IFB_260105_Francisco_Elias_Esquer_Bid_Schedule.xlsx
XLSX spreadsheet 16 KB Posted
- Solicitation number
- 260105
- Issued by
- Pima County, Tucson City, Arizona
About this file
The document is a comprehensive Bid Schedule for the Francisco Elias Esquer Park Dog Park & Water Harvesting project, issued by the City of Tucson under Invitation for Bid (IFB) No. 260105. The project encompasses multiple construction components including dog park development, bridge and walking path construction, and lighting and electrical infrastructure, with detailed line items covering activities such as clearing, excavation, landscape grading, water line installation, irrigation systems, fencing, and shade structures. The bid was released on August 13, 2025, with a pre-submittal meeting scheduled for August 20, 2025, at 10:00 am via Microsoft Teams, and bid responses due on September 18, 2025, at 2:00 pm local Arizona time. The contract duration is anticipated to be 270 consecutive calendar days from the Notice to Proceed, with liquidated damages of $1,290.00 per calendar day of delay.
The project is funded through the City of Tucson and potentially involves U.S. Department of Housing and Urban Development (HUD) funding, with an estimated budget between $1,000,000 and $5,000,000. Specific procurement requirements include set-aside provisions for Disadvantaged Business Enterprises (DBE) and Small Business Enterprises (SBE), mandating contractors demonstrate good faith efforts in DBE participation. Federal compliance requirements include Section 3 provisions requiring 25% of total labor hours to be worked by Section 3 workers, with 5% performed by Targeted Section 3 workers. Contractors must be certified through the Arizona Unified Certification Program (AZUCP) and submit comprehensive documentation including a bid bond, contractor responsibility form, and detailed project experience information. The bid schedule includes three alternate bid options: Bid Alt #1 for decorative elements, Bid Alt #2 for additional paving areas, and Bid Alt #3 for additional landscape elements.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Francisco Bid Schedule
| Project Name: | Francisco Elias Esquer Park Dog Park & Water Harvesting | ||||
| IFB | 260105 | ||||
| ITEM NO. | ITEM DESCRIPTION | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
| 2010001 | CLEARING AND GRUBBING | L SUM | 1 | $ - | |
| 2010002 | REMOVAL OF TREES | EACH | 18 | $ - | |
| 2020001 | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | L SUM | 1 | $ - | |
| 2020100 | REMOVE CHAIN LINK FENCE | L FT | 186 | $ - | |
| 2030401 | DRAINAGE EXCAVATION (DETENTION AND SWALES) | C.Y. | 1,450 | $ - | |
| 5030775 | CATCH BASIN SPECIAL | EACH | 1 | $ - | |
| 5010007 | PIPES, CORRUGATED METAL, 18" | L FT | 205 | $ - | |
| 5101401 | POTABLE WATER LINE - 1" PVC | L FT | 415 | $ - | |
| 8020001 | LANDSCAPE GRADING (INCLUDING WATER HARVESTING) | SY | 1,309 | $ - | |
| 8030031 | ROCK MULCH (3/8" SCREENED PEA GRAVEL) | SY | 4,100 | $ - | |
| 8030105 | DECOMPOSED GRANITE (3" MINUS, DESERT PAVEMENT) | SY | 1,580 | $ - | |
| 8030143 | DECORATIVE BOULDERS (3') | EA | 10 | $ - | |
| 8030144 | DECORATIVE BOULDERS (6') | EA | 2 | $ - | |
| 8050003 | SEEDING (CLASS II) | SY | 1,580 | $ - | |
| 8060066 | TREE PROTECTION (FENCING) AND TRIMMING | L SUM | 1 | $ - | |
| 8061011 | TREE (36" BOX) | EACH | 2 | $ - | |
| 8061066 | TREE (24" BOX) | EACH | 46 | $ - | |
| 8061101 | TREE STAKING AND GUYING (2 STAKES PER TREE) | EACH | 48 | $ - | |
| 8061296 | SHRUB (ONE GALLON) | EACH | 472 | $ - | |
| 8061390 | DASYLIRION (FIVE GALLON) | EACH | 3 | $ - | |
| 8061701 | BROWSER CAGES | EACH | 475 | $ - | |
| 8070001 | LANDSCAPING ESTABLISHMENT (24 MONTHS) | L SUM | 1 | $ - | |
| 8080011 | MISCELLANEOUS LANDSCAPE WORK | FA | |||
| 8080049 | EMITTER (ASSEMBLY)(MULTI-OUTLET) | EACH | 128 | $ - | |
| 8080067 | CONNECTION TO IRRIGATION CONTROLLER | EACH | 1 | $ - | |
| 8080074 | EMITTER DISTRIBUTION TUBING (STAKING INCLUDED) | L SUM | 1 | $ - | |
| 8080084 | PRESSURE REGULATOR | EACH | 4 | $ - | |
| 8080090 | QUICK COUPLING VALVE | EACH | 2 | $ - | |
| 8080120 | FILTER ASSEMBLY | EACH | 4 | $ - | |
| 8080168 | CONTROL VALVE (REMOTE)(ELECTRIC)(1")(BATTERY OPERATED-PLASTIC) | EACH | 4 | $ - | |
| 8080245 | END CAP ASSEMBLY - W/ 10" DIA. CAN | EACH | 21 | $ - | |
| 8080301 | MAINLINE PIPE - SCH. 40 PVC - 1" SIZE | L FT | 261 | $ - | |
| 8080304 | PIPE (SLEEVE) PVC, SCHEDULE 40 (4") | L FT | 147 | $ - | |
| 8080305 | PIPE (SLEEVE) PVC, SCHEDULE 40 (6") | L FT | 104 | $ - | |
| 8080312 | LATERAL LINE PIPE - SCH. 40 PVC - 3/4" SIZE | L FT | 3,070 | $ - | |
| 8100001 | AZPDES/NPDES (ORIGINAL) | L SUM | 1 | $ - | |
| 8100002 | AZPDES SWPPP MODIFICATIONS | FA | |||
| 9010001 | MOBILIZATION | L SUM | 1 | $ - | |
| 9020201 | STEEL FENCE | L FT | 1,394 | $ - | |
| 9030102 | FENCE GATE (12') | EACH | 2 | $ - | |
| 9030103 | FENCE GATE (6') | EACH | 4 | $ - | |
| 9130001 | RIPRAP (DUMPED) | C.Y. | 54 | $ - | |
| 9130009 | RIPRAP (HAND PLACED) (GROUTED) | C.Y. | 16 | $ - | |
| 9140085 | TENSILE SHADE STRUCTURE (AND FOUNDATION) | EACH | 2 | $ - | |
| 9140156 | SEATWALL (MASONRY) | SF | 146 | $ - | |
| 9300202 | MISCELLANEOUS WORK (DRINKING FOUNTAIN W/PET FOUNTAIN) | EACH | 2 | $ - | |
| DOG PARK CONSTRUCTION TOTAL | $0.00 |
| ITEM NO. | ITEM DESCRIPTION | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
| 2030502 | STRUCTURAL EXCAVATION | C.Y. | 131 | $ - | |
| 2030506 | STRUCTURE BACKFILL | C.Y. | 97 | $ - | |
| 5030084 | SIDEWALK SCUPPER TYPE 2 (3 CELL) | EACH | 2 | $ - | |
| 5030085 | SIDEWALK SCUPPER TYPE 2 (5 CELL) | EACH | 2 | $ - | |
| 5101522 | STEEL SLEEVE PIPE, 3" | L FT | 60 | $ - | |
| 6010004 | STRUCTURAL CONCRETE (CLASS S) (F'C = 4,000) | CU YD | 24 | $ - | |
| 6010903 | CONCRETE BRIDGE DECK | SQ.FT. | 600 | $ - | |
| 6040502 | SPECIAL PEDESTRIAN RAILING | L FT | 26 | $ - | |
| 6047000 | PREFAB. STEEL TRUSS PED. BRIDGE (INCLUDING DESIGN) | LS | 1 | $ - | |
| 6050001 | REINFORCING STEEL | LB. | 3,560 | $ - | |
| 9010001 | MOBILIZATION | L SUM | 1 | $ - | |
| 9080201 | CONCRETE SIDEWALK | SF | 15,125 | $ - | |
| 9080202 | DECORATIVE SIDEWALK | SF | 1,105 | $ - | |
| 9330001 | HANDRAIL PER PAG SD 105 | L FT | 319 | $ - | |
| 9340011 | POST BARRICADES (PC/COT STD DTL 107) | EACH | 2 | $ - | |
| 9340012 | REMOVEABLE POST BARRICADE (PC/COT STD DTL 107) | EACH | 2 | $ - | |
| BRIDGE/WALKING PATH CONSTRUCTION TOTAL | $0.00 | ||||
| ITEM NO. | ITEM DESCRIPTION | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
| 7320001 | PARK LIGHTING & ELECTRICAL | L SUM | 1 | $ - | |
| LIGHTING & ELECTRICAL CONSTRUCTION TOTAL | $0.00 |
| TOTAL BID AMOUNT | $0.00 | ||||
| Dog Park Construction (Bid Alt #1: Decorative Elements) | |||||
| ITEM NO. | ITEM DESCRIPTION | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
| 9140085 | TENSILE SHADE STRUCTURE (AND FOUNDATION) | EACH | 2 | $ - | |
| 9140156 | SEATWALL (MASONRY) | SF | 146 | $ - | |
| DOG PARK BID ALT #1 CONSTRUCTION TOTAL | $0.00 | ||||
| Bridge/Walking Path Construction (Bid Alt #2: Additional Paving Areas) | |||||
| ITEM NO. | ITEM DESCRIPTION | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
| 5030084 | SIDEWALK SCUPPER TYPE 2 (3 CELL) | EACH | 2 | $ - | |
| 5030085 | SIDEWALK SCUPPER TYPE 2 (5 CELL) | EACH | 2 | $ - | |
| 9080201 | CONCRETE SIDEWALK | SF | 13,214 | $ - | |
| 9080202 | EXPOSED AGGREGATE PAVING | SF | 563 | $ - | |
| 9340011 | POST BARRICADES (PC/COT STD DTL 107) | EACH | 2 | $ - | |
| 9340012 | REMOVEABLE POST BARRICADE (PC/COT STD DTL 107) | EACH | 2 | $ - | |
| 9330001 | HANDRAIL PER PAG SD 105 | L FT | 112 | $ - | |
| BRIDGE/WALKING PATH BID ALT #2 CONSTRUCTION TOTAL | $0.00 |
| Dog Park Construction (Bid Alt #3: Additional Landscape) | |||||
| ITEM NO. | ITEM DESCRIPTION | UNIT | UNIT PRICE | QUANTITY | AMOUNT |
| 8030143 | DECORATIVE BOULDERS (3') | EA | 10 | $ - | |
| 8030144 | DECORATIVE BOULDERS (6') | EA | 2 | $ - | |
| 8061296 | SHRUB (ONE GALLON) | EACH | 472 | $ - | |
| 8061390 | DASYLIRION (FIVE GALLON) | EACH | 3 | $ - | |
| 8061701 | BROWSER CAGES | EACH | 475 | $ - | |
| 8070001 | LANDSCAPING ESTABLISHMENT (24 MONTHS) | L SUM | 1 | $ - | |
| 8080049 | EMITTER (ASSEMBLY(MULTI-OUTLET) | EACH | 80 | $ - | |
| 8080245 | END CAP ASSEMBLY - W/ 10" DIA. CAN | EACH | 12 | $ - | |
| 8080312 | LATERAL LINE PIPE - SCH. 40 PVC - 3/4" SIZE | L FT | 1,614 | $ - | |
| DOG PARK BID ALT #3 CONSTRUCTION TOTAL | $0.00 |