IFB 23-24-092 Bid Tab
82 KB Posted
- Attached to
- IFB Five Fork Storm Sewer Replacement
- Solicitation number
- 68775
- Issued by
- Patrick County, Virginia
About this file
This document is an Invitation for Bid (IFB) issued by the City of Danville, Virginia for the Five Forks Storm Sewer Replacement project. The project involves the demolition and removal of existing concrete sidewalks, asphalt roadway, storm culvert and sewer lines, and the installation of new storm and sewer lines, replacement of sidewalk and curb, and repaving of the roadway. The scope of work includes 120 square yards of concrete demolition, 350 square yards of asphalt demolition, 30 tons of VDOT SM-9.5A surface asphalt, 100 tons of VDOT BM-25.0A base asphalt, 130 linear feet of CG-6 curb, 72 linear feet of existing 2'x2' culvert removal, and 194 linear feet of 36" RCP Class IV storm sewer. The bid closing date is June 24, 2024 at 2:00 p.m., with a pre-bid conference held on June 5, 2024. The contract completion time is 90 days, and liquidated damages are $350 per day. The bid shall be awarded to the lowest responsive and responsible bidder.
The bid requires a 5% bid bond, and the awarded contractor must provide 100% payment and performance bonds. All contractors and subcontractors must be registered with the Virginia Board for Contractors and obtain a City of Danville business license. No separate payment will be made for erosion and sedimentation control measures, maintenance of traffic, or restoration, as these costs are to be included in the prices bid for other items. The City of Danville has not specified any set-aside designations or restrictions on the types of organizations that can respond, and there is no information provided on any incumbent vendors or current contractors.
Text of this file
A B C D I J G H E F
ITEM ESTIMATED TOTAL ITEM PRICE TOTAL ITEM PRICE TOTAL ITEM PRICE
# QUANTITY (CxE) (CxG) (CxI)
1 MOBILIZATION 1 LS $ 14,500.00 $ 14,500.00 $ 25,000.00 $ 25,000.00 $ 46,252.00 $ 46,252.00 2 MAINTENANCE OF TRAFFIC 1 LS $ 25,240.00 $ 25,240.00 $ 25,000.00 $ 25,000.00 $ 13,533.00 $ 13,533.00
3 CONCRETE DEMO 120 SY $ 40.00 $ 4,800.00 $ 45.00 $ 5,400.00 $ 56.00 $ 6,720.00
4 ASPHALT DEMO 350 SY $ 35.00 $ 12,250.00 $ 14.00 $ 4,900.00 $ 22.00 $ 7,700.00
5 VDOT SM-9.5A SURFACE ASPHALT (1.5” DEPTH) 30 TN $ 190.00 $ 5,700.00 $ 275.00 $ 8,250.00 $ 175.00 $ 5,250.00 6 VDOT BM-25.0A BASE ASPHALT (5” DEPTH) 100 TN $ 180.00 $ 18,000.00 $ 175.00 $ 17,500.00 $ 165.00 $ 16,500.00
7 SAW CUT 235 LF $ 7.00 $ 1,645.00 $ 4.00 $ 940.00 $ 4.00 $ 940.00
8 CG-6 CURB 130 LF $ 91.00 $ 11,830.00 $ 60.00 $ 7,800.00 $ 44.00 $ 5,720.00
9 21A STONE BACKFILL 340 TN $ 45.00 $ 15,300.00 $ 55.00 $ 18,700.00 $ 60.00 $ 20,400.00
10 VDOT STD MH-2 6’ INNER DIAMETER (STM 16078) 1 EA $ 6,500.00 $ 6,500.00 $ 15,000.00 $ 15,000.00 $ 15,233.00 $ 15,233.00 11 8’ CURB INLET TYPE DI-4B (STM 16079) 1 EA $ 6,500.00 $ 6,500.00 $ 12,000.00 $ 12,000.00 $ 12,260.00 $ 12,260.00 12 8’ CURB INLET TYPE DI-4B (STM 16082) 1 EA $ 7,815.00 $ 7,815.00 $ 12,000.00 $ 12,000.00 $ 12,781.00 $ 12,781.00 13 6’ CURB INLET TYPE DI-4B (STM 02) 1 EA $ 9,600.00 $ 9,600.00 $ 10,000.00 $ 10,000.00 $ 14,536.00 $ 14,536.00 15 36” RCP CLASS IV 102 LF $ 336.00 $ 34,272.00 $ 455.00 $ 46,410.00 $ 367.00 $ 37,434.00 16 18” RCP CLASS IV 28 LF $ 227.00 $ 6,356.00 $ 250.00 $ 7,000.00 $ 311.00 $ 8,708.00 17 36” CORE (STM 30436) 1 EA $ 2,595.00 $ 2,595.00 $ 3,500.00 $ 3,500.00 $ 6,400.00 $ 6,400.00 18 4’ SANITARY SEWER MANHOLE (SMH 01) 1 EA $ 4,300.00 $ 4,300.00 $ 9,000.00 $ 9,000.00 $ 12,732.00 $ 12,732.00 19 4’ SANITARY SEWER MANHOLE (SMH 02) 1 EA $ 4,300.00 $ 4,300.00 $ 8,000.00 $ 8,000.00 $ 11,448.00 $ 11,448.00
20 8” PVC 60 LF $ 145.00 $ 8,700.00 $ 375.00 $ 22,500.00 $ 193.00 $ 11,580.00
21 8” CORE (SMH EX-02) 1 EA $ 1,500.00 $ 1,500.00 $ 2,700.00 $ 2,700.00 $ 5,501.00 $ 5,501.00 22 PLUG EXISTING 8” INVERT IN (SMH EX-03) 1 EA $ 550.00 $ 550.00 $ 750.00 $ 750.00 $ 5,032.00 $ 5,032.00 23 DEMO & REMOVE EX 8” TCP (SMH-01 TO SMH EX-03 1 LS $ 5,500.00 $ 5,500.00 $ 10,000.00 $ 10,000.00 $ 8,308.00 $ 8,308.00 24 VDOT CG-9D STANDARD ENTRANCE (30’) 1 EA $ 8,950.00 $ 8,950.00 $ 5,000.00 $ 5,000.00 $ 4,403.00 $ 4,403.00 25 VDOT CG-12 DETECTABLE WARNING SURFACE 1 EA $ 575.00 $ 575.00 $ 5,000.00 $ 5,000.00 $ 4,473.00 $ 4,473.00 26 TYPE-A INLET PROTECTION (TYP) 1 EA $ 500.00 $ 500.00 $ 600.00 $ 600.00 $ 600.00 $ 600.00 27 TYPE-B INLET PROTECTION (TYP) 3 EA $ 400.00 $ 1,200.00 $ 350.00 $ 1,050.00 $ 255.00 $ 765.00
TOTAL BASE BID 218,978.00$ 284,000.00$ 295,209.00$
UNIT PRICE
VA-CAROLINA PAVING CO BW INFRASTRUCTURE PDC INC.
DESCRIPTION OF WORK UNIT UNIT PRICE UNIT PRICE
IFB 23-24-092 FIVE FORKS STORM SEWER REPLACEMENT
Table 1
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .