This is a pricing schedule submitted in response to an Invitation to Negotiate (ITN) issued by the State of Michigan (ITN Number 19000000076) for concrete pavement joint repairs on Interstate 69 from the Calhoun/Eaton County Line to Island Highway in Eaton County. The project requires contractors to provide pricing for pourable pavement repair materials and traffic control services. The pricing schedule requests quotations for 32,500 gallons of pourable pavement repair material and one lump sum traffic control item. Contractors must submit their pricing in a modifiable format such as Microsoft Word or Excel, with the option to provide an additional non-modifiable version in PDF format. Failure to complete the pricing schedule as requested may result in proposal disqualification.

Price proposals must encompass all costs, including one-time or set-up charges, fees, and any potential charges to the State such as shipping, handling, and per-piece pricing. Contractors are encouraged to offer quick payment terms by specifying a percentage discount if the invoice is paid within a stated number of days after receipt. The required material must be a cold pour liquid, self-leveling, water-based petroleum emulsion containing no volatile organic compounds (VOCs), with 4Seasons Pothole Repair identified as the only known product meeting these specifications. By submitting a proposal, contractors certify that prices were developed independently without consultation or agreement with other contractors.

View the file

Other files

File Type Posted
itn_vendor_question_worksheetâ¿¿.docx DOCX document
MOT SP including typicals.pdf PDF
invitation_to_negotiate_Coversheet _Amended (2).docx DOCX document
I-69 Joint Repairs Schedule A.docx DOCX document
Standard Terms.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enter company name here.

STATE OF MICHIGAN

ITN Number 19000000076 Concrete Pavement Joint Repairs I-69 from the Calhoun/Eaton County Line to Island Highway, Eaton County

SCHEDULE B

PRICING

1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the table shown. The pricing schedule should be submitted in a modifiable format (e.g.. Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.

2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).

3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.

Quick payment terms: ________ % discount off invoice if paid within ________ days after receipt of invoice.

4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.

5.

ITEM DESCRIPTION
UNIT
QUANTITY
PRICE PER UNIT (Vendor Completes)
TOTAL COST (Vendor Completes)
Pourable Pavement Repair
Gallons
32,500
Traffic Control
Lump Sum
1

TOTAL

1. 4Seasons Pothole Repair is the only material that we have been able to find that is a cold pour liquid, water-based petroleum emulsion that contains no VOC’s.

1. The cold pour liquid must be self-leveling and be able to fill and repair the concrete joints with little to no settling of the material after it has been placed.

1. The material supplied must meet the following requirements:

2. Cold pour liquid

2. Self- leveling

2. Water-based petroleum emulsion

2. Contains no VOC’s