This is Addendum #2 to Invitation for Bid (IFB 25-063-JG) issued by the Kissimmee Utility Authority (KUA) for the Mill & Repave Transformer & Wire Storage Area project located at 2850 N. John Young Parkway in Kissimmee, Florida. The addendum, dated August 20, 2025, clarifies project requirements and addresses bidder questions regarding contractor licensing, surveying requirements, vegetation and equipment handling, and documentation submission. The addendum confirms that a licensed contractor is mandatory, surveying and as-built documentation are required to verify elevations and proper drainage, and three oak trees will remain with asphalt laid around visible roots while other vegetation is being removed by KUA. Steel storage racks will remain in place with work performed around concrete footings, and the lower shelf may be removed by KUA if necessary. Bidders must acknowledge receipt of this addendum by signing and returning the included acknowledgment form with their bid response. The mandatory pre-bid conference sign-in sheet was made available on VendorLink on August 19, 2025.
All information contained in this addendum is incorporated into the original solicitation documents as if set forth therein, and the addendum supersedes any verbal or other instructions previously provided to proposers. Bidders must confirm their bids align with all additions and revisions outlined in the addendum, and all associated costs must be included in the final bid pricing. This addendum maintains the force and effect of the original bidding and agreement documents issued for IFB 25-063-JG.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P a g e 1 | 2
TO: All Proposers FROM: Jennifer Grieves, Buyer DATE: August 20, 2025 RE: IFB 25-063-JG, Mill & Repave Transformer & Wire Storage Area
ADDENDUM #2
Bidders are hereby notified that this addendum shall be made a part of the above-named Invitation for Bid and agreement documents. The items listed below are issued to add, modify, and/or clarify the solicitation document and agreement documents. The items shall have the same force and effect as the original bidding and agreement documents, and cost involved shall be included in the bid pricing.
Bids, to be submitted, shall confirm with the addition and revision listed herein.
Return this sheet with your bid response.
I. QUESTIONS
Q1. Is a licensed contractor required for this project?
A1. Yes.
Q2. Are surveying and as-builts required?
A2. Yes, to verify the elevations and proper drainage.
Q3. Will KUA or the contractor be responsible for tree removal?
A3. The three oak trees will remain and asphalt should be laid around any visible roots. All other vegetation, including the small palm trees are currently being removed.
Q4. Will KUA or the contractor be responsible for moving the steel racks? If the contractor moves them, will disassembly and reassembly be required?
A4. The racks will remain in place and all work should be done around the concrete footings. The lower shelf on the racks can be removed by KUA if required to get at the asphalt under the racks.
Q5. Can you provide the mandatory prebid sign-in sheet? Thank you.
A5. The mandatory prebid sign-in sheet was posted in VendorLink on 08/19/25.
Bidder(s) must acknowledge receipt of this addendum by signing this form below and returning it with your bid response.
P a g e 2 | 2
Acknowledgment is hereby made of Addendum #2 to project IFB 25-063-JG, Mill & Repave Transformer & Wire Storage Area.
Bidder Signature Date
Bidder Printed Name Company Name
This addendum is issued to provide additional information, clarification, corrections, additions, deletions and/or to answers questions concerning the above referenced solicitation. All information provided in this addendum is incorporated into the solicitation document as if set forth therein. All other parts of the solicitation have been maintained as originally distributed.
This addendum supersedes any verbal or other instructions given to any proposer qualified to respond pursuant to the requirements set forth in the solicitation document.