USC-8_Milestones_28JAN15.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Universal Service Contract-8 (USC-8) Federal contract opportunity
Solicitation number
HTC711-15-R-W002
Issued by
Department of Defense United States Transportation Command

About this file

USC-8 Milestones

View the file

Other files for this federal contract opportunity

Other files attached to Universal Service Contract-8 (USC-8), newest first.
File Type Posted
HTC711-15-R-W002-0008.pdf PDF
HTC711-15-R-W002-0007.pdf PDF
HTC711-15-R-W002-0006.pdf PDF
HTC711-15-R-W002_Amendment_5.pdf PDF
New_CLINs_posted_22_July_15.pdf PDF
Deleted_and_Added_CLINs_17_Jul_15_(posted_21_Jul_15).pdf PDF
Added_CLINs_13_Jul_15_(posted_13_Jul_15).pdf PDF
HTC711-15-R-W002-0004.pdf PDF
Added_CLINS_7_July_15_(posted_9_July_15).pdf PDF
new_CLINs_July_1.pdf PDF
HTC711-15-R-W002-0003.pdf PDF
USC-8_Pre-Proprosal_(Att_2).pdf PDF
Pre-Proposal_Meeting_Minutes.pdf PDF
USC-8_Pre-Proposal_(Att_1).pdf PDF
BAF_Baselines.xlsx XLSX spreadsheet
HTC711-15-R-W002-0002.pdf PDF
USC8_Q As_26_Jun_15.pdf PDF
USC8_RFP_Questions_(23_JUN_15).pdf PDF
HTC711-15-R-W002-0001.pdf PDF
USC-8_Draft_RFP_Q As_(FBO_Posting-26May15).pdf PDF
USC-8_RFP_Q As_(26_May_15).pdf PDF
USC-8_RFP_Questions.xlsx XLSX spreadsheet
USC-8_RFP_HTC711-15-R-W002_(13MAY15).pdf PDF
USC-8_Milestones_7MAY15.pdf PDF
USC-8_Industry_Day__19_Feb_15_.pdf PDF
Draft_Readiness_Language.pdf PDF
USC-8_Exhibit_2_Additional_Clauses_DRAFT_Dec_14.pdf PDF
USC-8_Att_8_DLA_Prime_Vendor_DRAFT_Dec_14.pdf PDF
USC-8_PWS_Att_3_Rate_Rules_DRAFT_Dec_14.pdf PDF
USC-8_PWS_Att_5_Route_Info_DRAFT_Dec_2014.pdf PDF
USC-8_PWS_DRAFT_Dec_14.pdf PDF
FINAL_Industry_Day_Agenda_Feb_15x.pdf PDF
USC-8_RFP_DRAFT_Dec_14.pdf PDF
USC-8_Att_1_EDI_Reports_DRAFT_Dec_14.pdf PDF
USC-8_Att_7_EPAs_DRAFT_Dec_2014.pdf PDF
USC-8_PWS_Contingency_Annex_DRAFT_Dec_2014.pdf PDF
USC-8_Exhibit_4_Ordering_Procedure_DRAFT_Dec_14.pdf PDF
USC-8_Att_6_Invoicing_and_Payment_DRAFT_Nov_14.pdf PDF
USC-8_Att_2_Operational_Reports_Dec_2014.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milestones

MilestoneProposed MilestonesNet Workdays Between Dates
Column1Column4
Start Market Research0.00
Request Inputs from Industry & Gov’t Stakeholders0.00
Brief Director, TCAQ on Issues Matrix0.00
Brief SDDC, DCG on Issues Matrix0.00
Brief USTC Senior Leaders on Major Issues0.00
Complete 1st Draft RFP0.00
IPT Meeting #1 (Gov & Industry)0.00
IPT Meeting #2 (Gov & Industry)0.00
I-SAW0.00
Issue Draft RFP0.00
Issue Synopsis0.00
SAW Pt 20.00
Industry Engagement II0.00
Pre-Acquisition Strategy Panel (J3, J5/4, JA, J8, G8, AQ-P)20-Jan-1520-Jan-151.00
Acquisition Strategy Panel23-Jan-1523-Jan-151.00
Acquisition Plan Approval23-Jan-1523-Jan-151.00
Upload Documents for OSD Acquisition of Services Review29-Jan-1529-Jan-151.00*Required to upload documents a minimum of 30 days prior to OSD Briefing
OSD Briefing/Clearance (Acq of Services)02-Mar-1502-Mar-151.00
Business Clearance Reviews - Solicitation Issuance (TCAQ-I, TCAQ-P and TCJA)04-Mar-1512-Mar-157.00
Theater Business Clearance - Pre Solicitation13-Mar-1520-Mar-156.00
Upload Documents for OSD Peer Review23-Mar-1523-Mar-151.00*Required to upload documents to the OSD Peer Review portal 3-5 business days prior to commencement of each phase of the Peer Review
OSD Peer Review (Pre-Solicitation Issuance)31-Mar-1502-Apr-153.00
Written Business Clearance - Solicitation Issuance07-Apr-1507-Apr-151.00
Issue Final RFP13-Apr-1513-Apr-151.00
Pre-Proposal Conf04-May-1504-May-151.00
Proposal Closing Date12-Jun-1512-Jun-151.00
Contract Compliance Testing15-Jun-1523-Sep-1573.00
Proposal Evaluations15-Jun-1529-Jun-1511.00
Request EEOC Clearance29-Jun-1529-Jun-151.00
Discussions with Carriers30-Jun-1513-Jul-1510.00
Business Clearance Reviews - Final Proposal Revisions (TCAQ-I, TCAQ-P and TCJA)14-Jul-1527-Jul-1510.00
Upload Documents for OSD Peer Review (Pre-FPR)28-Jul-1528-Jul-151.00*Required to upload documents to the OSD Peer Review portal 3-5 business days prior to commencement of each phase of the Peer Review
OSD Peer Review (Pre-FPR)04-Aug-1506-Aug-153.00
Written Business Clearance - Final Proposal Revisions09-Aug-1509-Aug-150.00
Request Final Proposal Revisions10-Aug-1510-Aug-151.00
Receive Final Proposal Revisions13-Aug-1513-Aug-151.00
FPR Proposal Evaluations14-Aug-1518-Aug-153.00
Business Clearance Reviews - Contract Award (TCAQ-I, TCAQ-P and TCJA)19-Aug-1501-Sep-1510.00
Theater Business Clearance - Pre Award02-Sep-1508-Sep-155.00
Upload Documents for OSD Peer Review (Pre-Award)09-Sep-1509-Sep-151.00*Required to upload documents to the OSD Peer Review portal 3-5 business days prior to commencement of each phase of the Peer Review
OSD Peer Review (Pre-Award)16-Sep-1518-Sep-153.00
Written Business Clearance - Contract Award21-Sep-1521-Sep-151.00
Congressional Notification (1279 report)21-Sep-1523-Sep-153.00
Award Contract23-Sep-1523-Sep-151.00
Conduct Debriefings24-Sep-1530-Sep-155.00
Booking Period (45 Days Prior to Contract Start Date)23-Sep-1501-Nov-1528.00
USC-8 Contract Start01-Nov-1501-Nov-150.00
Contract Completion Date