Amendment 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract Boston Waterfront.pdf | ||
| Abstract Boston Waterfront.xls | XLS spreadsheet | |
| Amendment0004BostonWaterfrontRepairs.pdf | ||
| PAGE 3 OF SECTION 09 97 13.26 WITH REVISIONS.pdf | ||
| Amendment0003BostonWaterfrontRepairs.pdf | ||
| 01 50 00 Temporary Facilities.pdf | ||
| Amendment0001BostonWaterfrontRepairs.pdf | ||
| P2255035DwgB.PDF | ||
| P2255035DwgC.PDF | ||
| P2255035DwgD.PDF | ||
| BSU Boston waterfront wage rates.pdf | ||
| IFB BSU Boston Waterfront Repair Solicitation.pdf | ||
| P2255035DwgE.PDF | ||
| P2255035DwgA.PDF | ||
| P2255035Spc.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
07/25/2011
4. REQUISITION/PURCHASE REQ.
2111G11PRV090
5. PROJECT NO. (If applicable)
2255035
6. ISSUED BY CODE 51283 7. ADMINISTERED BY (If other than Item 6) CODE 51283
Contracting Officer USCG Civil Engineering Unit Providence 300 Metro Center Blvd.
Warwick, RI 02886-1747
Contracting Officer USCG Civil Engineering Unit Providence 300 Metro Center Blvd.
Warwick, RI 02886-1747
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
TO ALL BIDDERS
(AMENDMENT MUST BE ACKNOWLEDGED)
9A. AMENDMENT OF SOLICITATION NO.
HSCGG1-11-B-PRV090
9B. DATED (SEE ITEM 11)
08 JULY 2011
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The solicitation referenced in Block #9A is hereby amended to answer technical questions and revise the specifications as described on the following page:
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. The due date for submission of Bids is NOT extended as a result of this amendment. Bids remain due by 02:00 PM EST on August 09, 2011.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Gerald Fortin
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
This solicitation is amended to answer technical questions as follows:
QUESTION 1: It appears that the estimated qty. ( 8250 BF ) of timber fender system shown on sheet 2 of 16 is significantly higher than the actual qty. required to replace the fender system as detailed on plan sheet 3 of 16. Please clarify the discrepancy.
ANSWER 1: Delete bulkhead and Pier 2 quantities shown in Notes on Sheet 2 of 16 of the drawings; Quantities listed shall not be used for bidding purposes. Bidders shall calculate the quantities required to perform all work necessary to comply with solicitation plans and specifications.
QUESTION 2: Grout Fill - Sheet #2 notes for grout fill does not specify products recommended for this use nor a product listed on the qualified construction materials list of Mass DOT. Please advise.
ANSWER 2: On Sheet 2 of 16 under the notes for Grout Fill, add the following note 4: Grout shall be a product specifically produced for filling voids under pavement using the means and methods as selected by the contractor. Submit to the Contracting Officer the manufacturers product literature and installation instructions. The Submittal Register for Specification Section 01 33 00, shall include this as a preconstruction submittal for "Grout".
QUESTION 3: Sheet 14 notes wale splice connection at bent 18.5 requires a connection to existing steel fabricated member and references photo A-3. Photo A-3 is unclear as to what is required for this connection. Please advise.
ANSWER 3: The splice connection referenced is the connection at the interface of the new wale and wale remaining in-place (See Sheet 3 of 16, Detail A1 Pier 2 Framing Plan). Detail A3 on sheet 13 is a plan view of this butt type connection. The "steel fabricated member" is the existing butt connection.
QUESTION 4: Timber - Sheet #2 notes and the Pier Timberwork specification does not specify whether it is rough or dressed timber – Please advise.
ANSWER 4: See Specification Section 06 13 33, paragraph 2.1.1.1.
ADDITIONAL CHANGES TO SPECIFICATIONS:
1. Section 31 62 19.13, 2.1.1: Change “14 inches” to “44 inches” in last sentence to read: Minimum pile circumferences measured at 3 feet from the butt end shall be 44 inches.
2. Section 31 62 19.13, 3.1.1.1, line 8: Change pile length from “60-foot” to “65-foot” to read: It is the design intent to drive timber piles to full 65-foot length without shortening.