Amendment 0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract Boston Waterfront.pdf | ||
| Abstract Boston Waterfront.xls | XLS spreadsheet | |
| Amendment0004BostonWaterfrontRepairs.pdf | ||
| PAGE 3 OF SECTION 09 97 13.26 WITH REVISIONS.pdf | ||
| 01 50 00 Temporary Facilities.pdf | ||
| Amendment0002BostonWaterfrontRepairs.pdf | ||
| Amendment0001BostonWaterfrontRepairs.pdf | ||
| P2255035DwgB.PDF | ||
| P2255035DwgC.PDF | ||
| P2255035DwgD.PDF | ||
| BSU Boston waterfront wage rates.pdf | ||
| IFB BSU Boston Waterfront Repair Solicitation.pdf | ||
| P2255035DwgE.PDF | ||
| P2255035DwgA.PDF | ||
| P2255035Spc.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
07/27/2011
4. REQUISITION/PURCHASE REQ.
2111G11PRV090
5. PROJECT NO. (If applicable)
2255035
6. ISSUED BY CODE 51283 7. ADMINISTERED BY (If other than Item 6) CODE 51283
Contracting Officer USCG Civil Engineering Unit Providence 300 Metro Center Blvd.
Warwick, RI 02886-1747
Contracting Officer USCG Civil Engineering Unit Providence 300 Metro Center Blvd.
Warwick, RI 02886-1747
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
TO ALL BIDDERS
(AMENDMENT MUST BE ACKNOWLEDGED)
9A. AMENDMENT OF SOLICITATION NO.
HSCGG1-11-B-PRV090
9B. DATED (SEE ITEM 11)
08 JULY 2011
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The solicitation referenced in Block #9A is hereby amended to answer technical questions and revise the specifications as described on the following page:
The due date for submission of Bids is extended as a result of this amendment. Bids are due by 02:00 PM EST on August 12, 2011.
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Gerald Fortin
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
This solicitation is amended to answer technical questions as follows:
QUESTION 1: As identified on the title page of the Sol there is language that states all relevant taxes are applicable to the project as no Tax Exempt Certificate will be provided. Please confirm the project is a taxable project for materials incorporated in the repairs?
ANSWER 1: This is correct. A tax exempt number will NOT be provided under this contract.
QUESTION 2: On page 4 Section B, B.1 Scope of Construction Services: A reference is made to the contractor obtaining and providing the Boston Conservation Commission Order of Conditions for this work. In the contract specification final section the Order of Conditions for the project is attached. Please confirm what if any additional permits are the contractors responsibility as it appears the order of conditions has been obtained already.
ANSWER 2: Please note that the Order of Conditions in Appendix A of the specifications is an EXAMPLE and that Clause 52.236-7, Permits and Responsibilities, in Section I of the Solicitation states that the contractor is responsible for obtaining all permits and licenses necessary to perform the work. Specification Section 01 57 20.00 10 3.1 ENVIRONMENTAL PERMITS AND COMMITMENTS is hereby deleted and replaced with the following: “The contractor is responsible for identifying and obtaining all permits and licenses necessary to perform the work, including the Boston Conservation Commission Order of Conditions.”
QUESTION 3: Is Freshwater available to the contractor on site for their operations?
ANSWER 3: Specification Section 01 50 00, TEMPORARY FACILITIES AND CONTROLS, is attached to this Amendment and incorporated into the solicitation. See Section 01 50 00 1.4.2 in regards to the above question.
QUESTION 4: Please confirm that as per notes on sheet 2 of 16, GROUT FILL; that 5000 psi grout is specified to placed in the voids which abut the sheetpile bulkhead? No Details are provided to R&R any asphalt to access these voids either, please provide detail or section for asphalt replacement. We have read the section in addendum #2 regarding the grout fill and that language does not address the 5000 psi issue.
ANSWER 4: See sheet 16, Detail A1, Void Repair Note #1.
QUESTION 5: The pipe piles to be blasted and coated under Pier #2 possess cross and diagonal pipe bracing; can the contractor remove specific sections of cross bracing to allow for blasting and painting containment and access which will be re-installed immediately upon completion?
ANSWER 5: Means and methods are not specified and are the contractor’s responsibility.
ATTACHMENT: SPECIFICATION SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS