Universal Service Contract ‐ 8
| Milestone | Net | Workdays |
| Between | Dates Notes |
| OSD | Peer | Review | (Pre‐Solicitation | Issuance) 06‐Apr‐15 09‐Apr‐15 4.00 | ||||
| Senior | Leader | Review | of | Final | Requirements 27‐Apr‐15 06‐May‐15 8.00 | |||
| Written | Business | Clearance | ‐ | Solicitation | Issuance 07‐May‐15 12‐May‐15 4.00 | |||
| Issue | Final | RFP 13‐May‐15 13‐May‐15 1.00 | ||||||
| Pre‐Proposal | Conf 04‐Jun‐15 04‐Jun‐15 1.00 | |||||||
| Proposal | Closing | Date 13‐Jul‐15 13‐Jul‐15 1.00 | ||||||
| Contract | Compliance | Testing 14‐Jul‐15 27‐Oct‐15 76.00 | ||||||
| Proposal | Evaluations 14‐Jul‐15 30‐Jul‐15 13.00 | |||||||
| Request | EEOC | Clearance 30‐Jul‐15 30‐Jul‐15 1.00 | ||||||
| Discussions | with | Carriers 31‐Jul‐15 13‐Aug‐15 10.00 | ||||||
| Business | Clearance | Reviews | ‐ | Final | Proposal | Revisions | (TCAQ‐I, | |
| TCAQ‐P | and | TCJA) 14‐Aug‐15 27‐Aug‐15 10.00 |
Upload Documents for OSD Peer Review (Pre‐FPR) 28‐Aug‐15 28‐Aug‐15 1.00
| *Required | to | upload | documents | to | the |
| OSD | Peer | Review | portal | 3‐5 | business |
| days | prior | to | commencement | of | each |
| phase | of | the | Peer | Review |
| OSD | Peer | Review | (Pre‐FPR) 07‐Sep‐15 09‐Sep‐15 3.00 | |||||
| Written | Business | Clearance | ‐ | Final | Proposal | Revisions 11‐Sep‐15 11‐Sep‐15 1.00 | ||
| Request | Final | Proposal | Revisions 14‐Sep‐15 14‐Sep‐15 1.00 | |||||
| Receive | Final | Proposal | Revisions 17‐Sep‐15 17‐Sep‐15 1.00 | |||||
| FPR | Proposal | Evaluations 18‐Sep‐15 22‐Sep‐15 3.00 | ||||||
| Business | Clearance | Reviews | ‐ | Contract | Award | (TCAQ‐I, | TCAQ‐P | |
| and | TCJA) 23‐Sep‐15 06‐Oct‐15 10.00 | |||||||
| Theater | Business | Clearance | ‐ | Pre | Award 07‐Oct‐15 13‐Oct‐15 5.00 |
Upload Documents for OSD Peer Review (Pre‐Award) 14‐Oct‐15 14‐Oct‐15 1.00
| *Required | to | upload | documents | to | the |
| OSD | Peer | Review | portal | 3‐5 | business |
| days | prior | to | commencement | of | each |
| phase | of | the | Peer | Review |
| OSD | Peer | Review | (Pre‐Award) 21‐Oct‐15 23‐Oct‐15 3.00 | |||||
| Written | Business | Clearance | ‐ | Contract | Award 26‐Oct‐15 26‐Oct‐15 1.00 | |||
| Congressional | Notification | (1279 | report) 26‐Oct‐15 28‐Oct‐15 3.00 | |||||
| Award | Contract 28‐Oct‐15 28‐Oct‐15 1.00 | |||||||
| Conduct | Debriefings 29‐Oct‐15 04‐Nov‐15 5.00 | |||||||
| Booking | Period | (45 | Days | Prior | to | Contract | Start | Date) 28‐Oct‐15 01‐Dec‐15 25.00 |
| USC‐8 | Contract | Start 01‐Dec‐15 01‐Dec‐15 0.00 |