This is an Invitation for Bid (IFB #25-S-029) issued by the Washington Convention and Sports Authority, operating as Events DC, a District of Columbia government authority, for the replacement of damaged Special Lite Meeting Room Doors at the Walter E. Washington Convention Center. The project requires the provision of 80 wooden doors, 80 door hardware units with electrified functions, and 40 aluminum tube door frames, along with installation, inspection, and integration with the facility's Lenel OnGuard Access Control System. Bidders must submit questions by 3:00 PM EST on March 23, 2026, and submit complete bid responses electronically by 5:00 PM EST on Thursday, April 9, 2026. The contract will begin upon award and continue through September 30, 2026, with four one-year renewal options available at Events DC's discretion. Contractor personnel must work within standard business hours (8:00 AM to 5:00 PM EST, Monday through Friday) and coordinate schedules with the Contracting Officer's Technical Representative to avoid disruption to facility operations.

Bidders must provide fully loaded hourly rates for multiple labor categories and firm fixed costs for materials over the contract term and all option years, with prices evaluated on a lowest aggregate price basis over the full contract life. This solicitation is restricted to District of Columbia Department of Small, Local, and Business Development (DSLBD) certified business enterprises, with preference points available for qualifying small business enterprises, resident-owned businesses, longtime resident businesses, local business enterprises, disadvantaged business enterprises, veteran-owned businesses, local manufacturing businesses, and equity impact enterprises, totaling a maximum of 12 preference points. Contractors must demonstrate a minimum of five years of experience in commercial or institutional door fabrication and installation, active public facilities and convention centers, and panic hardware installation with access control system integration. All bidder submissions must include proof of DSLBD certification, W-9 forms, tax certifications, clean hands reports, Dun and Bradstreet reports, and three customer reference letters attesting to satisfactory performance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | IFB #25-S-029 – Replacement of Meeting Room Doors

REPLACEMENT OF MEETING ROOM DOORS

INVITATION FOR BID (IFB)

BID #25-S-029

The Washington Convention and Sports Authority t/a Events DC is soliciting bids from qualified firms to provide Replacements of Meeting Room Doors. Interested parties can view a copy of the IFB by accessing Events DC’s e-Procurement website at https://eventsdc.com/about/procurement.

This Invitation for Bid (“IFB”) is designated for District of Columbia Department of Small, Local, and Business Development (“DSLBD”) certified business enterprises only.

Key Dates

IFB Release Date: 3:00 PM EST, Tuesday, March 10, 2026

IFB Questions Due Date: 3:00 PM EST, Monday, March 23, 2026

IFB Response Due Date: 5:00 PM EST, Thursday, April 9, 2026

Primary Contact

Name: Jaylah Dawson, Senior Contracts & Procurement Analyst Email: Jdawson@eventsdc.com Phone: 202-249-3072 https://eventsdc.com/about/procurement.

https://eventsdc.sharepoint.com/sites/OCPTeam/Shared%20Documents/Jdawson@eventsdc.com

2 | IFB #25-S-029 – Replacement of Meeting Room Doors

SECTION A - INTRODUCTION

A.1 The Washington Convention and Sports Authority t/a Events DC (“Events DC”) is an independent authority of the District of Columbia (“District”) Government and operates as a corporate body with a legal existence separate from the District. Events DC is governed by a twelve (12) member Board of Directors appointed in accordance with D.C. Code § 10-1202.05. Its day-to-day operations are managed by its President and Chief Executive Officer.

A.2 Events DC has the responsibility to, among other things, promote, develop and maintain the District as a location for conventions, trade shows, meetings, concerts, sporting and entertainment events, and other special events. In that regard, it owns, manages and/or operates the Walter E. Washington Convention Center (“Convention Center”), the Carnegie Library at Mt. Vernon Square, Robert F. Kennedy Memorial Stadium and its surrounding campus (which includes the Festival Grounds, the Fields at RFK Campus, and Skate Park) (“RFK Stadium”), the non-military portions of the District of Columbia Armory, Gateway DC, the R.I.S.E. Demonstration Center, Nationals Park, and CareFirst Arena (each a “Facility”, collectively, the “Facilities”.

A.3 The Convention Center is a 2.3 million square foot convention and meeting facility that includes seven hundred and three thousand (703,000) square feed of exhibit space, a total of seventy-seven (77) break-out rooms and the largest ballroom in the Mid-Atlantic region.

The Convention Center hosts approximately two hundred (200) events per year with an average annual attendance figure of 1.2 million people.

A.4 Events DC is seeking a qualified contractor (the “Contractor”) to provide Replacements of damaged Special Lite Meeting Room Doors located throughout the Convention Center (“Services”). The Contractor shall provide all supervision, labor, materials, equipment and supplies required to provide the Work, meeting the specifications identified in this solicitation.

A.5 Events DC intends to award a time and materials contract (“Contract”) for the Work identified herein. The Base Term of the Contract will be from Date of Award through September 30, 2026, with four (4), one-year renewal options.

A.6 If a prospective Bidder has any questions relative to this IFB, the Bidder must submit the questions in the OpenGov system via the “Question and Answer” tab of the to receive a binding answer. Any question asked and answered outside of the OpenGov system will be considered informal and non-binding. Questions must be received no later than the close of business, 03:00 PM EST, March 23, 2026. Events DC will not consider any questions received after this date.

[End of Section A]

3 | IFB #25-S-029 – Replacement of Meeting Room Doors

SECTION B - GENERAL REQUIREMENTS

B.1 GENERAL DESCRIPTION OF WORK

(a) Events DC seeks an experienced Contractor to provide the Work on an as needed basis.

(b) The Contractor shall conduct all Services under the direction of Events DC’s designated on-site representative, the Contracting Officer’s Technical Representative (“COTR”).

Contact information for the COTR will be provided at the time of Contract award.

B.2 CONTRACTOR QUALIFICATIONS

To be considered for award of the Contract, the Bidder must:

(a) Possess a minimum of five (5) years of experience in commercial or institutional door fabrication and installation;

(b) Possess a minimum of five (5) years of experience in active public facilities and convention centers;

(c) Possess a minimum of five (5) years of experience in experience installing panic hardware and integrating with Lenel or comparable access control systems.

(d) Be bonded and licensed to perform the Work and be a licensed contractor in the District;

(e) Have the ability to meet ADA, NFPA, and DC building code standards; and

(f) Perform all Services in conformance with applicable federal, state, and District laws and regulations.

B.3 REFRENCES

The Bidder shall provide references letters and resumes of the roofers and laborers who will complete the Work detail in Section C. The Bidder must be included with the submission of the bid package in support of the Bidder’s ability to Services as identified within this solicitation. At a minimum, the references shall include:

(a) Company name and address;

(b) Company webpage (if applicable);

(c) Main products and services provided; and

(d) Point of contact information including: name, job title, telephone and email.

B.4 PRICE/COSTS

(a) Bidders shall provide fully loaded, hourly rates and firm fixed cost to perform the Services during the Base Term and all Option Years for items and services specified in Section C below.

4 | IFB #25-S-029 – Replacement of Meeting Room Doors

(b) The prices offered shall be a low as, or lower than those charged to the Contractor’s most favored customer for comparable quantities, terms and conditions.

(c) The price shall include administration fees and delivery cost to the final destination(s) identified in this solicitation.

B.5 QUESTIONS

(a) If a prospective Bidder has any questions related to this IFB, the Bidder must submit the questions in the OpenGov system via the “Question and Answer Message” tab to receive a binding answer. Any questions asked and answered outside of the OpenGov system will be considered informal and non-binding.

(b) Questions must be received no later than 5:00 PM, EST, Wednesday, March 25, 2026.

Events DC will not consider any questions received after this date.

(c) Events DC will furnish responses promptly to the requesting prospective Bidder and to other prospective Bidders if deemed by Events DC to be necessary to prepare a complete and accurate proposal, or if the lack of a copy of the response would be prejudicial to any other prospective Bidder.

[End of Section B]

SECTION C - SCOPE OF WORK AND OTHER REQUIREMENTS

C.1 GENERAL DESCRIPTION

The existing doors have sustained significant structural and cosmetic damage due to years of impact from carts, staging equipment, and routine operations. The new doors will restore the structural integrity, functionality, and aesthetic consistency of the meeting rooms while incorporating modern crash bars (panic hardware) and compatibility with Events DC’s Lenel Access Control System for improved safety, accessibility, and security management.

C.2 SCOPE OF WORK

(a) The Contractor shall provide the following services including but not limited to:

i. Inspection and verification to determine doors/frames that require replacement;

ii. Detailed Report on inspection findings, including current conditions of doors and door frames;

a. Door fabrication and specifications, inclusive of all hardware and Lenel OnGuard

Access Control System connectivity meeting the specifications below:

5 | IFB #25-S-029 – Replacement of Meeting Room Doors

Description Manufacturer Specifications* Quantity Pairs

Wooden Door

Special-Lite

SL-19 Wood Grain Hybrid FRP Door, Wood Grain FRP Finish, Color: Dark Maple (Item #:

5550)

Eighty (80)

Forty (40)

Door Hardware

Von Durpin

99 CRP with electrified function

Eighty (80) Forty (40)

Door Frame

Aluminum Tube Frame

Forty (40)

N/A

*Please see Attachment D for PDF of Equipment Specifications

iii. Finish and appearance, which will be approved by Events DC prior to installation;

iv. Removal of existing damaged doors; and

v. Installation of new doors and hardware while repairing and reinforcing frames as needed.

C.3 SCHEDULE OF SERVICES

(a) The Contractor shall coordinate with the COTR to develop a work schedule (“Schedule”), within the timeframe determined by the COTR. The Schedule must be approved by the COTR prior to the performance of Work. The Schedule must not interfere with the normal business of the respective Facility or disrupt any activity. This may require that some Work be performed during late or overnight hours.

(b) The Contractor shall perform all Services between the hours of 8:00 AM and 5:00 PM EST, Monday through Friday. Other working hours may be considered if deemed necessary by the COTR.

(c) The Contractor shall immediately notify the COTR if the Contractor anticipates the Services cannot be performed as scheduled and shall promptly propose a rescheduling of the Services, provided, however, that nothing in this section shall be construed as requiring Events DC to accept the proposed rescheduling. Events DC may, in its sole discretion, and without waiving any of its rights under the Contract, reject any proposed rescheduling of the Services and may obtain the required Services from another contractor.

(d) Should the Contractor fail to provide the Services in accordance with the agreed upon schedule, the Contractor may be liable for the costs incurred by Events DC to acquire substitute services of similar quality. In addition, the Contractor may, in addition to other obligations under the Contract, be liable for the difference of the cost of the substituted services and the fees that would otherwise have been due the Contractor under the Contract.

6 | IFB #25-S-029 – Replacement of Meeting Room Doors

(e) Events DC may, without incurring any liability, cancel any scheduled Services upon twenty- four (24) hours’ prior notice to the Contractor.

(f) The Contractor shall respond to all repair requests within twenty-four (24) hours of the request to schedule the repair.

C.4 QUALITY OF WORKMANSHIP

(a) The Contractor shall perform, or cause to be performed, all Services, required under the Contract to the reasonable satisfaction of Events DC, with that degree of skill, care and diligence normally exercised by experienced contractors performing Services of similar scope and magnitude. The Contractor shall at all times act in the best interest of Events DC.

(b) All Services performed under the Contract shall be inspected by the COTR. The Contractor shall be required to repair and/or redo work that is determined by the COTR to be deficient.

If the Work is found to be deficient, the Contractor shall, within twenty-four (24) hours after being notified by the COTR of such deficiency, submit a Corrective Action Plan (“Plan”) describing how the deficiency will be corrected, which Plan shall include any labor or parts that may be needed. Upon approval of the Plan, the Contractor will work with the COTR to schedule the corrective work required. The Contractor shall bear all costs associated with correcting deficient work to include all costs associated with removing and replacing any nonconforming equipment or supplies, and the performance of any additional services made necessary thereby.

C.5 CONTRACTOR PROVIDED EQUIPMENT

(a) The Contractor shall provide all equipment, lifts, materials, tools and supplies necessary to perform the Services. All equipment must meet standard OSHA safety requirements as well as all safety requirements pursuant to law. All equipment must be operated in a safe manner and must be clean and in good repair at all times while the Services are being performed.

(b) The Contractor is solely responsible for the quality and performance of all Contractor provided materials and equipment. The Contractor shall be responsible for the cost of any repairs necessary to their own equipment.

(c) The Contractor and its personnel shall be knowledgeable in the proper use and operation of all equipment used to fulfill the requirements of the Contract.

(d) All Contractor provided materials and equipment shall be available for inspection by

Events DC at the request of the COTR.

7 | IFB #25-S-029 – Replacement of Meeting Room Doors

C.6 PERSONNEL

(a) The Contractor shall provide and supervise all personnel, or subcontractors, necessary to perform the Services in accordance with the Contract.

(b) The Contractor’s personnel must sign in and sign out at the Convention Center’s Security Labor Office upon entering or exiting the Convention Center.

(c) The Contractor shall take all necessary measures to comply and ensure that its employees comply with “Rules of the Jobsite for Contractors”.

(d) The Contractor’s personnel and/or subcontractors shall exercise safe and sound business practices with the requisite skill, care and diligence normally shown by professionals in the fields of Work required under the Contract.

(e) The Contractor shall at all times be independent contractors, and the Contract shall not in any way create or form a partnership or joint venture with Events DC. No agent, servant, or employee of the Contractor shall under any circumstances be deemed an agent, servant, or employee of Events DC.

(f) The Contractor shall not subcontract any of the Services to any subcontractor without the prior written consent of the COTR. Any Services so subcontracted shall be performed pursuant to a subcontract agreement, which the COTR will have the right to review and approve prior to its execution by the Contractor. Any such subcontract shall specify that the Contract and the subcontractor shall be subject to every provision of the Contract.

Notwithstanding any such subcontract approved by the COTR, the Contractor shall remain liable to Events DC for all Services required hereunder.

[End of Section C]

SECTION D - CONTRACT TERM, DELIVERABLES AND PERFORMANCE

D.1 TERM OF CONTRACT

a) The Base Term of the Contract shall be Date of Award through September 30, 2026.

b) Events DC has the right to extend the term of the Contract for four (4), one-year Option

Years, or successive fractions thereof, by written modification to the Contract before expiration, provided that Events DC gives the Contractor a preliminary written notice of its intent to extend at least thirty (30) days prior to Contract expiration. The preliminary notice does not commit Events DC to an extension. The Contractor may waive the thirty

(30) day preliminary notice requirement by providing a written waiver to the COTR prior

8 | IFB #25-S-029 – Replacement of Meeting Room Doors to Contract expiration. The exercise of an option is subject to the availability of funds at the time the option is exercised.

c) The Services to be required will be determined at the time each Option is exercised. If Events DC exercises an Option, the Contract shall be considered to include the option provision.

D.2 DELIVERABLES

The Contractor shall provide, at a minimum, the deliverables set forth below. Additionally, and upon request, the Contractor shall provide other reports which may be presented to Events DC’s Board of Directors, or the Council of the District of Columbia. The number of copies of other reports will be determined at the time of the request by Events DC.

DELIVERABLE METHOD OF

DELIVERY

DUE DATE TO WHOM

Pre-installation Condition Report

E-mail Within thirty (30) days of award

COTR

Door and Hardware inventory

Electronic and

Hard Copy

Within Sixty (60) days of award

Submittals including door, hardware, crash bar, and

Lenel-compatible electronic hardware specifications

E-Mail

As requested by Events DC

As directed

Samples and Finish

Options

E-Mail As determined by Events DC

Installation Schedule and

Phasing Plan

Electronic and Hard Copy

Within twenty-four

(24) hours of award

Final Inspection and Acceptance Report

E-Mail

Within twenty-four

(24) hours of completion of any work

Warranty Documentation E-Mail Within thirty (30) days of award

COTR

Invoices E-Mail Monthly COTR and invoices@eventsdc.com

[End of Section D] mailto:invoices@eventsdc.com

9 | IFB #25-S-029 – Replacement of Meeting Room Doors

SECTION E - STANDARD CONTRACT PROVISIONS

E.1 STANDARD CONTRACT PROVISIONS

Events DC’s Standard Contract Provisions are located under the “Attachments” tab of the bid. In the event of a conflict between this IFB and the Standard Contract Provisions, the prevailing document shall be this IFB.

[End of Section E]

SECTION F - EVALUATION OF RESPONSES

F.1 EVALUATION

(a) Events DC intends to make a single award to the responsive Bidder whose responses conform to the solicitation and is most advantageous to Events DC.

(b) All quotations received in response to this IFB will be evaluated based on the lowest price.

(c) Price will be evaluated in terms of the lowest aggregate overall price over the life of the Contract.

F.2 DEPARTMENT OF SMALL AND LOCAL BUSINESS DEVELOPMENT

(DSLBD) PREFERENCE CRITERIA

Any Bidder seeking to receive preferences for this solicitation must submit at the time of, and as part of its bid or proposal, evidence of the Bidder’s certification by the DSLBD.

F.3 CERTIFIED BUSINESS ENTERPRISE (CBE) PREFERENCE POINTS: 12

POINTS MAXIMUM

Events DC will allocate a maximum of twelve (12) preference points to qualified vendors in accordance with D.C. Code § 2-218.43 as follows:

(a) Three (3) points for a small business enterprise (“SBE”).

(b) Five (5) points for a resident-owned business (“ROB”).

(c) Five (5) points for a longtime resident business (“LRB”).

(d) Two (2) points for a local business enterprise (“LBE”).

(e) Two (2) points for a local business enterprise with its principal office located in an enterprise zone (“DZE”).

(f) Two (2) points for a disadvantaged business enterprise (“DBE”).

(g) Two (2) points for a veteran-owned business enterprise (“VOB”).

10 | IFB #25-S-029 – Replacement of Meeting Room Doors

(h) 2 points for a local manufacturing business enterprise (“LME”).

(i) 5 points for an equity impact enterprise (“EIE”).

[End of Section F]

SECTION G - SUBMISSION INSTRUCTIONS

G.1 Responses must be submitted electronically no later than 5:00 PM, Thursday, April 9, 2026 and shall consist of the following:

(a) Completion of the Quote Form at Attachment A, including confirmation that you have received Events DC’s Standard Contract Provisions;

(b) A copy of the Bidder’s W-9 form;

(c) Tax Certification Affidavit;

(d) OCPS Disclosure Form;

(e) Automated Clearing House (ACH) Form;

(f) First Source Employment Agreement;

(g) Representatives and Certifications Form;

(h) A Clean Hands Report;

(i) A copy of the Bidder’s most recent Dun and Bradstreet Report;

(j) Bidder’s General Services Administration (GSA)/DC Supply Schedule Contract (if applicable);

(k) Bidder’s current DSLBD CBE Certification Letter (if applicable); and

(l) Three (3) customer references letters (references must provide at a minimum a satisfactory rating) in support of the Bidder’s ability to provide the required Services as identified within this solicitation.

G.2 All Bidders must submit responses electronically via OpenGov to be considered for this award. Your response shall be signed by an official authorized to bind the Bidder and shall contain a statement that the quote is firm for a period of ninety (90) calendar days.

Questions and responses shall be submitted electronically to the COTR Contacts and Procurement Analyst listed below:

PRIMARY POINT OF CONTACT

Jaylah Dawson, Senior Contracts & Procurement Analyst Email: Jdawson@eventsdc.com Phone: 202-249-3072

[End of Section G] mailto:Jdawson@eventsdc.com

11 | IFB #25-S-029 – Replacement of Meeting Room Doors

SECTION H - AMENDMENTS

Any amendments to this IFB, including changes in the due date or scope of work, will be issued via OpenGov and will appear on the Amendments Tab of the OpenGov bid.

Enclosures: Attachment A – Quote/Price Form Attachment B – Events DC’s Standard Contract Provisions

Attachment C – Rules for the Jobsite Attachment D – Equipment Specifications

[End of Section H]

12 | IFB #25-S-029 – Replacement of Meeting Room Doors

ATTACHMENT A

QUOTE/PRICE FORM

MEETING ROOM SPECIAL LITE DOOR REPLACEMENT

(a) Please provide the loaded Firm Fixed Cost for each item and labor category listed below:

Item Manufacturer Description Firm Fixed Cost

Door

SL-19 Wood Grain Hybrid

FRP Door, Wood Grain FRP Finish, Color: Dark

Maple (Item #: 5550)

Door Hardware Von Durpin 99 CRP with electrified function

Door Frame Special- Lite Special Lite Aluminum Tube Frame

Fully Loaded Hourly Rate

Description Base Term Option Year

One Option

Year Two Option Year

Three Option

Year Four Project Manager $ $ $ $ $

Security Systems Project Manager

Door and Hardware Specialist

Technician $ $ $ $ $

Electrician $ $ $ $ $

Fire and Life Safety Inspector

Carpenter $ $ $ $ $

13 | IFB #25-S-029 – Replacement of Meeting Room Doors

Events DC’s Standard Contract Provisions Acceptance

a. Events DC are exempt from Federal Excise Tax, Transportation Tax, and District of

Columbia Sales and Use Taxes. All prices shall exclude all taxes.

b. Price quote shall be F.O.B. Destination, unless otherwise specified in writing by Events

DC.

By checking this box, I confirm that I have received Events DC’s Standard Contract Provisions (Attachment B).

Signed by: _____________________________ Date: ______________________

Title: _________________________________ Company: __________________

Quotes are valid for a period of ninety (90) calendar days from date of quote.

REPLACEMENT OF MEETING ROOM DOORS
INVITATION FOR BID (IFB)
BID #25-S-029
SECTION A - INTRODUCTION
SECTION B - GENERAL REQUIREMENTS
B.1 GENERAL DESCRIPTION OF WORK
B.2 CONTRACTOR QUALIFICATIONS
SECTION C - SCOPE OF WORK AND OTHER REQUIREMENTS
C.1 GENERAL DESCRIPTION
C.3 SCHEDULE OF SERVICES
C.4 QUALITY OF WORKMANSHIP
C.5 CONTRACTOR PROVIDED EQUIPMENT
C.6 PERSONNEL

SECTION D - CONTRACT TERM, DELIVERABLES AND PERFORMANCE

A
B
F.1 EVALUATION
F.2 DEPARTMENT OF SMALL AND LOCAL BUSINESS DEVELOPMENT (DSLBD) PREFERENCE CRITERIA
F.3 CERTIFIED BUSINESS ENTERPRISE (CBE) PREFERENCE POINTS: 12 POINTS MAXIMUM

SECTION H - AMENDMENTS