOIL EROSION

CONTROL ALL LPSM

A0280 20301-3900

REMOVAL OF

PAVEMENT

MARKINGS, SYMBOLS

AND WORDS

10.000 EACH

A0300 20302-0150 REMOVAL OF BRIDGE

RAILING 50.000 LNFT

A0320 20302-2600

REMOVAL OF

PAVEMENT

MARKINGS

3,000.000 LNFT

A0340 41202-0000 TACK COAT 12.000 GAL

A0360 41301-0100

ASPHALT PAVEMENT

MILLING, 3/4-INCH

DEPTH

65.000 SQYD

A0380 41401-2000 CRACKS, CLEANING

AND SEALING 2,500.000 LNFT

A0400 41801-2000

ASPHALT CONCRETE

PAVEMENT PATCH,

TYPE 2

270.000 SQYD

A0420 43102-0000

THIN LIFT ASPHALT

CONCRETE

PAVEMENT

65.000 SQYD

A0440 55601-1300 BRIDGE RAILING,

TIMBER 50.000 LNFT

A0460 57501-0000

MINOR BRIDGE WORK (REMOVE DECK

DEBRIS AND TIGHTEN

BOLTS)

ALL LPSM

A0480 63401-0900

PAVEMENT

MARKINGS, TYPE E,

SOLID

3,000.000 LNFT

A0500 63405-1750

PAVEMENT

MARKINGS, TYPE E,

STRAIGHT ARROW

5.000 EACH

A0520 63405-1900

PAVEMENT

MARKINGS, TYPE E,

"STOP" WORD

MESSAGE

4.000 EACH

A0540 63405-2050

PAVEMENT

MARKINGS, TYPE E,

ACCESSIBILITY

SYMBOL

3.000 EACH

A0560 63501-0000 TEMPORARY TRAFFIC

CONTROL ALL LPSM

A0580 63701-0000 FIELD OFFICE 1.000 EACH

B-1Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, SAGA, SAHI, SARA, SPAR, VAMA)

A0600 64501-0000 LOCATE UTILITIES ALL LPSM

Submitted By: Schedule Total:

B-2Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, Project No : NP NER PMS BMS FY24(1) Schedule : B

Project Name : Northeast Region Pavement and Bridge Preservation Construction

(ELRO, HOFR, FIIS, SAGA, SAHI,

SARA, SPAR, VAMA)

Schedule Type : Option

AMD# Line Item Number

Pay Item Number

Description Supplemental Description

Quantity Unit Unit Price Amount

B0200 15101-0000 MOBILIZATION ALL LPSM

B0220 15201-0000

CONSTRUCTION

SURVEY AND

STAKING

ALL LPSM

B0240 15401-0000 CONTRACTOR

TESTING ALL LPSM

B0260 15701-0000 SOIL EROSION

CONTROL ALL LPSM

B0280 20301-0100 REMOVAL OF

BOLLARD 13.000 EACH

B0300 20301-3900

REMOVAL OF

PAVEMENT

MARKINGS, SYMBOLS

AND WORDS

2.000 EACH

B0320 20302-2600

REMOVAL OF

PAVEMENT

MARKINGS

700.000 LNFT

B0340 30303-4000 SHOULDER

RECONDITIONING 230.000 SQYD

B0360 41401-2000 CRACKS, CLEANING

AND SEALING 1,400.000 LNFT

B0380 41801-2000

ASPHALT CONCRETE

PAVEMENT PATCH,

TYPE 2

190.000 SQYD

B0400 60704-0000 CLEANING CULVERT

IN PLACE 1.000 EACH

B0420 61904-0000 BOLLARD POST 13.000 EACH

B0440 63304-0900

SIGNS, ALUMINUM

PANELS, TYPE 3

SHEETING

32.000 SQFT

B0460 63328-0000 SPEED BUMP 2.000 EACH

B0480 63401-0900

PAVEMENT

MARKINGS, TYPE E,

SOLID

700.000 LNFT

B0500 63405-1900

PAVEMENT

MARKINGS, TYPE E,

"STOP" WORD

MESSAGE

1.000 EACH

B0520 63405-2050

PAVEMENT

MARKINGS, TYPE E,

ACCESSIBILITY

SYMBOL

1.000 EACH

B0540 63501-0000 TEMPORARY TRAFFIC

CONTROL ALL LPSM

B0560 63701-0000 FIELD OFFICE 1.000 EACH

B0580 64501-0000 LOCATE UTILITIES ALL LPSM

Submitted By: Schedule Total:

B-3Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, Project No : NP NER PMS BMS FY24(1) Schedule : C

Project Name : Northeast Region Pavement and Bridge Preservation Construction

(ELRO, HOFR, FIIS, SAGA, SAHI,

SARA, SPAR, VAMA)

Schedule Type : Option

AMD# Line Item Number

Pay Item Number

Description Supplemental Description

Quantity Unit Unit Price Amount

C0200 15101-0000 MOBILIZATION ALL LPSM

C0220 15201-0000

CONSTRUCTION

SURVEY AND

STAKING

ALL LPSM

C0240 15401-0000 CONTRACTOR

TESTING ALL LPSM

C0260 15701-0000 SOIL EROSION

CONTROL ALL LPSM

C0280 20302-2600

REMOVAL OF

PAVEMENT

MARKINGS

520.000 LNFT

C0300 40702-1300 CHIP SEAL, TYPE 2C 620.000 SQYD

C0320 41202-0000 TACK COAT 220.000 GAL

C0340 41401-2000 CRACKS, CLEANING

AND SEALING 220.000 LNFT

C0360 63401-0100

PAVEMENT

MARKINGS, TYPE A,

SOLID

520.000 LNFT

C0380 63501-0000 TEMPORARY TRAFFIC

CONTROL ALL LPSM

C0400 63701-0000 FIELD OFFICE 1.000 EACH

C0420 64501-0000 LOCATE UTILITIES ALL LPSM

Submitted By: Schedule Total:

B-4Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, Project No : NP NER PMS BMS FY24(1) Schedule : D

Project Name : Northeast Region Pavement and Bridge Preservation Construction

(ELRO, HOFR, FIIS, SAGA, SAHI,

SARA, SPAR, VAMA)

Schedule Type : Option

AMD# Line Item Number

Pay Item Number

Description Supplemental Description

Quantity Unit Unit Price Amount

D0200 15101-0000 MOBILIZATION ALL LPSM

D0220 15201-0000

CONSTRUCTION

SURVEY AND

STAKING

ALL LPSM

D0240 15401-0000 CONTRACTOR

TESTING ALL LPSM

D0260 15701-0000 SOIL EROSION

CONTROL ALL LPSM

D0280 20301-3900

REMOVAL OF

PAVEMENT

MARKINGS, SYMBOLS

AND WORDS

15.000 EACH

D0300 20302-0500 REMOVAL OF CURB,

CONCRETE 45.000 LNFT

D0320 20302-2600

REMOVAL OF

PAVEMENT

MARKINGS

4,200.000 LNFT

D0340 21101-1000

ROADWAY

OBLITERATION,

METHOD 1

110.000 SQYD

D0360 40702-0300 CHIP SEAL, TYPE 1C 14,000.000 SQYD

D0380 41202-0000 TACK COAT 2,400.000 GAL

D0400 41301-0000 ASPHALT PAVEMENT

MILLING

(MICRO-MILLING) 210.000 SQYD

D0420 41401-2000 CRACKS, CLEANING

AND SEALING 1,400.000 LNFT

D0440 41801-2000

ASPHALT CONCRETE

PAVEMENT PATCH,

TYPE 2

310.000 SQYD

D0460 60901-0400 CURB, CONCRETE, 6-

INCH DEPTH 45.000 LNFT

D0480 61108-1000 ADJUST WATER

VALVE 1.000 EACH

D0500 63304-0900

SIGNS, ALUMINUM

PANELS, TYPE 3

SHEETING

14.000 SQFT

D0520 63401-0900

PAVEMENT

MARKINGS, TYPE E,

SOLID

4,400.000 LNFT

D0540 63405-1750

PAVEMENT

MARKINGS, TYPE E,

STRAIGHT ARROW

8.000 EACH

D0560 63405-2050

PAVEMENT

MARKINGS, TYPE E,

ACCESSIBILITY

SYMBOL

7.000 EACH

D0580 63501-0000 TEMPORARY TRAFFIC

CONTROL ALL LPSM

D0600 63701-0000 FIELD OFFICE 1.000 EACH

D0620 64501-0000 LOCATE UTILITIES ALL LPSM

B-5Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, Submitted By: Schedule Total:

B-6Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, Project No : NP NER PMS BMS FY24(1) Schedule : E

Project Name : Northeast Region Pavement and Bridge Preservation Construction

(ELRO, HOFR, FIIS, SAGA, SAHI,

SARA, SPAR, VAMA)

Schedule Type : Option

AMD# Line Item Number

Pay Item Number

Description Supplemental Description

Quantity Unit Unit Price Amount

E0200 15101-0000 MOBILIZATION ALL LPSM

E0220 15201-0000

CONSTRUCTION

SURVEY AND

STAKING

ALL LPSM

E0240 15401-0000 CONTRACTOR

TESTING ALL LPSM

E0260 15701-0000 SOIL EROSION

CONTROL ALL LPSM

E0280 20701-0800

SEPARATION-

STABILIZATION

GEOTEXTILE, CLASS

2, TYPE C

15.000 SQYD

E0300 25101-0200 PLACED RIPRAP,

METHOD A, CLASS 2 5.000 CUYD

E0320 31302-0000 AGGREGATE-

TOPSOIL COURSE 15.000 SQYD

E0340 41401-2000 CRACKS, CLEANING

AND SEALING 350.000 LNFT

E0360 41801-2000

ASPHALT CONCRETE

PAVEMENT PATCH,

TYPE 2

30.000 SQYD

E0380 55220-0000 REPAIR CONCRETE 5.000 SQYD

E0400 55225-0000 CLEAN AND RESEAL

JOINTS 110.000 LNFT

E0420 63501-0000 TEMPORARY TRAFFIC

CONTROL ALL LPSM

E0440 63701-0000 FIELD OFFICE 1.000 EACH

E0460 64501-0000 LOCATE UTILITIES ALL LPSM

Submitted By: Schedule Total:

B-7Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, Project No : NP NER PMS BMS FY24(1) Schedule : F

Project Name : Northeast Region Pavement and Bridge Preservation Construction

(ELRO, HOFR, FIIS, SAGA, SAHI,

SARA, SPAR, VAMA)

Schedule Type : Option

AMD# Line Item Number

Pay Item Number

Description Supplemental Description

Quantity Unit Unit Price Amount

F0200 15101-0000 MOBILIZATION ALL LPSM

F0220 15201-0000

CONSTRUCTION

SURVEY AND

STAKING

ALL LPSM

F0240 15401-0000 CONTRACTOR

TESTING ALL LPSM

F0260 15701-0000 SOIL EROSION

CONTROL ALL LPSM

F0280 20302-0500 REMOVAL OF CURB,

CONCRETE 30.000 LNFT

F0300 20302-0600 REMOVAL OF CURB,

STONE 10.000 LNFT

F0320 20303-3100 REMOVAL OF

SIDEWALK, BRICK 1.000 SQYD

F0340 30303-4000 SHOULDER

RECONDITIONING 64.000 SQYD

F0360 31302-0000 AGGREGATE-

TOPSOIL COURSE 64.000 SQYD

F0380 41401-2000 CRACKS, CLEANING

AND SEALING 170.000 LNFT

F0400 41801-2000

ASPHALT CONCRETE

PAVEMENT PATCH,

TYPE 2

5.000 SQYD

F0420 50202-0000 SEALING JOINTS AND

CRACKS 390.000 LNFT

F0440 60412-2000

REMOVE AND RESET

MANHOLE FRAME

AND COVER

1.000 EACH

F0460 60901-0400 CURB, CONCRETE, 6-

INCH DEPTH 30.000 LNFT

F0480 60901-2900 CURB, STONE, TYPE

1, 6-INCH DEPTH 10.000 LNFT

F0500 60910-0000 RESET CURB (STONE) 60.000 LNFT

F0520 61201-0000 SEWER SYSTEM (ADJUST SEWER) ALL LPSM

F0540 61501-1000 SIDEWALK, BRICK 1.000 SQYD

F0560 61508-0200 RESET BRICK

SIDEWALK 15.000 SQYD

F0580 62502-0000 TURF

ESTABLISHMENT 64.000 SQYD

F0600 63501-0000 TEMPORARY TRAFFIC

CONTROL ALL LPSM

F0620 63701-0000 FIELD OFFICE 1.000 EACH

F0640 64501-0000 LOCATE UTILITIES ALL LPSM

Submitted By: Schedule Total:

B-8Bid Schedule Project: NP NER PMS BMS FY24(1), Northeast Region Pavement and Bridge Preservation Construction (ELRO, HOFR, FIIS, B-9

BID SUMMARY

Project NP NER PMS BMS FY24(1)

(1) Schedule A (Base Contract) BID Total (from Page B-2) =

(2) Schedule B (Government Option 1) BID Total (from Page B-3) =

(3) Schedule C (Government Option 2) BID Total (from Page B-4) =

(4) Schedule D (Government Option 3) BID Total (from Page B-6) =

(5) Schedule E (Government Option 4) BID Total (from Page B-7) =

(6) Schedule F (Government Option 5) BID Total (from Page B-8) =

(1) $_________________________

(2) $_________________________

(3) $_________________________

(4) $_________________________

(5) $_________________________

(6) $_________________________

Total Price of Project (for evaluation purposes only)

EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) + (3) + (4) + (5) + (6) $_________________________

Maximum Time Allowed for the Contract if Schedules A, B, C, D, E and F are Awarded at the Same Time:

If the Government awards the contract as Schedules A + B + C + D + E + F, the performance period to complete all contract work will be 78 calendar days.

Maximum Time Allowed for Each Schedule of Work if Awarded Separately:

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 17 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 13 calendar days and will start on the effective date of Schedule B’s Notice to

Proceed.

If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 22 calendar days and will start on the effective date of Schedule C’s Notice to

Proceed.

If Schedule D (Government Option 3) is…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .