QUESTION TECH/KTR QUESTION ANSWER

1 TECH

What does the US Government define as the “Port of Rotterdam”?

This includes all ports considered under the Ports of Rotterdam which may be utilized, as defined by the Port of Rotterdam infrastruture, refer to the following link:

https://www.portofrotterdam.com/en/our-port/facts-and-figures/facts-figures-about-the-port/port-infrastructure.

This contract is to be used for missions in/out of the Port of Rotterdam. This is not an requirement for All Ports Netherlands Contract.

2 TECH

Can the Government agree to a pre notice requirement if the space needed is greater than 20,000 sqmters?

Yes, the Government will provide as much advanced notice as possible for any additional space needed over 20k SQMTs .

3 TECH

Will the Government consider using the PLRS contract to ensure the correct terminal is used for the correct cargo?

As answered in question 1 above: This contract is to be used for missions in/out of the Ports of Rotterdam as defined in the link above. This is not an All Ports Netherlands requirement. The Government does not anticipate the use of the PRLS-E contract, but reserves the right to utilize all resources at its disposal.