01 50 00 Temporary Facilities.pdf
PDF 29 KB Posted
- Attached to
- USCG BSU Boston Waterfront Repairs Federal contract opportunity
- Solicitation number
- HSCGG1-11-B-PRV090
About this file
Attachment to Amendment 0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract Boston Waterfront.pdf | ||
| Abstract Boston Waterfront.xls | XLS spreadsheet | |
| Amendment0004BostonWaterfrontRepairs.pdf | ||
| PAGE 3 OF SECTION 09 97 13.26 WITH REVISIONS.pdf | ||
| Amendment0003BostonWaterfrontRepairs.pdf | ||
| Amendment0002BostonWaterfrontRepairs.pdf | ||
| Amendment0001BostonWaterfrontRepairs.pdf | ||
| P2255035DwgB.PDF | ||
| P2255035DwgC.PDF | ||
| P2255035DwgE.PDF | ||
| P2255035DwgA.PDF | ||
| P2255035Spc.pdf | ||
| P2255035DwgD.PDF | ||
| BSU Boston waterfront wage rates.pdf | ||
| IFB BSU Boston Waterfront Repair Solicitation.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Waterfront Repairs, Coast Guard BSU Boston PSN 2255035
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
5/10
1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
FEDERAL HIGHWAY ADMINISTRATION (FHWA)
FHWA MUTCD (1988) Manual on Uniform Traffic Control
Devices
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (1999) National Electrical Code
NFPA 241 (1996) Safeguarding Construction, Alteration, and Demolition Operations
1. S2
UBMITTALS
Submit the following in accordance with Section 01 33 00, "Submittal Procedures."
SD-01 Preconstruction Submittals
Traffic control plan
Construction site plan
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit a site plan showing the locations of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes used for this contract. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 TEMPORARY UTILITIES
1.4.1 Contractor Utilities
The Contractor shall provide his own utilities.
1.4.2 Utilities at Special Locations
When and if necessary, connections to base fire hydrants shall be coordinated with the Contracting Officer and BSU Boston. Connections shall be made in accordance with the Boston water and Sewer Commission, Water Use
Section 01 50 00 Page 1
Regulations, adopted December 21, 2000, Section 7. Connections shall be checked daily for leaks. At the end of the work day the contractor shall insure that the water hydrant is charged and available for use in the event of a fire; remove the connection if necessary on a daily basis to insure hat the hydrant remains operational. t
1.5 WEATHER PROTECTION
Take immediate actions when rain or other detrimental weather is imminent, and at the end of each workday, to insure that installed work is protected and that equipment, tools, boats, barges, vehicles, and material are secure and able to withstand inclement weather.
1.5.1 Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions shall include, but are not limited to, removing/securing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work.
1.6 STATION OPERATION EFFECTS ON CONTRACTOR OPERATIONS
1.6.1 Interruption of Vehicular Traffic
If during the performance of work, it becomes necessary to modify vehicular traffic patterns at any locations, notify the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic.
1. T7
EMPORARY SANITARY FACILITIES
Provide adequate sanitary conveniences of a type approved for the use of persons employed on the work, properly secluded from public observation, and maintained in such a manner as required and approved by the Contracting Officer. Maintain these conveniences at all times without nuisance. Upon completion of the work, remove the conveniences from the premises, leaving the premises clean and free from nuisance. Include provisions for pest control and elimination of odors.
1.7.1 Maintenance of Temporary Facilities
Suitably paint and maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.
1.7.2 Trailers or Storage Buildings
Trailers or storage buildings will be permitted, where space is available, subject to the approval of the Contracting Officer. The trailers or buildings shall be in good condition, free from visible damage rust and deterioration, and meet all applicable safety requirements. Trailers shall be roadworthy and comply with all appropriate state and local vehicle requirements. Failure to maintain storage trailers or buildings to these standards shall result in the removal of non-complying units at the Contractor's expense. A sign not smaller than 24 by 24 inches shall be
Section 01 50 00 Page 2
Section 01 50 00 Page 3 conspicuously placed on the trailer depicting the company name, business phone number, and emergency phone number. Trailers shall be anchored to resist high winds and must meet applicable state of local standards for anchoring mobile trailers.
2 PRODUCTS
Not Used.
3 EXECUTION
3.1 TEMPORARY PHYSICAL CONTROLS
3.1.1 Access Controls
3.1.1.1 Temporary Barricades
Contractor shall provide for barricading around all work areas to prevent public access.
3.1.1.2 Fencing
Fencing shall be provided to control access to the work area(s) by unauthorized people. Fencing must be installed to be able to restrain a force of at least 250 pounds against it.
3.1.1.3 Signs
Place warning signs at the construction area perimeter designating the presence of construction hazards requiring unauthorized persons to keep out.
Signs must be placed on all sides of the project, with at least one sign every 300 feet. All points of entry shall have signs designating the construction site as a hard hat area.
3.2 TEMPORARY WIRING
Provide temporary wiring in accordance with NFPA 241 and NFPA 70, Article 305-6(b), Assured Equipment Grounding Conductor Program. Program shall include frequent inspection of all equipment and apparatus.
--End of Section--
| 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.4 TEMPORARY UTILITIES |
| 1.4.1 Contractor Utilities |
| 1.4.2 Utilities at Special Locations |
| 1.5 WEATHER PROTECTION |
| 1.5.1 Storm Protection |
| 1.6 STATION OPERATION EFFECTS ON CONTRACTOR OPERATIONS |
| 1.6.1 Interruption of Vehicular Traffic |
| 1.7 TEMPORARY SANITARY FACILITIES |
| 1.7.1 Maintenance of Temporary Facilities |
| 1.7.2 Trailers or Storage Buildings |
| 2 PRODUCTS |
| 3 EXECUTION |
| 3.1 TEMPORARY PHYSICAL CONTROLS |
| 3.1.1 Access Controls |
| 3.1.1.1 Temporary Barricades |
| 3.1.1.2 Fencing |
| 3.1.1.3 Signs |
3.2 TEMPORARY WIRING