QUESTION AND ANSWER ROUND TWO.pdf

PDF 274 KB Posted

Attached to
Ports of Alaska S&RTS
Solicitation number
HTC711-20-R-R018
Issued by

About this file

This document contains questions and answers from a second round of discussions regarding a federal solicitation for stevedoring and related terminal services at ports in Alaska. The solicitation seeks these services at the Ports of Alaska, Valdez, Seward, and Whittier. Several line items have been removed from the schedule of rates for all four port locations, as have lifting capacity requirements for mobile cranes. Amendments have been made to the performance work statement, schedule of rates, and technical worksheet documents. Offerors are instructed to submit proposals based on the most recent amended documents.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION AND ANSWER ROUND TWO

PORTS OF ALASKA S&RTS

HTC711-20-D-R-018

Question 1:

Port Gantry and or Mobile Container Cranes and Permanent Office Facilities are not available at all port locations, how should this be annotated in the Schedule of Rates (SOR)?

Answer 1:

The Government has removed several line items on the SOR, on all four port locations which are highlighted in green. As a reminder, if the Unit Price is yellow, a rate is expected to be provided for that particular line item on the SOR.

Question 2:

Mobile Cranes with the lifting capacity in the original Schedule of Rates are not available at all port locations, how should this be annotated in the Schedule of Rates?

Answer 2:

The Government has revised the lifting capacity requirements for mobile cranes at all four port locations. Changes are highlighted in green on the SOR.

The Government has amended the following three documents:

1. RFP Attachment 1 – PWS dated 10 Sep 2020

2. RFP Attachment 2 - SOR dated 10 Sep 2020

3. RFP Attachment 4 – Technical Worksheet dated 10 Sep 2020

All Offerors are requested to ensure proposal submissions are based on the most recent amended documents.