IBM09B0004 Amendment A004 Specs 60 23 00

View the file

Other files

File Type Posted
GFMS IBM09B0004-A007.pdf PDF
GFMS IBM09B0004-A006.pdf PDF
GFMS IBM09B0004-A005.pdf PDF
60 80 00 Flood Gate-Rev.pdf PDF
NF1_12.63A.pdf PDF
GFMS IBM09B0004-A004.pdf PDF
AC1_12.17.pdf PDF
01 19 00R ScopeofWork.pdf PDF
U0450517(acn2)_Addendum 2 09-03-09.pdf PDF
01 33 00 Submittals.pdf PDF
02 02 00 ExistConds.pdf PDF
01 19 00 ScopeofWork.pdf PDF
U0450515(nf1)_Addendum 2 09-03-09.PDF PDF
00 31 24 EA Information.pdf PDF
50 25 00 HotMix.pdf PDF
01 46 00 QC-QA.pdf PDF
00 31 21 Survey Information.pdf PDF
GFMS IBM09B0004-A003.pdf PDF
60 21 00 HydraCement.pdf PDF
U0450516(acn1)_Addendum 2 09-03-09.pdf PDF
u0450518(nf2)_ADDENDUM NO.2_09_03_09.pdf PDF
60 50 00 Railing.pdf PDF
60 41 00 SteelStr.pdf PDF
15.01-15.22.pdf PDF
06.01-06.02.pdf PDF
12.01-12.41.pdf PDF
05.01-05.06.pdf PDF
13.01.pdf PDF
09.01-09.33.pdf PDF
04.01.pdf PDF
03.01.pdf PDF
08.01-08.140.pdf PDF
07.01-07.10.pdf PDF
14.01.pdf PDF
01.01.pdf PDF
02.01-02.20.pdf PDF
10.01-10.336.pdf PDF
GFMS IBM09B0004-A002.pdf PDF
Appendix A.pdf PDF
Final Report - NFW2 NFE2.pdf PDF
nfe2.pdf PDF
Appendix G.pdf PDF
Appendix F.pdf PDF
Appendix B.pdf PDF
Appendix C.pdf PDF
Appendix D.pdf PDF
nfw2.pdf PDF
Appendix E.pdf PDF
Div02.pdf PDF
Div60.pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lower Rio Grande Flood Control Project – Interior Floodways Rehabilitation of North Floodway (North and South Levees) and Arroyo Colorado Floodway (North Levee) Hidalgo and Cameron Counties, Texas

FLOODWALLS AND RETAINING WALLS

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 1

SPECIFICATION 60 23 00

This specification includes requirements for the construction of floodwalls and/or retaining walls within the work area, and includes the following:

1.0 General

2.0 Materials & Equipment

3.0 Construction Methods

4.0 Measurement and Payment

PART 1 - GENERAL

1.1 RELATED DOCUMENTS, CONTRACT CLAUSES, & SPECIFICATIONS

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification in accordance with all terms of the Contract herein.

A. Related documents: As described in paragraph 1.2 of SPECIFICATION 01 01 00.

B. Contract: Section I, 52.236-21“Specifications and Drawings for Construction”

C. Technical Specifications:

• SPECIFICATION 33 46 00, “Pipe Underdrains”

• SPECIFICATION 60 20 00, “Concrete Structures”

• SPECIFICATION 60 21 00, “Hydraulic Cement Concrete”

• SPECIFICATION 60 24 00, “Precast Concrete Structures (Fabrication)”

• SPECIFICATION 60 40 00, “Reinforcing Steel”

• SPECIFICATION 60 45 00, “Galvanizing”

• SPECIFICATION 60 50 00, “Railing”

• SPECIFICATION 60 58 00, “Waterproofing Membranes for Structures”

D. References:

• American Society of Testing and Materials (ASTM) C90 - 09 Standard Specification for Loadbearing Concrete Masonry Units

• ASTM C140 - 08a Standard Test Methods for Sampling and Testing Concrete Masonry Units and Related Units

• Texas Department of Transportation Department Material Specification (DMS)-6200, “Filter Fabric,” August 2004

• Texas Department of Transportation Testing Standard (Tex)-106-E “Calculating the

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 2

Plasticity Index of Soils,” August 1999

• Tex-110-E “Particle Size Analysis of Soils,” August 1999

• Tex-114- E “Laboratory Compaction Characteristics and Moisture-Density Relationship of Subgrade, Embankment Soils, and Backfill Material,” February 2005

• Tex-115-E “Field Method for Determining In-Place Density of Soils and Base Materials,” August 1999

• Tex-128-E “Determining Soil pH,” August 1999

• Tex-129-E “Measuring the Soil Resistivity of Soil Materials,” August 1999

• Tex-411-A “Soundness of Aggregate Using Sodium Sulfate or Magnesium Sulfate,” October 2004

• Tex-620-J “Determining Chloride or Sulfate Contents in Soils,” August 2005

1.2 GENERAL

In general, the Contractor shall furnish, construct, and install floodwalls and/or retaining walls.

1.3 DEFINITIONS

This Specification uses the following terms:

• Permanent Retaining Wall – A retaining wall with a design service life of 75 years. All walls are presumed to be permanent walls unless otherwise specified in the plans.

• Temporary Retaining Wall – A retaining wall so designated by description, with a design service life of 3 years.

• Mechanically Stabilized Earth (MSE) Retaining Wall – A wall consisting of a volume of select backfill with tensile earth reinforcement elements distributed throughout.

Permanent MSE walls use a precast concrete panel as a facing element. Temporary MSE walls use welded wire fabric with filter fabric backing as a facing element.

• Concrete Block Retaining Wall – A retaining wall that uses machine-made, precast concrete block units as facing elements. The walls may use a volume of select fill with tensile earth reinforcements distributed throughout, or may use only the facing unit and unit fill weight for support.

• Floodwall – A flood control structure; a concrete wall constructed in accordance with requirements in SPECIFICATION 60 20 00, this Specification, and the Contract Drawings.

PART 2 – MATERIALS & EQUIPMENT

2.1 MATERIALS

A. General. The Contractor shall furnish materials in accordance with the following:

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 3

• SPECIFICATION 33 46 00, “Pipe Underdrains”

• SPECIFICATION 60 20 00, “Concrete Structures”

• SPECIFICATION 60 21 00, “Hydraulic Cement Concrete”

• SPECIFICATION 60 40 00, “Reinforcing Steel”

• SPECIFICATION 60 45 00, “Galvanizing”

Unless otherwise shown on the plans, the Contractor shall use concrete that conforms to the requirements of Table 1.

Table 1

Concrete for Retaining Walls Application Concrete

Cast-in-place, non-reinforced Class A Cast-in-place, reinforced Class C Precast Class H, f′c = 4,000 psi

The Contractor shall furnish concrete for machine-made concrete block units in accordance with ASTM C 90, Class 1, Type II, except that the minimum 28 day compressive strength must be 4,000 psi with maximum moisture absorption of 7%.

The Contractor shall provide Type 1 filter fabric in accordance with DMS 6200, “Filter Fabric”;

provide filter fabric rated as UV-resistant when used as part of the exposed facing for a temporary wall.

Joint fillers, pads, waterstops, and other incidental materials must be as shown on the plans or as compliance-confirmed by the COR.

When the plans call for epoxy coating of steel earth reinforcements, epoxy coat all steel used in concrete panels and coping including connectors, dowels, stirrups, and reinforcing steel.

B. Fabrication. If required, the Contractor shall provide the following as shown in the plans:

(1) Cast-in-Place – meet SPECIFICATION 60 20 00, “Concrete Structures.”

(2) Formed Precast - meet SPECIFICATION 60 24 00, “Precast Concrete Structures

(Fabrication).”

(3) Machine-Made Precast - furnish machine-made concrete block units in accordance with

ASTM C90, sampled and tested in accordance with ASTM C140; furnish units with molded dimensions within 1/8 in. of specified dimensions, except height must be within 1/16 in.

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 4

C. Backfill. The Contractor shall provide the following as shown in the plans:

(1) Non-Select - Furnish backfill of the type specified in the plans. If no type is specified, provide material with a maximum plasticity index of 30 as determined by Tex 106 E.

(2) Select - Select backfill is required in specific areas of permanent and temporary MSE and concrete block-type retaining walls. Provide select backfill that is free from organic or otherwise deleterious materials and that conforms to the gradation limits in Table 2 as determined by Tex 110 E. Provide backfill that does not contain shale, caliche, or other soft, poor-durability coarse aggregate particles. Backfill appearing to contain such particles will be tested for soundness. Backfill with 5 cycle magnesium sulfate soundness of more than 30% when tested in accordance with Tex 411 A will be rejected. Type A, B, and D particles larger than 1/4 in. must be angular or crushed. Rounded rock or gravel is not allowed.

When the backfill gradation results in 85% or more material retained on the No. 4 sieve, the backfill will be considered rock backfill. All Type D backfill is considered rock backfill.

Unless otherwise shown on the plans, furnish Type B backfill for permanent walls. Furnish Type C backfill for temporary walls. Furnish Type D backfill for areas of walls subject to inundation or below the 100-year flood elevation as noted in the plans.

Table 2

Select Backfill Gradation Limits Type Sieve

Size Percent Retained

3 in. 0 1/2 in. 50–100 No. 4 See Note A

No. 40 85–100 3 in. 0 No. 4 See Note No. 40 40–100 B

No. 200 85–100 3 in. 0 No. 4 See Note C

No. 200 70–100 3 in. 0 D 3/8 in. 85–100

Note: Use No. 4 sieve for determination of rock backfill as described in Section 423.C, “Backfill.”

When nonmetallic or epoxy-coated earth reinforcements are used, furnish backfill meeting the requirements of this Section but with a maximum particle size of 3/4 in.

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 5

(3) Drainage Aggregate - Use drainage aggregate to fill the void within concrete block units and in the zone 1 ft. behind the units. Provide drainage aggregate that is free from organic or otherwise deleterious materials and that conforms to the gradation limits in Table 3 below as determined by Tex 110 E.

Table 3

Drainage Aggregate Gradation Limits Sieve Size Percent Retained

1 in. 0 3/4 in. 25–50 1/2 in. 50–100 No. 4 75–100

(4) Cement-Stabilized Backfill - Use cement-stabilized backfill when required or as compliance-confirmed. Stabilize Type C backfill with 5% hydraulic cement by dry weight of the backfill material. Use a stationary plant to thoroughly mix the backfill material, cement, and water. Place and compact the backfill within 2 hours of mixing. When cement-stabilized backfill is used, provide special drainage provisions as shown on the plans.

(5) Electrochemical. Provide backfill meeting the following additional requirements for permanent retaining wall systems using galvanized metallic earth reinforcements:

• The pH is between 5.5 and 10.0 as determined by Tex-128-E.

• Resistivity is more than 3,000 ohm-cm as determined by Tex-129-E.

• Material with resistivity between 1,500 and 3,000 ohm-cm may be used if the chloride content is less than 100 ppm and the sulfate content is less than 200 ppm as determined by Tex-620-J.

When cement-stabilized backfill is used, perform electrochemical testing on the raw, unstabilized backfill material.

D. Earth Reinforcements. The Contractor shall furnish earth reinforcements that meet the design requirements. For permanent walls, galvanize or epoxy coat all steel elements in contact with soil. Epoxy coat in accordance with SPECIFICATION 60 40 00, “Reinforcing Steel,” except provide a minimum 18 mil coating thickness. Epoxy coat the reinforcing only when shown in the plans or as compliance-confirmed. When using nonmetallic or epoxy coated earth reinforcements, use connection hardware that is likewise nonmetallic or epoxy coated:

2.2 EQUIPMENT (No Requirements Defined for this Specification)

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 6

PART 3 – CONSTRUCTION METHODS

3.1 GENERAL

The Contractor shall construct floodwalls and/or retaining walls in accordance with details shown on the Contract Drawings, on the compliance-confirmed working drawings, and to the pertinent requirements of the following Specifications:

• SPECIFICATION 33 46 00, “Pipe Underdrains”

• SPECIFICATION 60 40 00, “Excavation and Backfill for Structures”

• SPECIFICATION 60 20 00, “Concrete Structures”

Construct required piling or drilled shafts in accordance with the pertinent specification.

3.2 OPTIONAL DESIGNS

When optional design details are shown on the plans, the Contractor is required to use the same facing design within an area of continuous retaining walls. When proposing the use of two or more systems, provide drawings for review indicating the proposed design arrangement.

3.3 WORKING DRAWINGS FOR PROPRIETARY RETAINING WALL SYSTEMS

When proprietary wall systems are used, the Contractor shall submit casting drawings, construction drawings, and design calculations bearing the seal of a licensed professional engineer for review and compliance-confirmation. For permanent walls, submit 7 sets of casting and construction drawings and 2 sets of design calculations. Upon completion of construction, submit 1 set of reproducible as-built drawings to the COR. For temporary walls, submit 5 sets of construction drawings, and 2 sets of design calculations.

A. Casting Drawings. The Contractor shall include all information necessary for casting wall elements, including railing and coping when prefabricated. Show shape and dimensions of panels; size, quantity, and details of the reinforcing steel; quantity, type, size, and details of connection and lifting hardware; and additional necessary details.

B. Construction Drawings. The Contractor shall include a numbered panel layout showing horizontal and vertical alignment of the walls as well as the existing and proposed groundlines.

Include all information needed to erect the walls, including the proposed leveling pad elevations;

the type and details of the soil reinforcing system (if applicable); the details and manufacturer of all pads, fillers, and filter fabric; the limits and dimensions of structural backfill; details necessary to incorporate coping, railing, inlets, drainage, and electrical conduit; and additional necessary details. Leveling pad elevations may vary from the elevations shown on the plans. Unless a different minimum cover or a specified minimum leveling pad elevation is shown, provide at least 1 ft. of cover from the top of the leveling pad to finish grade.

C. Design Calculations. The Contractor shall include calculations covering the range of heights and loading conditions on the project. Calculations for both internal and external stability as

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 7 described in the plans will be required. Include a summary of all design parameters used; material types, strength values, and assumed allowables; loads and loading combinations; and factor-of-safety parameters.

3.4 PERMANENT MSE WALLS

The Contractor shall grade the foundation for the structure level for a width equal to or exceeding the length of the reinforcing system. Compact the foundation with a smooth-wheel vibratory roller or other compliance-confirmed roller. Remove and replace unsuitable foundation soils.

Place drilled shafts and piling located within the MSE volume prior to construction of the wall. Place any required pipe underdrain before construction of the wall.

Place the concrete leveling pad as shown on the construction drawings. Provide a wood float finish, and wait a minimum of 24 hours before beginning panel erection. No curing or strength testing of the leveling pad concrete is required.

Shim the first row of panels as necessary to achieve correct alignment. Use plastic shims or other material that will not deteriorate. If the required shim height exceeds 1 in., remove and replace the leveling pad or provide a grout level-up.

Place filter fabric behind the wall along the joint between the leveling pad and the panels. At leveling pad steps, grout areas where filter fabric spans more than 6 in.

After backfilling the first row of panels, place and compact fill material over the leveling pad to an elevation even with or above the surrounding ground. Do not allow water to accumulate and stand at the base of the wall.

Place filter fabric behind all wall joints and at the intersection of retaining walls with other structures, including riprap. Cover joints at least 6 in. on each side and use adhesive to hold the filter fabric in place.

Exercise care while lifting, setting, and aligning panels to prevent damage to the panels. Discontinue any operation that results in chipping, spalling, or cracking of panels. Remove and replace damaged panels, or repair as compliance-confirmed by the COR.

Provide external bracing for the initial row of panels. Use wooden wedges, clamps or other means necessary to maintain position and stability of panels during placement and compaction of backfill.

Remove wooden wedges as soon as the panel or coping above the wedged element is erected and backfilled. Remove all wedges after completing the wall.

Review plumbness and position of each row of panels before placing the subsequent row. Remove and rebuild any portion of the wall that is out of tolerance. Modify panel batter and bracing, and backfill material, placement, and compaction methods as required to maintain wall tolerances.

Construct walls to a vertical and horizontal alignment tolerance of 3/4 in. when measured along a 10 ft.

straightedge. Construct walls to an overall vertical tolerance (plumbness from top to bottom) of 1/2 in.

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 8 per 10 ft. of wall height. Construct walls so that the maximum out-of-plane offset at any panel joint is less than 3/4 in.; no joint is open to the extent that the filter fabric is visible from the front of the wall; and no joint is closed to the extent that there is concrete-to-concrete contact.

Place backfill to closely follow the erection of each row of panels. Place the select and embankment backfill to the same elevation where possible, and operate the compaction equipment over the interface.

Do not create a continuous, distinct, vertical joint between the select and embankment backfill. Do not complete the embankment prior to construction of the retaining wall.

When building a wall against existing ground, maintain the stability of the interface area between the existing ground and the select fill. Remove and re-compact any material that loosens, caves, or fails.

Compact backfill to provide not less than 95% of density determined in accordance with Tex -114-E.

Field density determination will be made in accordance with Tex -115-E. Test results will be made immediately available to the COR upon request. Unless otherwise requested or directed by the COR, the Contractor shall provide a certified hard-copy of each test report to the COR within 24-hours of each test result or as requested by the COR.

Sprinkle backfill as required to ensure adequate uniformly distributed moisture in each lift prior to and during compaction. Place fill in lifts of 8 in. or less (loose measurement). Place fill in a manner that avoids segregation of the fill. Decrease the lift thickness if necessary to obtain the required compaction.

Use hand-operated or walk-behind compaction equipment in the 3 ft. wide strip adjacent to the wall panels. Do not displace panels or distort or damage the reinforcement system during compaction. Modify backfill material, placement, and compaction methods as necessary to meet density requirements while maintaining wall tolerances.

Place rock backfill or material that is too coarse for density testing by the “Ordinary Compaction” method.

At each earth reinforcement level, place and compact the backfill to the reinforcement level before placing the reinforcement. Place earth reinforcements perpendicular to the face of the wall. Remove slack in connections prior to placing backfill. For systems using nonmetallic earth reinforcements, pretension each layer of reinforcement to remove slack before placing backfill. Use devices capable of mechanically applying and holding the required force. Do not operate tracked equipment directly on any reinforcement.

When rock backfill is used, cover the rock backfill with filter fabric before placing the 2 ft. of backfill immediately below the pavement structure or top of wall. Overlap the fabric at least 18 in. at splices, and extend it past the edge of the rock backfill at least 18 in. Above the filter fabric, use backfill that contains sufficient fines to fill the voids in a compacted state. Place a horizontal layer of filter fabric as noted above when transitioning from rock backfill to finer grained backfill anywhere within the wall volume.

Prevent surface water or rainwater from damaging the retaining walls during construction. Shape the backfill to prevent water from ponding or flowing on the backfill or against the wall face. Remove and replace any portion of the retaining wall damaged or moved out of tolerance by erosion, sloughing, or saturation of the retaining wall or embankment backfill.

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 9

3.5 TEMPORARY MSE WALLS

Provide a facing system rigid enough to maintain a smooth and straight wall face both during and after construction.

Grade and compact the foundation for the structure as described in “Permanent MSE Walls” herein.

Place earth reinforcement and facing system in accordance with the compliance-confirmed working drawings. Backfill the 2-ft. zone immediately behind the facing with clean coarse rock meeting the requirements of Coarse Aggregate Grade 1, 2, or 3 of SPECIFICATION 60 21 00, “ Hydraulic Cement Concrete,” or of Type D backfill as described in “Select” herein. Cement-stabilized backfill as described in “Cement-Stabilized Backfill” herein, may be used in place of the coarse rock.

Place and compact backfill in accordance with the requirements in “Permanent MSE Walls” herein.

Construct walls to a vertical and horizontal alignment tolerance of 3 in. when measured along a 10 ft.

straight edge. Construct walls to an overall vertical tolerance (plumbness from top to bottom) of 2 in. per 10 ft. of wall height. Place adjacent facing elements so that the maximum out-of-plane offset at any facing element joint is less than 1 in. Place facing elements and filter fabric with no gaps in the facing or fabric.

Prevent surface water or rainwater from damaging the retaining walls during and after construction.

Place temporary berms or curbs, shape the backfill, or use other compliance-confirmed methods to prevent water from flowing against or over the wall face. Remove and replace any portion of the wall damaged or moved out of tolerance by erosion, sloughing, or saturation of the retaining wall or embankment backfill.

3.6 CONCRETE BLOCK RETAINING WALLS

The concrete block units may be sampled and tested by the COR prior to shipment or upon delivery to the construction site. Display for compliance-confirmation samples of block units indicating the color, texture, and finish. Store, transport, and handle all block units carefully to prevent cracking or damage.

Grade and compact the foundation for the structure, and place the leveling pad as described in “Permanent MSE Walls” herein.

Place the concrete block facing units in accordance with the compliance-confirmed working drawings.

Fill the voids within the units and fill the 1-ft. zone immediately behind the facing with drainage aggregate as described in “Drainage Aggregate” herein. Systems tested without unit fill may omit the fill as indicated on the compliance-confirmed drawings. Systems with compliance-confirmed filter fabric details may omit the drainage aggregate in the 1-ft. zone immediately behind the facing.

For walls using earth reinforcements, place reinforcements and backfill in accordance with the requirements of “Permanent MSE Walls” herein. Pay particular attention to the connection details of the earth reinforcements to the concrete block units.

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 10

Construct walls to a vertical and horizontal alignment tolerance of 1-1/2 in. when measured along a 10-ft.

straightedge. Construct walls to an overall vertical tolerance (deviation from the vertical or battered control line, top to bottom) of 1 in. per 10 ft. of wall height. Place adjacent facing elements so that the maximum out-of-plane offset at any facing element joint is less than 1 in. Place facing elements with maximum 1/4-in. gaps between block units.

Prevent surface water or rainwater from damaging the retaining walls during construction. Shape the backfill to prevent water from ponding or flowing on the backfill or against the wall face. Remove and replace all portions of the retaining wall damaged or moved out of tolerance by erosion, sloughing, or saturation of the retaining wall or embankment backfill.

3.7 FLOODWALLS

The Contractor shall construct floodwalls as shown in the Contract Drawings and in accordance with SPECIFICATION 60 20 00, Concrete Structures.

The Contractor shall grade the foundation for the structure level for a width equal to or exceeding the length of the reinforcing system. Compact the foundation with a smooth-wheel vibratory roller or other compliance-confirmed roller. Remove and replace unsuitable foundation soils.

Place any required pipe underdrain before construction of the wall.

Construct walls to a vertical and horizontal alignment tolerance of 3/4 in. when measured along a 10 ft.

straightedge. Construct walls to an overall vertical tolerance (plumbness from top to bottom) of 1/2 in.

per 10 ft. of wall height.

3.8 CONCRETE STAIRS & PEDESTRIAN RAILING

The Contractor shall construct concrete stairs as shown in the Contract Drawings and in accordance with SPECIFICATION 60 20 00, Concrete Structures.

The Contractor shall construct pedestrian railing as shown in the Contract Drawings and in accordance with SPECIFICATION 60 50 00, Railing.

PART 4 – MEASUREMENT AND PAYMENT

4.1 MEASUREMENT

The Work performed under this Specification will be measured by the square foot of the front surface area of the wall. Unless otherwise shown on the plans, the area will be measured from 1 ft. below finished grade of the ground line on the face of the exterior wall to the top of the wall including any coping required (not including railing). This is a plans quantity measurement Specification. The quantity to be paid for is the quantity shown in the proposal except as modified by Contract Provisions.

Additional measurements or calculations will be made if adjustments of quantities are required.

4.2 PAYMENT

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 11

The work performed and materials furnished in accordance with this Specification and measured as provided under “Measurement” will be paid for at the unit price bid for “Floodwall” or “Retaining Wall”.

This price is full compensation for excavation in back of floodwalls, retaining walls, seepage walls, footings; furnishing and placing footings, leveling pads, copings, and traffic railing foundations;

furnishing, placing, and compacting backfill, including drainage blanket, cement for stabilization;

furnishing and placing concrete, reinforcing steel, waterproofing material, water stop, and filter fabric when required; fabricating, curing, and finishing all panels; furnishing and placing earth reinforcement, anchorage systems, and fasteners; wall erection; furnishing and constructing concrete stairs; furnishing and constructing pedestrian railing; equipment, labor, tools, and incidentals.

When piling is required, it will be measured and paid for as specified in the plans for piling of the appropriate type.

- END OF SPECIFICATION -

USIBWC Contract No.: IBM09B0004 Page 60.23.00 - 12

This Page Intentionally Blank