HSFE20-14-R-0001_-_Questions_and_Answers___4.docx

DOCX document 20 KB Posted

Attached to
Integrated Facilities Operation and Maintenance Services Federal contract opportunity
Solicitation number
HSFE20-14-R-0001
Issued by
Federal Emergency Management Agency Preparedness Section

About this file

Questions and Answers 4

View the file

Other files for this federal contract opportunity

Other files attached to Integrated Facilities Operation and Maintenance Services, newest first.
File Type Posted
Attachment_A_PWS_1-8-14.pdf PDF
HSFE20-14-R-0001_A00006.pdf PDF
HSFE20-14-R-0001_A00005.pdf PDF
HSFE20-14-R-0001_A00004.pdf PDF
HSFE20-14-R-0001_-_Questions_and_Answers___3.docx DOCX document
Attachment_C_Site_Characteristics _Maps_and_Floor_Plans.pdf PDF
HSFE20-14-R-0001_A00003.pdf PDF
Attachment_S_-_Annual_WOs__Lodging_Occupants.pdf PDF
Attachment_T_-_Custodial_Schedule.pdf PDF
HSFE20-14-R-0001_-_Questions_and_Answers___2.docx DOCX document
Attachment_A_PWS_12-30-13.pdf PDF
HSFE20-14-R-0001_-_Questions_and_Answers___1.docx DOCX document
HSFE20-14-R-0001_A00002.pdf PDF
HSFE20-14-R-0001_-_FOSS_Site_Visit_List_12-12-13.docx DOCX document
HSFE20-14-R-0001_Amendment_A00001.pdf PDF
HSFE20-14-R-0001_RFP_Attachments_Nov_27_2013.pdf PDF
Attachment_Q_Cost_Proposal_Form_FINAL.xls XLS spreadsheet
HSFE20-14-R-0001_RFP_Nov_27_2013_FINAL.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP # HSFE20-14-R-0001 – CDP Facility Operations and Support Services Questions and Answers # 4 – Follow-Up Responses to Previous Q&A # 2 The Government’s responses to questions are provided below highlighted in yellow:

From Questions and Answers # 2

48. IRT SOW 7.21, ATM Machine, Contractor will maintain an anytime teller type cash machine at the hospitality hall and registration area. Is this requirement to provide one single machine? One single machine at each required location.

Who holds the service agreement with the bank?

Contractor

134. Reference: PWS, Paragraph 7.10.1 Locksmith, Page 45, Attachment A Questions: (1) Since locksmith certification is not required, please confirm that the contractor will not be responsible for any master key system design or development of key symbols.

Will the government answer this question?

The CDP Security services contractor (currently G4S) is responsible for master key system design and development of key symbols.

145. Reference: PWS, Paragraph 7.21 ATM Machine, Page 60, Attachment A Question: Who furnishes the ATM Machine? Local Bank. Who is responsible for supplying the funds for the ATM? Local Bank. Who is responsible for collecting the funds at the end of the day? Local Bank.

What bank is currently used and who holds the service agreement contract with the bank?

Fort McClellan Federal Credit Union – Current FOSS Contractor

161. Reference: PWS, Paragraph 7.17.3.2 – Pick-up and delivery of Mail Question: Please provide the number of locations that require daily mail pickup and delivery? Post Office; one (1) location at Lodging Area; one (1) location at bldg. 61; one (1) location at bldg. 490.

How many pick-ups and deliveries are made on a daily basis?

Two (2) times each business day