IFB Package_Cherrywood Dr _ Keel Ct Waterline Repalcements Project EAM8.7.25.pdf
PDF 2 MB Posted
- Solicitation number
- IFB-25-20-PW
- Issued by
- Boulder County, Lakewood City, Colorado
About this file
This document is an Invitation for Bid (IFB) package for the City of Lafayette Public Works Department's Cherrywood Dr. & Keel Ct. Waterline Replacements Project in Lafayette, Colorado. The project involves replacing approximately 2,185 linear feet of watermain across three general locations: N Cherrywood Dr from Sprucewood Ct to E Cherrywood Dr, S Cherrywood Dr from W Cherrywood Dr to Autumn Ridge Blvd, and Keel Ct from Paschal Dr to Waneka Lake Tr. The work includes installing fire hydrants, gate valves, associated pavement improvements, temporary water supply, and all necessary project components. Bids will be received via BidNet until 5:00 p.m. on Friday, August 29th, 2025, with a mandatory pre-bid conference scheduled for August 14th, 2025. The contract is anticipated to be awarded on or about September 2nd, 2025, with a 60-calendar day completion timeframe once work begins.
The total project cost is structured through unit price bidding, with the contractor responsible for providing performance and payment bonds equal to 100% of the contract price. The bid includes two schedules: Schedule A for N and S Cherrywood Dr. Waterline Replacement and Schedule B for Keel Ct. Waterline Replacement. Each schedule contains line items for traffic control, mobilization, landscape removal and replacement, pavement and concrete removal and replacement, waterline installation, fittings, valves, and fire hydrant assemblies. The project will be funded through the City of Lafayette's public works budget, with account number 41-701-941000. Liquidated damages are set at $500 per day for delays in substantial completion or final completion, and the contractor will be required to provide comprehensive insurance coverage and comply with local regulations and specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 04 - Contractor_s Bid.xlsx | XLSX spreadsheet | |
| 2025-05-01 Geotech Report - Lafayette Waterlines.pdf | ||
| 240355-001 Lafayette Waterlines - Stamped Construction Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Lafayette Public Works Department
CONTRACT DOCUMENTS
FOR
CHERRYWOOD DR & KEEL CT WATERLINE
REPLACEMENTS PROJECT
LAFAYETTE, COLORADO
City of Lafayette – Public Works Department 1290 S. Public Rd
Lafayette, Colorado 80026
August 2025
INVITAT ION FOR
BI D
IFB-25-20-PW
Project: Cherrywood Dr & Keel Ct Waterline Replacements Project
Contractor:
Design Professional: Professional Engineering Consultants (PEC) Total Cost:
Term:
Acct. or P.O. # 41-701-941000
TABLE OF CONTENTS
# of Pages
Invitation to Bid 2
Contractor’s Bid 9
Bid Bond 2
Notice of Award 2
Construction Contract 10
Performance Bond 5
Payment Bond 5
Notice to Proceed Construction Contract General Conditions Special Construction Provisions Temporary Water Service Landscaping
CONTRACT DRAWINGS
No. Title
C101 COVER SHEET
C102 GENERAL NOTES
VF101 OVERALL EXISTING CONDITIONS KEY
VF102-103 EXISTING CONDITIONS N CHERRYWOOD DR
VF104 EXISTING CONDITIONS S CHERRYWOOD DR
VF105 EXISTING CONDITIONS KEEL CT
CU101 OVERALL UTILITY PLAN
CU201-203 WATERLINE PLAN & PROFILE N CHERRYWOOD DR
CU204-205 WATERLINE PLAN & PROFILE S CHERRYWOOD DR
CU206 WATERLINE PLAN & PROFILE KEEL CT
CU501-503 UTILITY DETAILS
L101 LANDSCAPE PLAN
Contractor:____________________
Design Professional: Professional Engineering Consultants (PEC)
Total Cost: ____________________
Term: _______________________
Acct. or P.O. #: 41-701-941000________________
HRO #686627 v1 Invitation to Bid
Form Approved by City Attorney on 1/22/01
INVITATION TO BID
I. RECEIPT OF BIDS
Proposals will be received by the City of Lafayette, via BidNet, until 5:00 p.m. on Friday, August 29th, 2025 for the construction of CHERRYWOOD DR & KEEL CT WATERLINE
REPLACEMENTS PROJECT in accordance with the Plans, Contract Documents and
Specifications prepared by Professional Engineering Consultants (PEC).
II. DESCRIPTION OF WORK
The project is inclusive of three (3) general locations; N Cherrywood Dr from Sprucewood
Ct to E Cherrywood Dr, S Cherrywood Dr from W Cherrywood Dr to Autumn Ridge Blvd, and
Keel Ct from Paschal Dr to Waneka Lake Tr.
The Work includes, but is not necessarily limited to furnishing labor, materials, and equipment for the construction of the following:
Cherrywood Dr & Keel Ct Waterline Replacements including:
• Approximately 2,185 linear feet of watermain;
• Fire hydrants, gate valves, and all appurtenances associated with the work;
• Associated pavement improvements;
• Temporary water supply; and
• All other items necessary to complete the project, including traffic/pedestrian control, erosion control, demolition, etc. as detailed in the Drawings and
Specifications.
III. DOCUMENT INSPECTION AND PROCUREMENT
A copy of the Contract Documents may be viewed and downloaded from the solicitation posted on BidNet.
Questions regarding the documents may be submitted through BidNet until 5:00 pm Friday, August 15th, 2025.
IV. BONDS
Each bid shall be accompanied by a bid guarantee bond, or a certified or cashier's check payable to the order of the City of Lafayette in an amount not less than five (5) percent of the
HRO #686627 v1 Invitation to Bid
Form Approved by City Attorney on 1/22/01 amount of the bid as a guarantee that the bidder will execute the Contract, if awarded, in conformity with the bid form.
The bidder to whom a Contract is awarded shall be required to furnish both a Performance
Bond and Payment Bond acceptable to the City of Lafayette for 100% of the Contract Price for each bond, in accordance with the requirements of the Contract Documents.
V. CONTRACT AWARD
The Contract will be awarded or bids rejected no earlier than September 2nd, 2025. The
City of Lafayette may reject any and all bids. The City of Lafayette reserves the right to reject any and all Bids, waive any informalities in bidding or to accept the Bid (or Bids) that best serve the interest of the City, including but not limited to contract price, schedule, and contractor qualifications.
VI. SCHEDULE
Time for completion of the Work as proposed by the Contractor will be as required in the
Contract Documents. The current schedule calls for award of the Contract on or about September
2nd, 2025. The Contract Time shall commence to run on the date specified in the Notice to Proceed.
The Contract Time will be 60 calendar days once work has begun.
VII. PRE-BID CONFERENCE
A mandatory pre-bid conference will be held by the City of Lafayette on August 14th, 2025 at 10:00 am, located at City of Lafayette City Hall, 1290 S. Public Rd, Lafayette, CO
80026. Bidders are required to attend and are encouraged to voice questions regarding the
Contract Documents. If a Bidder is unable to attend, they will be ineligible for consideration of award of contract.
The following Proposal is hereby made to:
1290 S Public Road
Lafayette, CO 80026
Dollars and
Cents ($ ), based on unit prices.
The undersigned hereby acknowledges receipt of the following Addenda:
Project: Cherrywood Dr & Keel Ct Waterline Replacements Project
Contractor:
Design Professional: Professional Engineering Consultants (PEC)
II. STIPULATED AMOUNT
The undersigned hereby propose and agree to furnish all the necessary labor, material, equipment, tools, and services necessary for the construction of the Cherrywood Dr & Keel Ct Waterline
Replacements Project for the City of Lafayette all in accordance with the Contract Documents prepared by Professional Engineering Consultants (PEC) for the following stipulated amount:
III. KNOWLEDGE OF LOCAL CONDITIONS AND CONTRACT DOCUMENTS
VI. ADDENDA
Within fifteen (15) Business Days after being awarded the Contract, the undersigned agrees to execute the form of Agreement included in Contract Documents, and to furnish a Performance Bond and Payment Bond, both in an amount equal to one hundred percent (100%) of the Contract amount on the forms provided in these documents.
The undersigned has examined the location of the proposed work, as well as Contract Documents and is familiar with the local conditions present where the work is to be performed.
IV. PROPOSAL GUARANTY
The Proposal Guaranty attached, without endorsement, in the sum of not less than five percent (5%) of the amount of the Proposal, is furnished to the CITY as a guarantee that the Agreement will be executed and a Performance Bond and a Payment Bond will be furnished within ten (10) Business
Days after award of the Contract to the undersigned, or that the undersigned will pay to the CITY the difference between the stipulated amount of this Contractor’s Bid and such larger amount for which the CITY may in good faith contract with another party to perform the work covered by this
Proposal, provided that such payment shall be limited to the amount of the Proposal Guaranty.
V. EXECUTION OF AGREEMENT AND FURNISHING BONDS
Total Cost:
Term:
Acct. or P.O. #: 41-701-941000
CONTRACTOR'S BID - ADDENDUM
I. RECIPIENT
Item Qty Unit Price
a. 1.0 LS
VII. STATEMENT OF ITEMS
Description Item Total
Addendum No. Dated
Definitions for Measurement and Payment of Work items in this Contract are described below. The descriptions below are not intended to be comprehensive listings of each and every work item included in each bid item. The descriptions are intended to supplement the Contract Documents and in no way relieve the Contractor from properly completing the work for each bid item.
Bid Schedule A: N and S Cherrywood Dr Waterline Replacement
Traffic Control - Traffic control shall be paid for on a lump sum basis, and shall include all labor, equipment, materials, supervision, and incidentals required to complete the work. No separate payment will be made for additional traffic control measures required due to Contractor’s means and methods or sequencing.
Preparation and submittal of Traffic Control Plans.
Installation and maintenance of signs, barricades, cones, flaggers, detour routes, and temporary pavement markings
Providing flagging operations and/or traffic control personnel as needed
Coordination with local agencies and emergency services
Daily inspection and adjustment of traffic control devices
Prompt removal of all traffic control devices upon completion or as directed
Traffic Control
Change Order
Form Approved by City Attorney on DATE
a. 1.0 LS
3 1,170.0 SY
4 1,170.0 SF
5 3.0 EA
6 10.0 EA
Mobilization
Remove & Replace Asphalt Pavement -
Includes sawcutting, removal & disposal of existing pavement and placement of road base and new pavement sections.
Mobilization - Mobilization: No separate measurement for payment will be made for any labor, equipment, and materials required for this item. The lump sum price will include all of the
Contractor's costs. This bid item includes, but is not limited to installing / removing temporary fencing around project work areas and any other fencing/security items as deemed necessary by the contractor, miscellaneous Erosion Control Measures, including items shown on the drawings and specifications as erosion control measures, including but not limited to maintaining and submitting
City of Lafayette Erosion and Sediment Control Field Inspection Checklist, silt fence, culvert protection, inlet protection, check dam, protected staging area, vehicle tracking control, street cleaning/sweeping, erosion control blankets, concrete washout area and other items associated with erosion control, preparation and maintaining traffic control plans, obtaining and transferring permits, providing required bonds and insurance, preparing and maintaining the project schedule, delivering and removing the Contractor's equipment, supplies, and excess materials, and cleaning up the site, restoring the project site to pre-project or final grades and conditions, preparing submittals, preparing record drawings, preparing and providing copies of stormwater and other required plans/reports, potholing existing utilities, verifying elevations of existing utilities are not in conflict with proposed design, notify existing utility companies of construction operations and confirm that all their utilities were located, providing all other related and necessary labor, equipment, and materials to complete the work.
Payment will be based on the percentage of completed and accepted work. Fifty (50) percent of the lump sum price will be paid at the time of the first monthly progress payment; an additional thirty
(30) percent will be paid when one-half the original contract amount is earned. The remaining twenty (20) percent will be paid upon final acceptance of the project. The total amount for mobilization will not exceed five (5) percent of the total bid, for the lump sum price of:
Abandon Existing Hydrant - Includes removal of hydrant, cutting riser min 2ft.
below surface, filling riser with grout, backfilling and seeding as required.
Abandon Existing Waterline - Cap & Fill
Ends with Grout
Remove & Replace Concrete - Includes sawcutting, removal & disposal of existing concrete and placement of new concrete as detailed on drawings.
a. 1,820.0 LF
b. 15.0 LF
c. 50.0 LF
a. 5.0 EA
b. 2.0 EA
c. 1.0 EA
d. 14.0 EA
e. 1.0 EA
f. 200.0 LF
g. 1.0 EA
h. 1.0 EA
14" Bend
2" Insulated Board
8" X 8" Cross
12" X 8" Reducer
Water Pipeline Installation - Includes furnishing and handling all required equipment and materials, locating existing pipelines and utilities, all excavation, de-watering, removal of existing pipe where required, pipe installation, support of all existing utilities, couplings, tracer wires, pipe restraint devices, bedding-zone and pipe-zone backfill material, backfilling, compaction, flushing, testing, disinfecting, temporary and permanent plugs, all surface restoration (except those items specifically listed hereinafter in the Proposal, at the unit price per lineal foot of pipeline in place, measured from end of pipe or center of fittings:
Waterline Fittings - Includes furnishing, handling, and installation of pipeline fittings and thrust blocks, as detailed on the Drawings, and wrapping in polyethylene sheathing and pipe restraints, at the unit price over and above the costs of the water pipelines:
Water Pipeline Valves - Includes furnishing, handling, and installing butterfly valves and valve boxes, extension keys, retainer glands, or tie rods, as shown on the
Drawings, wrapping in polyethylene sheathing, and all other items necessary to complete the valve installations, at the unit price over and above the costs of the water pipelines:
8" Bend
12" X 8" Tee
14" PVC Pipe incl. Trenching, Bedding, &
Backfill
8" PVC Pipe incl. Trenching, Bedding, &
Backfill
12" PVC Pipe incl. Trenching, Bedding, &
Backfill
8" X 8" Tee
14" X 8" Tee
a. 24.0 EA
b. 2.0 EA
c. 2.0 EA
a. 3.0 EA
12 42.0 EA
13 1.0 LS
14 1.0 LS $15,000.00
Item Qty Unit Price
a. 1.0 LS
2 1.0 LS
Landscape Removal & Replacement
Fire Hydrant Assemblies
Reconnect Service Taps - Includes furnishing and installing all items, including double strap bronze saddle, corp stop, fittings and connection to service lines
8" Gate Valve
12" Gate Valve
14" Butterfly Valve
Fire Hydrant Assembly - Includes furnishing, handling, and installing all required equipment and materials, all excavation, fire hydrant, swivel tees, gate valve and box, 6” PVC pipe, 6” thrust blocks, pipe restraints, gravel drain material, tracer wire, flushing and testing, backfill and compaction, and all other items necessary to complete installation of the fire hydrant assemblies as shown on the drawings and described in the specifications, at the unit price of:
Total Schedule A: $15,000.00
Traffic Control
Mobilization - See Item 2 description above.
Minor Contract Revisions - This line item is intended solely for unforeseen conditions or changes in scope that are not otherwise covered under the base contract. Use of any contingency funds is strictly prohibited without the prior written approval of the City
$15,000.00
Bid Schedule B: Keel Ct Waterline Replacement
Description Item Total
Traffic Control - See Item 1 description above.
3 1.0 LS
a. 1.0 LS
5 308.0 SY
6 1,396.0 SF
7 2.0 EA
a. 530.0 LF
b. 36.0 LF
Water Pipeline Installation - Includes furnishing and handling all required equipment and materials, locating existing pipelines and utilities, all excavation, de-watering, removal of existing pipe where required, pipe installation, support of all existing utilities, couplings, tracer wires, pipe restraint devices, bedding-zone and pipe-zone backfill material, backfilling, compaction, flushing, testing, disinfecting, temporary and permanent plugs, all surface restoration (except those items specifically listed hereinafter in the Proposal, at the unit price per lineal foot of pipeline in place, measured from end of pipe or center of fittings:
Temporary Water Service - Lump sum to provide temporary service as described in specification section 01 51 36.
Landscape Removal & Replacement
Landscape Removal & Replacement - to be paid on a lump sum basis. The price shall include all materials, labor, equipment, maintenance during the establishment period, and any related costs necessary for a complete and accepted installation.
Scope includes, but is not limited to:
Site preparation (clearing, grubbing, soil amending, grading, and finish grading);
Supply and installation of topsoil, mulch, and soil additives;
Planting of trees, shrubs, groundcover, and other specified vegetation;
Seeding or sodding of lawn areas, including hydroseeding where required;
Irrigation system repair, installation, testing, and adjustments;
Weed control, erosion control, and protective measures;
Initial maintenance and watering period, one year; and
Removal and disposal of all excess materials and cleanup of site.
Abandon Existing Waterline - Install Cap
& Fill Ends with Grout
8" PVC Pipe incl. Trenching, Bedding, &
Backfill
12" PVC Pipe incl. Trenching, Bedding, &
Backfill
Remove & Replace Asphalt Pavement -
Includes sawcutting, removal & disposal of existing pavement and placement of road base and new pavement sections.
Remove & Replace Concrete - Includes sawcutting, removal & disposal of existing concrete and placement of new concrete as detailed on drawings.
a. 5.0 EA
b. 2.0 EA
c. 14.0 EA
d. 20.0 LF
e. 20.0 LF
f. 1.0 EA
g. 2.0 EA
a. 6.0 EA
b. 3.0 EA
a. 3.0 EA
16" C900 Casing Pipe
Fire Hydrant Assemblies
8" Gate Valve
12" Gate Valve
12" X 8" Reducer
8" Bend
24" C900 Casing Pipe
Waterline Fittings - Includes furnishing, handling, and installation of pipeline fittings and thrust blocks, as detailed on the Drawings, and wrapping in polyethylene sheathing and pipe restraints, at the unit price over and above the costs of the water pipelines:
Water Pipeline Valves - Includes furnishing, handling, and installing butterfly valves and valve boxes, extension keys, retainer glands, or tie rods, as shown on the
Drawings, wrapping in polyethylene sheathing, and all other items necessary to complete the valve installations, at the unit price over and above the costs of the water pipelines:
Fire Hydrant Assembly - Includes furnishing, handling, and installing all required equipment and materials, all excavation, fire hydrant, swivel tees, gate valve and box, 6” PVC pipe, 6” thrust blocks, pipe restraints, gravel drain material, tracer wire, flushing and testing, backfill and compaction, and all other items necessary to complete installation of the fire hydrant assemblies as shown on the drawings and described in the specifications, at the unit price of:
8" X 8" Tee
12" X 8" Tee
8" X 8" Cross
12 12.0 EA
13 1.0 LS $15,000.00
• Public Right of Way Accessibility Guidelines (PROWAG)
• Architectural Barriers Act
• Colorado Department of Transportation (CDOT)
• Manual on Uniform Traffic Control Devices (MUTCD)
• American Water Works Association (AWWA)
• Colorado Department of Public Health & Envrionment (CDPHE)
CONTRACTOR
VIII. OWNER'S RIGHT RESERVED
VII. CONTRACT TIME
All work shall be completed within calendar days after the issuance of the Notice to Proceed. The CITY anticipates issuance of the Notice to
Proceed within ten (10) calendar days from the date of the Notice of Award.
Furthermore, the CONTRACTOR agrees that failure to complete the Contract within the time proposed, including any extension thereof, shall be considered a breach of the Contract, and entitles the CITY to liquidated damages as specified in Article 3 of the Construction Contract.
Contractor to construct all Work in compliance with current applicable accessibility standards and specifications as required by the following:
2010 ADA Standards for Accessible Design
Total Schedule B: $15,000.00
Total Proposal: $30,000.00
Minor Contract Revisions - This line item is intended solely for unforeseen conditions or changes in scope that are not otherwise covered under the base contract. Use of any contingency funds is strictly prohibited without the prior written approval of the City
$15,000.00
Reconnect Service Taps - Includes furnishing and installing all items, including double strap bronze saddle, corp stop, fittings and connection to service lines
The undersigned understands that the CITY reserves the right to reject any or all Proposals and to waive any formality or technicality in any Proposal in the interest of the CITY.
IX. THE ABOVE PROPOSAL IS HEREBY RESPECTFULLY SUBMITTED BY:
Business Name an individual a Colorado corporation a Colorado partnership a Colorado limited liability company as an independent contractor
City State Zip Code
By Title
Date
Business Address
Contractor: ___________________ Design Professional: Professional Engineering Consultants (PEC) Total Cost: ___________________ Term:
Acct. or P.O. #: 41-701-941000_______________ Bond No. ___________________
HRO #686651 v1 Bid Bond Form Approved by City Attorney on 1/22/01
BID BOND
KNOW ALL MEN BY THESE PRESENTS: that [insert name and address of Contractor] as Principal, hereinafter called CONTRACTOR, and [insert name and address of Surety] as Surety, hereinafter called SURETY, are held and firmly bond unto
1290 S. Public Road Lafayette, CO 80026 as Obligee, hereinafter called CITY, in the amount of _________________________________ Dollars ($_______________), for the payment whereof CONTRACTOR and SURETY bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, CONTRACTOR has submitted a Bid dated ___________________, 20__, in accordance with the Invitation to Bid issued by CITY, which Bid is by reference made a part hereof, and is hereinafter referred to as the Bid.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if CONTRACTOR shall promptly comply with all requirements of the Notice of Award dated _______________________, 20__, then this obligation shall be null and void; otherwise, the amount of this Bond shall be paid to the CITY upon demand.
Signed and sealed this _______ day of ___________, 20__.
HRO #686651 v1 Bid Bond
[CONTRACTOR] [SURETY]
[Name, Title] [Name, Title]
ATTTEST: ATTEST:
[Title] [Title]
Design Professional: Professional Engineering Consultants (PEC) Total Cost:
Term:
Acct. or P.O. #: 41-701-941000
HRO # 686744 v1 Notice of Award
NOTICE OF AWARD
Dated: _________________
To:
Owner: CITY OF LAFAYETTE; PUBLIC WORKS (“CITY”)
You are hereby notified that your Bid dated _______________, 20__, for the above Contract has been considered. You are the apparent Successful Bidder and have been awarded a contract:
☐for the total Work for the Project.
☐for construction of : CHERRYWOOD DR & KEEL CT WATERLINE
REPLACEMENTS PROJECT
The Contract Price of your Contract is _______________________________
You must comply with the following conditions precedent within 15 days of this Notice of Award, that is by _____________________________________________________________.
1. You must deliver to CITY two fully executed counterparts of the Construction Contract, including all the Contract Documents. Each of the Contract Documents must bear your signature on the cover of each Contract Document and where specified throughout each Document.
2. You must deliver with the executed Construction Contract, the Bonds and Certificates of Insurance as specified in Article V of the General Conditions and Supplementary Conditions.
HRO # 686744 v1 Notice of Award
Failure to comply with these conditions within the time specified will entitle CITY to consider your Bid in default, to annul this Notice of Award and to declare your Bid Security forfeited.
Within 10 days after you comply with the above conditions, CITY will return to you one fully signed counterpart of the Construction Contract with the Contract Documents attached.
CITY OF LAFAYETTE; PUBLIC WORKS DEPARTMENT
Chair
Acceptance of Award: Attest:
Contractor Secretary
Copy to Design Professional
Construction Contract (Construction of Public Works $150,000 or More City of Lafayette, 1290 South Public Road, Lafayette, CO 80026; Phone: 303-665-5588
Form Approved by City Attorney August 2022 Page 1
Project: Cherrywood Dr & Keel Ct Waterline Replacements Project Contractor:
Design Professional: Professional Engineering Consultants (PEC) Total Cost:
Acct. or P.O. # 41-701-941000
CONSTRUCTION CONTRACT
FOR CONSTRUCTION OF PUBLIC WORKS $150,000 OR MORE
THIS AGREEMENT (“Agreement”) is dated as of the ____ day of _______________ , 20___, by and between the City of Lafayette, Colorado, a Colorado home rule city and municipal corporation, (hereinafter called CITY), and ________________________________________, whose address is __________________________________(hereinafter called CONTRACTOR).
CONTRACTOR agrees to work for CITY as an independent contractor, on the following terms and conditions contained in this Agreement.
CITY and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:
ARTICLE 1
WORK
1.1. “Project”: The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:
CHERRYWOOD DR & KEEL CT WATERLINE REPLACEMENTS PROJECT, which consists of watermain replacements and other materials per the Construction Documents prepared by Professional Engineering Consultants (PEC) (“DESIGN PROFESSIONAL”), dated July 25, 2025.
1.2. “Work”: CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows:
Cherrywood Dr & Keel Ct Waterline Replacements including, approximately 2,185 linear feet of watermain, fire hydrants, gate valves, and all appurtenances associated with the work as specified in the plans, pavement improvements, sidewalk improvements, temporary water supply, and all other items necessary to complete the project, including traffic/pedestrian control, demolition, etc.
as detailed in the Drawings and Specifications.
1.3. “Site”: The Site is the place where the Project is located, specifically N Cherrywood Dr from Sprucewood Ct to E Cherrywood Dr, S Cherrywood Dr from W Cherrywood Dr to Autumn Ridge Blvd, and Keel Ct from Paschal Dr to Waneka Lake Tr.
Form Approved by City Attorney August 2022 Page 2
ARTICLE 2
DESIGN PROFESSIONAL
This Project has been designed by: Professional Engineering Consultants (PEC), who is hereinafter called DESIGN PROFESSIONAL and who is to act as CITY's representative, assume all duties and responsibilities and have the rights and authority assigned to DESIGN PROFESSIONAL in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents.
ARTICLE 3
CONTRACT TIMES
3.1. The Work will be substantially completed within 60 days after the date when the
Contract Times commence to run as provided in paragraph 2.3. of the General Conditions and completed and ready for final payment in accordance with paragraph 14.9. of the General Conditions within 90 days after the date when the Contract Times commence to run.
3.2. Liquidated Damages: CITY and CONTRACTOR recognize that time is of the essence of this Agreement and that CITY will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1. above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense and difficulties involved in proving the actual loss suffered by CITY if the Work is not completed on time. Accordingly, instead of requiring any such proof, CITY and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay CITY five hundred dollars and zero cents ($500.00) for each day that expires after the time specified in paragraph 3.1 for Substantial Completion until the Work is substantially complete. After Substantial Completion, if CONTRACTOR shall neglect, refuse or fail to complete the remaining Work within the time specified in paragraph 3.1 for completion and readiness for final payment or any proper extension thereof granted by CITY, CONTRACTOR shall pay CITY five hundred dollars and zero cents ($500.00) for each day that expires after the time specified in paragraph 3.1 for completion and readiness for final payment or after actual Substantial Completion, whichever is later. Liquidated damages for delay in reaching substantial completion and liquidated damages for delay in reaching completion and readiness for final payment shall not accrue simultaneously.
ARTICLE 4
CONTRACT PRICE
CITY shall pay CONTRACTOR for completion of the Work in accordance with the
Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to paragraphs 4.1 and 4.2. below:
4.1. for all work other than Unit Price Work, a Lump Sum of: NOT APPLICABLE
Form Approved by City Attorney August 2022 Page 3
All specific cash allowances are included in the above price and have been computed in accordance with paragraph 11.8. of the General Conditions; plus: NOT APPLICABLE
4.2. For all Unit Price Work, an amount equal to the sum of the established unit price for each separately identified item of Unit Price Work times the estimated quantity of that item as indicated in this paragraph 4.2.:
As set forth in section VII., “STATEMENT OF ITEMS,” of the CONTRACTOR’s BID of the contract documents.
TOTAL OF ALL UNIT PRICES ________________________________ ($_____________)
(use words) figures
As provided in paragraph 11.9 of the General Conditions estimated quantities are not guaranteed, and determinations of the actual quantities and classifications are to be made by DESIGN PROFESSIONAL as provided in paragraph 9.8 of the General Conditions. Unit prices have been computed as provided in paragraph 11.9.2 of the General Conditions.
4.3. CITY has appropriated funds equal to or in excess of the Contract Price.
ARTICLE 5
PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by DESIGN PROFESSIONAL as provided in the General Conditions.
5.1. Progress Payments; Retainage: CITY shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Applications for Payment as recommended by DESIGN PROFESSIONAL, on or about the 3rd Thursday of each month during construction as provided herein. All such payments will be measured by the schedule of values established in paragraph 2.7 of the General Conditions (and in the case of Unit Price Work, based on the number of units completed) or, in the event there is no schedule of values, as provided in the Specifications.
5.1.1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as DESIGN PROFESSIONAL shall determine, or CITY may withhold, in accordance with paragraph 14.4.4 of the General Conditions:
• 95% of Work completed, with the balance being retainage. The withheld percentage of the contract price shall be retained until the contract is completed satisfactorily and finally accepted by CITY.
• 95% of materials and equipment not incorporated in the Work (but delivered, suitably stored and accompanied by documentation satisfactory
Form Approved by City Attorney August 2022 Page 4 to CITY as provided in paragraph 14.2. of the General Conditions), with the balance being retainage.
The withheld percentage of the contract price shall be retained until the contract is completed satisfactorily and finally accepted by CITY.
5.1.2. Upon Substantial Completion, payments shall be made in an amount sufficient to increase total payments to CONTRACTOR to at least 95% of the Contract Price, if in the opinion of the CITY, satisfactory progress had been made in the Work, (with the balance being retainage), less such amounts as DESIGN PROFESSIONAL shall determine, or CITY may withhold, in accordance with paragraph 14.4.4 of the General
5.1.3. Whenever CONTRACTOR receives payment pursuant to this paragraph
5.1., CONTRACTOR shall make payments to each of its Subcontractors of any amounts actually received that were included in CONTRACTOR’s request for payment to CITY for such Subcontracts. CONTRACTOR shall make such payments within seven calendar days of receipt of payment from CITY in the same manner as CITY is required to pay CONTRACTOR pursuant to this paragraph 5.1 if the Subcontractor is satisfactorily performing under its contract with CONTRACTOR. CONTRACTOR shall be relieved of the requirements of this paragraph regarding payment in seven days and the payment of interest until its Subcontractor submits the list required by paragraph 5.1.4. Nothing in this paragraph 5.1.3 shall be construed to affect the retention provisions of this Agreement, or the CONTRACTOR’S obligation to pay Subcontractors pursuant to Section 24-91-103, C.R.S. (as amended).
5.1.4. CONTRACTOR shall include a provision in all of its subcontracts requiring its Subcontractors to pay all Suppliers, sub-subcontactors, and laborers any amounts actually received that were included in the Subcontractor’s request for payment to CONTRACTOR for such persons, in the same manner set forth in this paragraph 5.1 regarding payments by CONTRACTOR to the Subcontractor. Further, all said subcontracts shall include a provision that at the time the Subcontractor submits a request for payment to the CONTRACTOR, the Subcontractor shall also submit to the CONTRACTOR a list of the Subcontractor’s Suppliers, sub-subcontractors, and laborers.
5.2. Final Payment: Upon final completion and acceptance of the Work in accordance with paragraph 14.9 of the General Conditions, CITY shall pay the remainder of the Contract Price as recommended by DESIGN PROFESSIONAL as provided in said paragraph 14.9.
5.3. No Lien Rights: CONTRACTOR understands that this is a contract for the construction or repair of a public building or public work, and is therefore governed by C.R.S. §§ 38-26-105 through 107. CONTRACTOR further understands that these statutory provisions are in lieu of any lien rights. CONTRACTOR further understands that failure on the part of CONTRACTOR, any Subcontractor, Supplier, sub-subcontractor or laborer furnishing labor or supplies to the Work must follow the said statutory provisions in filing any claim for payment, and that failure on the part of any such claimant to comply with said statutory requirements, shall
Form Approved by City Attorney August 2022 Page 5 relieve CITY from any liability for making payment to such claimant. CONTRACTOR agrees to include this provision in any and all subcontracts.
ARTICLE 6
INTEREST
6.1 All moneys not paid when due as provided in Article 14 of the General Conditions shall bear interest at a rate not to exceed 1.5%.
6.2 If CONTRACTOR fails to make timely payments to any subcontractors as required by C.R.S. § 24-91-103 or this Agreement, CONTRACTOR or its subcontractors may be responsible to pay subcontractor(s) interest at the rate of fifteen percent (15%) per annum on the amount of the payment which was not made in a timely manner.
ARTICLE 7
CONTRACTOR’S REPRESENTATIONS
In order to induce CITY to enter into this Agreement, CONTRACTOR makes the following representations:
7.1. CONTRACTOR has examined and carefully studied the Contract Documents (including the Addenda listed in Article 8 herein) and the other related data identified in the Bidding Documents, including "technical data."
7.2. CONTRACTOR has visited the site and become familiar with and is satisfied as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work.
7.3. CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress, performance and furnishing of the Work.
7.4. CONTRACTOR has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) that have been identified in the Supplementary Conditions as provided in paragraph 4.2.1 of the General Conditions. CONTRACTOR accepts the determination set forth in paragraph SC-4.2. of the Supplementary Conditions of the extent of the "technical data" contained in such reports and drawings upon which CONTRACTOR is entitled to rely as provided in paragraph 4.2 of the General Conditions. CONTRACTOR acknowledges that such reports and drawings are not Contract Documents and may not be complete for CONTRACTOR’s purposes.
CONTRACTOR acknowledges that CITY and DESIGN PROFESSIONAL do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the site.
CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all such additional supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to
Form Approved by City Attorney August 2022 Page 6 the site or otherwise which may affect cost, progress, performance or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto. CONTRACTOR does not consider that any additional examinations, investigations, explorations, tests, studies or data are necessary for the performance and furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents.
7.5. CONTRACTOR is aware of the general nature of work to be performed by CITY and others at the site that relates to the Work as indicated in the Contract Documents.
7.6. CONTRACTOR has correlated the information known to CONTRACTOR, information and observations obtained from visits to the site, reports and drawings identified in the Contract Documents and all additional examinations, investigations, explorations, tests, studies and data with the Contract Documents.
7.7. CONTRACTOR has given DESIGN PROFESSIONAL written notice of all conflicts, errors, ambiguities or discrepancies that CONTRACTOR has discovered in the Contract Documents and the written resolution thereof by DESIGN PROFESSIONAL is acceptable to CONTRACTOR, and the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
ARTICLE 8
CONTRACT DOCUMENTS
The Contract Documents that comprise the entire agreement between CITY and CONTRACTOR concerning the Work consist of the following:
8.1. This Agreement (pages 1 to 10, inclusive).
8.2. Exhibits to this Agreement
- Exhibit A: CONTRACTOR’S Bid (pages 1 to 8, inclusive)
- Exhibit B: Section 00 08 00 Special Construction Provisions
- Exhibit C: Section 01 51 36 Temporary Water Service
- Exhibit D: Section 32 90 00 Landscaping
8.3. General Conditions (pages 1 to 66, inclusive).
8.4. Drawings consisting of 18 total pages, stamped for construction on July 25, 2025.
8.5. Performance, Payment, and other Bonds
8.6. Notice to Proceed.
8.7. Addenda numbers ________ to ________, inclusive.
Form Approved by City Attorney August 2022 Page 7
8.8. Invitation to Bid.
8.9 The following documents that may be delivered or issued after the Effective
Date of the Agreement and are not attached hereto: All Written Amendments and other documents amending, modifying or supplementing the Contract Documents pursuant to paragraphs 3.4. and 3.5. of the General
The documents listed in paragraphs 8.2 et seq., above, are attached to this Agreement (except as expressly noted otherwise above) and are made a part of this Agreement.
There are no Contract Documents other than those listed above in this Article 8. The Contract Documents may only be amended, modified, or supplemented as provided in paragraphs 3.4 and
3.5 of the General Conditions.
The provisions of this Agreement, followed by the Supplementary Conditions, and then the General Conditions, shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Agreement and any of the Contract Documents.
ARTICLE 9
MISCELLANEOUS
9.1. Any notice to the parties required under this Agreement shall be in writing, delivered to the person designated below for the parties at the indicated address unless otherwise designated in writing. Only mailing by United States mail or hand-delivery shall be utilized. E-mail addresses are provided for convenience only.
Lafayette: City of Lafayette Contractor: _______________________ 1290 South Public Road _______________________ Lafayette, Colorado 80026 _______________________ Attn: Melanie Asquith Attn: ___________________ Telephone: (303) 661-1279 Telephone: ______________ E-mail: Melanie.Asquith@lafayetteco.gov E-mail: _________________
Design Professional: Professional Engineering Consultants (PEC) 351 Linden St Suite 100 Fort Collins, Colorado 80524 Attn: Kent Bruxvoort Telephone: (970) 342-0428 E-mail: kent.bruxvoort@pec1.com
Form Approved by City Attorney August 2022 Page 8
9.2. Terms used in this Agreement that are defined in Article 1 of the General
Conditions will have the meanings indicated in the General Conditions.
9.3. No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and, unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.
9.4. This Agreement is between CITY and CONTRACTOR and no other person or organization shall be entitled to enforce any of its provisions or have any right under this Agreement.
9.5. CITY and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, agreements and obligations contained in the Contract Documents.
9.6. Nothing herein shall constitute a multiple fiscal year obligation pursuant to
Colorado Constitution Article X, Section 20. Notwithstanding any other provision of this Agreement, CITY's obligations under this Agreement are subject to annual appropriation by the City Council of the CITY. Any failure of the City Council annually to appropriate adequate funds to finance CITY's obligations under this Agreement shall terminate this Agreement at such time as such then-existing appropriations are to be depleted. Notice shall be given promptly to CONTRACTOR of any failure to appropriate such adequate monies.
9.7. This Agreement is to be governed by the laws of the State of Colorado. Venue for any legal proceeding under this Agreement shall be in Boulder County, Colorado.
9.8. This Agreement may only be amended, supplemented, or modified in a written document signed by both parties.
9.9. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon CITY and CONTRACTOR, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.
9.10. In the event of default of any of the provisions herein, the defaulting party shall be liable to the non-defaulting party for all reasonable attorney fees, legal expenses and costs incurred as a result of the default.
Form Approved by City Attorney August 2022 Page 9
9.11. Delays in enforcement or the waiver of any one or more defaults or breaches of this Agreement by the CITY shall not constitute a waiver of any of the other terms or obligations of this Agreement.
9.12 CONTRACTOR agrees to perform the work in compliance with all applicable federal, state, county and city laws, ordinances, rules and regulations, including, without limitations, any preference for Colorado Labor as may be required pursuant to Article 17, of Title 8 of the Colorado Revised Statutes (the “Keep Jobs in Colorado Act”), as amended.
9.13. Counterparts and Signatures. This Agreement may be executed by the parties in counterparts, each of which shall be deemed to be an original and all of which, when taken together, shall constitute one and the same Agreement. Each of the parties shall be entitled to rely upon a counterpart of the instrument executed by the other party and sent by facsimile or electronic transmission. The parties further agree this Agreement may be executed by electronic signatures, and any electronic signatures, electronic record of this Agreement containing an electronic signature, or a paper copy of an electronic signature shall be binding upon the party providing such electronic signature as if it were the party’s original signature.
[The remainder of this page is intentionally blank.]
Form Approved by City Attorney August 2022 Page 10
IN WITNESS WHEREOF, CITY and CONTRACTOR have signed this Agreement in triplicate. One counterpart each has been delivered to CITY, CONTRACTOR and DESIGN PROFESSIONAL. All portions of the Contract Documents have been signed, initialed or identified by CITY and CONTRACTOR or identified by DESIGN PROFESSIONAL on their behalf.
This Agreement executed to be effective on __________________________, 20___.
FOR THE CITY OF LAFAYETTE:
Mayor
Attest:
City Clerk
Approved as to Form:
City Attorney for the City of Lafayette
FOR THE CONTRACTOR:
[INSERT NAME OF CONTRACTOR]
By:
Printed Name:________________________ Title: _______________________________
CONTRACTOR’s License No:
CONTRACTOR’s Agent for service of process:
ATTEST:
Title:_______________________________
Design Professional: Professional Engineering Consultants (PEC) Total Cost:
HRO #686783 v1 Performance Bond
PERFORMANCE BOND
Dollars ($_______________), for the payment whereof CONTRACTOR and SURETY bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, CONTRACTOR has by written agreement dated ________________, 20__, entered into a Construction Contract with CITY for the following Project:
in accordance with Drawings and Specifications prepared by Professional Engineering Consultants (PEC), DESIGN PROFESSIONAL, whose address is: 351 Linden St, Suite 100, Fort Collins, CO 80524, which contract is by reference made a part hereof, and is hereinafter referred to as the Construction Contract.
Form Approved by City Attorney on 1/22/01
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if the CONTRACTOR performs the Construction Contract, then this obligation shall be null and void;
otherwise, the SURETY and the CONTRACTOR shall have the following obligations:
1. If CITY is not in Default under the Construction Contract, SURETY's obligation under this Bond shall arise after:
1.1 CITY has notified CONTRACTOR and SURETY at its address listed on the first page hereof that CITY by seven days' written notice intends to terminate the services of CONTRACTOR or otherwise declare CONTRACTOR to be in Default of its obligations under the Construction Contract; and
1.2 CITY has declared CONTRACTOR to be in Default and formally terminated CONTRACTOR's right to complete the Construction Contract; and
1.3 CITY has agreed to pay the Unpaid Balance of the Contract Price to SURETY in accordance with the terms of the Construction Contract or to a contractor selected to perform the Construction Contract in accordance with the terms of the Construction Contract with
CITY.
2. When CITY has satisfied the conditions of paragraph 1, SURETY shall promptly and at SURETY's expense take one of the following actions:
2.1 Arrange for CONTRACTOR, with consent of the CITY, to perform and complete the Construction Contract; or
2.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors; or
2.3 Obtain bids or negotiated proposals from qualified contractors acceptable to CITY for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by CITY and the contractor selected with CITY's concurrence, to be secured with the performance and payment bonds executed by a qualified Surety equivalent to the Bonds issued on the Construction Contract, and paid to CITY the amount of damages as described in paragraph 4 in excess of the Unpaid Balance of the Contract Price incurred by CITY resulting from the CONTRACTOR's Default; or
2.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances, after investigation, determine the amount for which it is liable to CITY and, as soon as practicable after the amount is determined and approved by CITY, tender payment therefor to CITY.
3. If SURETY does not proceed as provided in paragraph 2 with reasonable promptness, SURETY shall be deemed to be in default on this Bond 15 days after receipt of an additional written notice from CITY to SURETY demanding that SURETY perform its obligations under this Bond, and CITY shall be entitled to enforce any remedy available to CITY. If SURETY
Form Approved by City Attorney on 1/22/01 proceeds as provided in subparagraph 2.4 and CITY refuses the payment tendered or SURETY has denied liability, in whole or in part, without further notice, CITY shall be entitled to enforce any remedy available to CITY.
4. After CITY has terminated CONTRACTOR's right to complete the Construction Contract, and if SURETY elects to act under subparagraph 2.1, 2.2, or 2.3 above, then the responsibilities of SURETY to CITY shall not be greater than those of CONTRACTOR under the Construction Contract, and the responsibilities of CITY to SURETY shall not be greater than those of CITY under the Construction Contract. To the limit of the amount of this Bond, but subject to commitment by CITY of the unpaid balance of the Contract Price to mitigation of costs and damages on the Construction Contract, SURETY is obligated without duplication for:
4.1 The responsibilities of CONTRACTOR for correction of defective work and completion of the Construction Contract; and
4.2 Additional legal, design professional and delay costs resulting from CONTRACTOR's Default, and resulting from the actions or failure to act of SURETY under paragraph 2; and
4.3 Liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non-performance of
CONTRACTOR.
5. SURETY hereby waives notice of any change, including changes to the Contract Times, to the Construction Contract or to related subcontracts, purchase orders and other obligations.
6. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the Work or part of the Work is located…