This is a Quick Quote document from Collier County, Florida, for Hurricane Ian Repairs involving exterior wall painting at Clam Pass. The project involves painting approximately 20,297 square feet of precast concrete exterior walls, with a total project completion timeline of 120 days from purchase order issuance. The project is scheduled to be released on October 23, 2025, with response submissions due by November 6, 2025, at 3:00 pm. Work will be performed Monday through Friday, 7 am to 5 pm, and includes comprehensive surface preparation, cleaning, repairs, moisture checking, and application of a Sherwin-Williams primer and two topcoats in a specified color (SW6106 or equivalent).
The pricing is structured as a lump sum (LS) procurement, with vendors required to provide a total cost inclusive of all labor, materials, equipment, and markup. Insurance requirements are detailed, including worker's compensation, employer's liability, commercial general liability, and automobile liability, with specific coverage limits. Vendors must submit their quote through Collier County's e-Procurement Portal and comply with extensive insurance and indemnification provisions. The project appears to be funded potentially through FEMA, as indicated by a reference to "2026-076 FPP FEMA FY25" in the document attachments, suggesting this is part of hurricane recovery and reconstruction efforts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our County’s e-Procurement Portal, located at https://procurement.opengov.com/portal/collier-county-fl
COLLIER COUNTY
QUICK QUOTE
FOR
HURRICANE IAN REPAIRS - CLAM PASS EXTERIOR WALL
PAINTING
Michael Levy, Project Manager
Procurement Services Division
3335 Tamiami TRL E, Ste 101,Naples, FL, 34112 michael.levy@colliercountyfl.gov
(239) 252-4047
Quick Quote Title: Hurricane Ian Repairs - Clam Pass Exterior Wall Painting
Table Of Contents
1. QUICK QUOTE
2. INTRODUCTION
3. TERM
4. AWARD CRITERIA
5. SPECIFICATIONS/SCOPE OF WORK
6. INSURANCE REQUIREMENTS
7. PRICING PROPOSAL
8. VENDOR QUESTIONNAIRE
Attachments:
A - PO Terms and Conditions
B - Quick Quotes Instructions Version 1
C - 2026-076 FPP FEMA FY25 5.1.25
D - RFQ - Hurricane Ian Repairs - Clam Pass Exterior Wall Painting
E - Images
1. QUICK QUOTE
Hurricane Ian Repairs - Clam Pass Exterior Wall Painting
Release Project Date: October 23, 2025
Pre-Bid Meeting (Non-Mandatory): October 23, 2025, 10:30am
No pre-bid meeting
Question Submission Deadline: October 30, 2025, 3:00pm
Response Submission Deadline: November 6, 2025, 3:00pm
All quotes shall be submitted online via the Collier County Procurement Services Division Online
Bidding System: https://procurement.opengov.com/portal/collier-county-fl no later than the date and time specified above. We will not accept any quotation responses later than the noted time and date.
2. INTRODUCTION
The Facilities Management Division (hereinafter, the “Division or Department”) has issued this informal competition Quick Quote (hereinafter, “QQ”) with the intent of obtaining quotes from interested vendors in accordance with the terms, conditions and specifications stated or attached. The vendor, at a minimum, must achieve the requirements of the Specifications or Scope of Work stated.
3. TERM
The purchase order term, if an award is made is intended to be for a one-time purchase.
Prices shall remain firm for the term of the resultant purchase order.
NO EXCEPTIONS TO THE COUNTY’S PURCHASE ORDER TERMS AND CONDITIONS NOR A
VENDOR PROVIDED CONTRACT WILL BE ACCEPTED.
Surcharges will not be accepted in conjunction with this purchase order, and such charges should be incorporated into the pricing structure.
All goods are FOB destination and must be suitably packed and prepared to secure the lowest transportation rates and to comply with all carrier regulations. Risk of loss of any goods sold hereunder shall transfer to the COUNTY at the time and place of delivery; provided that risk of loss prior to actual receipt of the goods by the COUNTY nonetheless remain with VENDOR.
4. AWARD CRITERIA
https://procurement.opengov.com/portal/collier-county-fl
For the purposes of determining the winning quote, the County will select the responsive vendor with the lowest quote.
5. SPECIFICATIONS/SCOPE OF WORK
5.1. Hurricane Ian Repairs - Clam Pass Exterior Wall Painting
The contractor shall provide all labor, materials, equipment, and supervision necessary to complete the painting project.
The total estimated surface area to be painted is approximately 20,297 square feet.
The work shall include:
• Surface preparation, including cleaning and any necessary repairs to ensure a smooth, paintable surface.
o Cleaning: Pressure wash (Basic Routine Pressure Washing Services) or manually clean the entire surface to remove all dirt, oil, efflorescence (salt deposits), loose paint, mildew, and other foreign contaminants. Allow the surface to dry thoroughly.
o Patching/Repair: Contractor must ensure any non-structural hairline cracks or imperfections that are
1/8" or less are filled with an exterior-grade, flexible acrylic sealant, feathered smooth.
o Moisture Check: The moisture content of the concrete must be at an acceptable level (typically below 13% for acrylic topcoats) before primer application.
• Application of primer coat and two top/finish coats of paint to entire surface area of the wall.
• Deliver materials to site in unopened containers with manufacturers’ labels. Protect adjacent finishes and materials, prepare surfaces, and apply materials in strict accordance with manufacturers’ recommendations and instructions. Verify material compatibility with substrates.
• Apply paints only when temperature of surfaces to be painted and ambient air temperatures are between
50 and 95 deg F.
• Do not apply paints in snow, rain, fog, or mist; when relative humidity exceeds 85 percent; at temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.
• Contractor will need to coordinate with Facilities Management and Parks and Recreation for blocking off parking spots during the duration of the project.
• All materials and equipment must be safely stored and secured at the end of each working day.
3. Paint Specifications: All paint used on this project shall meet the following specifications:
• Primer coat: Sherwin-Williams Loxon® Concrete & Masonry Primer/Sealer or approved equivalent product.
• Coats 2 and 3: Sherwin-Williams “Superpaint”, Pro-Industrial Pre-Catalyzed
Water-Based Epoxy, Pro-Industrial Anti-Graffiti Coating, Industrial Enamel, Paint Shield Microbicidal Latex or approved equivalent product.
• Color shall be Sherwin Williams SW6106 or nearest equivalent.
4. Quote Submission: Please submit your quote in a format that clearly outlines the following:
• Total cost for the complete project, including all labor, materials, and equipment and markup (all inclusive)
5. Project timeline:
• Project to be completed within 120 days of the issuance of the PO.
• Project working hours are Monday – Friday – 7 am – 5 pm
6. INSURANCE REQUIREMENTS
6.1. Worker’s Compensation
Statutory Limits of Florida Statutes, Chapter 440 and all Federal Government Statutory Limits and
Requirements
Evidence of Workers’ Compensation coverage or a Certificate of Exemption issued by the State of Florida is required. Entities that are formed as Sole Proprietorships shall not be required to provide a proof of exemption.
An application for exemption can be obtained online at https://apps.fldfs.com/bocexempt/
6.2. Employer’s Liability
$500,000 single limit per occurrence
6.3. Commercial General Liability (Occurrence Form) patterned after the current ISO form
Bodily Injury and Property Damage
$1,000,000 single limit per occurrence, $2,000,000 aggregate for Bodily Injury Liability and Property Damage
Liability. This shall include Premises and Operations; Independent Contractors; Products and Completed
Operations and Contractual Liability.
6.4. Indemnification
To the maximum extent permitted by Florida law, the Contractor/Vendor shall defend, indemnify and hold harmless Collier County, its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys’ fees and paralegals’ fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Contractor/ Vendor or anyone employed or utilized by the Contractor/Vendor in the performance of this Agreement.
6.5. Automobile Liability
https://apps.fldfs.com/bocexempt/
$500,000 Each Occurrence; Bodily Injury & Property Damage, Owned/Non-owned/Hired; Automobile
Included
6.6. Additional Information
A. Vendor shall ensure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Vendor shall provide County with certificates of insurance meeting the required insurance provisions.
B. Collier County must be named as "ADDITIONAL INSURED" on the Insurance Certificate for
Commercial General Liability where required. This insurance shall be primary and non-contributory with respect to any other insurance maintained by, or available for the benefit of, the Additional Insured and the Vendor’s policy shall be endorsed accordingly.
C. The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of
County Commissioners in Collier County, OR Collier County Government, OR Collier County. The
Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read: For any and all work performed on behalf of Collier County.
D. On all certificates, the Certificate Holder must read: Collier County Board of Commissioners, 3295
Tamiami Trail East, Naples, FL 34112
E. Thirty (30) Days Cancellation Notice required.
F. Collier County shall procure and maintain Builders Risk Insurance on all construction projects where it is deemed necessary. Such coverage shall be endorsed to cover the interests of Collier County as well as the Contractor. Premiums shall be billed to the project and the Contractor shall not include Builders
Risk premiums in its project proposal or project billings. All questions regarding Builder’s Risk
Insurance will be addressed by the Collier County Risk Management Division.
G. Professional Services and/or Consulting Services may require professional liability insurance.
H. Environmental services, repairs, construction and/or hazardous materials projects may require pollution insurance.
7. PRICING PROPOSAL
Line Item Description Quantity Unit of
Measure Unit Cost Total
1 Exterior Precast Concrete Wall
Painting (see scope for specific details)
1 LS
TOTAL
8. VENDOR QUESTIONNAIRE
1. Vendor's Insurance Statement*
By confirming, we understand the insurance requirements of these specifications and that the evidence of insurability may be required within five (5) days of the award.
☐ Please confirm
*Response required
File details come from the government source that posted it. Updated .